BASTROP VARIOUS (0914-18-130)

Items: 24

County: BASTROP
Length: 0.0000 MILES
Highway: VARIOUS
District: AUSTIN
Control Number: 0914-18-130
DBE Goal: 0.0%
Project: F 2026(903)
Guaranty: $7,000.00
Time: 59 WORKING DAYS
Engineer's Estimate: $355,991.98
Date: 08/06/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263244
Type: LANDSCAPE DEVELOPMENT
Project ID: A00217764
Contract Type: FEDERAL
Project Description: FY 2026 BAAO GREEN RIBBON
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 2 files available
Bidders (8)
E
Engineer's Estimate
$355,991.98
Over/Under Est: -37.07% -$131,965.28
Over/Under Est: -18.83% -$67,037.98
Amt Left: 28.98% $64,927.30
Over/Under Est: -15.51% -$55,200.87
Amt Left: 34.27% $76,764.41
Delta: -4.10% -$11,837.11
Over/Under Est: -13.11% -$46,667.88
Amt Left: 38.07% $85,297.40
Delta: -2.84% -$8,532.99
Over/Under Est: -5.51% -$19,601.98
Amt Left: 50.16% $112,363.30
Delta: -8.75% -$27,065.90
Over/Under Est: 71.01% $252,797.52
Amt Left: 171.75% $384,762.80
Delta: -80.98% -$272,399.50
Over/Under Est: 81.25% $289,252.02
Amt Left: 188.02% $421,217.30
Delta: -5.99% -$36,454.50
Over/Under Est: 98.62% $351,076.32
Amt Left: 215.62% $483,041.60
Delta: -9.58% -$61,824.30

Bid Items & Bid Tabulations

24 Total 0 of 24
BASTROP  |  VARIOUS  |  AUSTIN  |  0914-18-130  |  08/06/2026 1:00 PM CDT  |  $355,991.98  |  F 2026(903)  |  LANDSCAPE DEVELOPMENT  |  59 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
APEX LANDSCAPE & IRRIGATION, LLC
TIGHT LINE CONSTRUCTION, LLC
RARE EARTH LANDSCAPE SOLUTIONS LLC
GREEN SAGE SERVICES LLC
TEXAS ROAD CONSTRUCTION, LLC
SHALOM SERVICES CORPORATION
CENTRAL NORTH CONSTRUCTION, LLC
RATLIFF HARDSCAPE, LTD.
RMV (14"-18") TRT/UNTRT BASE & ASPH PAV
SY 336.000 $18.000 $16.000 $30.000 $25.750 $75.000 $25.000 $15.000 $75.000 $62.500
EMBANK (VEH)(OC)(TY C)
CY 5.000 $31.000 $160.000 $100.000 $0.100 $90.000 $100.000 $65.000 $500.000 $40.650
FURN & PLACE TOPSOIL (12")
SY 781.000 $35.000 $8.500 $17.000 $19.400 $12.000 $50.000 $65.000 $20.000 $12.450
GENERAL USE COMPOST (VEH)
CY 78.000 $40.000 $47.500 $70.000 $92.750 $45.000 $80.000 $30.000 $90.000 $65.000
VEGETATIVE WATERