PREPARING ROW
|
STA
|
5.000
|
$3,500.000
|
$3,000.000
|
$3,500.000
|
$3,250.000
|
$1,000.000
|
$6,000.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
7,126.000
|
$10.000
|
$11.000
|
$16.000
|
$14.000
|
$10.000
|
$15.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
15,654.000
|
$15.000
|
$14.000
|
$22.000
|
$24.000
|
$15.000
|
$29.500
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
77,738.000
|
$1.200
|
$1.000
|
$1.060
|
$1.110
|
$1.140
|
$1.150
|
|
|
BLOCK SODDING
|
SY
|
2,640.000
|
$4.000
|
$4.900
|
$3.850
|
$5.530
|
$4.150
|
$5.750
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
38,869.000
|
$0.100
|
$0.110
|
$0.190
|
$0.070
|
$0.210
|
$0.070
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
38,869.000
|
$0.100
|
$0.110
|
$0.190
|
$0.090
|
$0.210
|
$0.090
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
77,738.000
|
$0.300
|
$0.090
|
$0.150
|
$0.100
|
$0.170
|
$0.100
|
|
|
VEGETATIVE WATERING
|
MG
|
657.000
|
$20.000
|
$15.000
|
$32.000
|
$36.000
|
$25.920
|
$27.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY D)
|
SY
|
8,765.000
|
$2.500
|
$1.100
|
$0.940
|
$1.950
|
$1.020
|
$2.050
|
|
|
CEMENT
|
TON
|
420.000
|
$180.000
|
$170.000
|
$181.000
|
$190.000
|
$158.310
|
$165.000
|
|
|
CEMENT TREAT(EXIST MATL)(8")
|
SY
|
38,869.000
|
$4.200
|
$3.000
|
$2.700
|
$4.810
|
$1.760
|
$3.100
|
|
|
PRIME COAT (MC-30)
|
GAL
|
9,721.000
|
$6.000
|
$4.500
|
$4.850
|
$6.330
|
$5.450
|
$4.250
|
|
|
ASPH (AC-20-5TR)
|
GAL
|
38,481.000
|
$4.500
|
$3.200
|
$3.450
|
$4.210
|
$4.000
|
$3.250
|
|
|
AGGR(TY-PE GR-4 SAC-B)
|
CY
|
891.000
|
$115.000
|
$100.000
|
$140.000
|
$147.380
|
$95.000
|
$140.000
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
|
TON
|
14,968.000
|
$130.000
|
$103.000
|
$106.000
|
$104.000
|
$132.500
|
$110.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
2,917.000
|
$45.000
|
$55.000
|
$32.000
|
$31.000
|
$7.400
|
$48.500
|
|
|
FLEX PAVEMENT STRUCTURE REPAIR (2.5")
|
SY
|
1,494.000
|
$30.000
|
$28.000
|
$35.000
|
$16.000
|
$7.400
|
$50.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
1,244.000
|
$1.500
|
$3.500
|
$7.020
|
$6.000
|
$7.400
|
$11.000
|
|
|
CMP (GAL STL 18 IN)
|
LF
|
135.000
|
$50.000
|
$50.000
|
$65.000
|
$78.960
|
$50.400
|
$52.500
|
|
|
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
|
LF
|
58.000
|
$650.000
|
$530.000
|
$375.000
|
$421.090
|
$525.000
|
$550.000
|
|
|
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
|
LF
|
62.000
|
$800.000
|
$580.000
|
$650.000
|
$736.910
|
$577.500
|
$605.000
|
|
|
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
|
LF
|
25.000
|
$1,000.000
|
$820.000
|
$750.000
|
$842.190
|
$813.750
|
$850.000
|
|
|
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
|
LF
|
66.000
|
$1,200.000
|
$850.000
|
$675.000
|
$847.450
|
$840.000
|
$875.000
|
|
|
WINGWALL (PW - 2) (HW=3 FT)
|
EA
|
4.000
|
$8,000.000
|
$4,800.000
|
$4,000.000
|
$4,737.310
|
$4,725.000
|
$4,900.000
|
|
|
WINGWALL (PW - 2) (HW=4 FT)
|
EA
|
2.000
|
$11,000.000
|
$6,900.000
|
$5,700.000
|
$6,316.410
|
$6,825.000
|
$7,100.000
|
|
|
WINGWALL (PW - 2) (HW=5 FT)
|
EA
|
4.000
|
$13,000.000
|
$9,000.000
|
$7,500.000
|
$8,421.880
|
$8,925.000
|
$9,300.000
|
|
|
SET (TY II) (18 IN) (CMP) (6: 1) (P)
|
EA
|
10.000
|
$1,000.000
|
$1,100.000
|
$1,200.000
|
$1,473.830
|
$1,050.000
|
$1,100.000
|
|
|
REMOV STR (SET)
|
EA
|
10.000
|
$500.000
|
$1,300.000
|
$250.000
|
$263.180
|
$1,260.000
|
$1,300.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
10.000
|
$1,500.000
|
$2,200.000
|
$800.000
|
$842.190
|
$2,100.000
|
$2,200.000
|
|
|
REMOV STR (PIPE)
|
LF
|
125.000
|
$20.000
|
$37.000
|
$15.000
|
$26.320
|
$36.750
|
$38.500
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$489,141.560
|
$420,000.000
|
$415,000.000
|
$490,000.000
|
$401,260.060
|
$540,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$10,000.000
|
$9,000.000
|
$25,250.000
|
$3,500.000
|
$990.000
|
$17,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
160.000
|
$30.000
|
$29.000
|
$27.940
|
$46.320
|
$30.180
|
$48.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
160.000
|
$1.000
|
$15.000
|
$9.740
|
$18.950
|
$10.520
|
$19.500
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
9,580.000
|
$2.500
|
$2.100
|
$2.000
|
$2.050
|
$2.160
|
$2.150
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
9,580.000
|
$1.000
|
$0.550
|
$0.480
|
$1.050
|
$0.520
|
$1.100
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
1,320.000
|
$4.000
|
$2.100
|
$2.940
|
$3.110
|
$3.180
|
$3.250
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,320.000
|
$1.000
|
$0.550
|
$0.940
|
$0.790
|
$1.010
|
$0.820
|
|
|
DRIVEWAYS (CONC)
|
SY
|
180.000
|
$90.000
|
$150.000
|
$110.000
|
$70.630
|
$141.750
|
$150.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
661.000
|
$50.000
|
$40.000
|
$35.000
|
$45.730
|
$60.000
|
$74.500
|
|
|
TURNOUTS (ACP)
|
SY
|
33.000
|
$50.000
|
$50.000
|
$100.000
|
$46.330
|
$35.000
|
$81.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
43,729.000
|
$0.200
|
$0.230
|
$0.260
|
$0.240
|
$0.110
|
$0.290
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
26,665.000
|
$0.250
|
$0.250
|
$0.260
|
$0.330
|
$0.160
|
$0.290
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
1.000
|
$500.000
|
$360.000
|
$344.000
|
$263.180
|
$361.200
|
$375.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
2.000
|
$700.000
|
$700.000
|
$657.000
|
$631.640
|
$689.850
|
$720.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
1.000
|
$800.000
|
$880.000
|
$838.000
|
$1,052.730
|
$879.900
|
$920.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
8.000
|
$500.000
|
$550.000
|
$523.000
|
$473.730
|
$549.150
|
$575.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
3.000
|
$500.000
|
$570.000
|
$540.000
|
$447.410
|
$567.000
|
$590.000
|
|
|
RELOCATE SM RD SN SUP&AM TY TWT
|
EA
|
1.000
|
$350.000
|
$510.000
|
$480.000
|
$315.820
|
$504.000
|
$525.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
14.000
|
$80.000
|
$95.000
|
$90.000
|
$263.180
|
$94.500
|
$98.500
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
26.000
|
$80.000
|
$110.000
|
$100.000
|
$94.750
|
$105.000
|
$110.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,388.000
|
$0.800
|
$0.650
|
$1.500
|
$1.130
|
$0.750
|
$1.350
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
3,860.000
|
$0.800
|
$0.650
|
$1.300
|
$1.130
|
$0.750
|
$1.350
|
|
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
|
LF
|
665.000
|
$0.700
|
$1.800
|
$1.720
|
$1.320
|
$1.080
|
$1.100
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
43,278.000
|
$0.150
|
$0.170
|
$0.160
|
$0.160
|
$0.160
|
$0.160
|
|
REFL PAV MRK TY II (Y) 4" (BRK)
|
LF
|
75.000
|
$0.150
|
$1.050
|
$1.000
|
$0.160
|
$1.080
|
$1.100
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
130,678.000
|
$0.150
|
$0.170
|
$0.160
|
$0.160
|
$0.160
|
$0.160
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
3,270.000
|
$0.300
|
$0.460
|
$0.440
|
$0.530
|
$0.540
|
$0.550
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
43,728.000
|
$0.300
|
$0.380
|
$0.360
|
$0.470
|
$0.450
|
$0.460
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
75.000
|
$0.300
|
$1.050
|
$1.000
|
$0.420
|
$1.080
|
$1.100
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
52,388.000
|
$0.300
|
$0.400
|
$0.370
|
$0.470
|
$0.450
|
$0.460
|
|
PREFAB PAV MRK TY C (W) (LNDP ARROW)
|
EA
|
4.000
|
$500.000
|
$500.000
|
$455.000
|
$463.200
|
$324.000
|
$330.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
165.000
|
$2.600
|
$3.900
|
$3.650
|
$5.260
|
$3.670
|
$3.750
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,311.000
|
$2.600
|
$3.900
|
$3.650
|
$3.680
|
$3.670
|
$3.750
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
1,640.000
|
$2.000
|
$2.000
|
$1.850
|
$2.110
|
$2.160
|
$2.200
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
12,025.000
|
$90.000
|
$76.000
|
$65.000
|
$71.000
|
$98.000
|
$77.000
|
|
|
BONDING COURSE
|
GAL
|
10,351.000
|
$4.500
|
$2.800
|
$3.800
|
$4.280
|
$2.900
|
$2.900
|
|
|
TMA (STATIONARY)
|
DAY
|
178.000
|
$200.000
|
$200.000
|
$275.000
|
$246.360
|
$166.280
|
$205.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
20.000
|
$360.000
|
$200.000
|
$600.000
|
$1,356.830
|
$366.280
|
$985.000
|
|
Totals: |
$5,500,557.160
|
$4,616,373.180
|
$4,861,679.420
|
$4,916,417.840
|
$5,056,348.760
|
$5,396,451.870
|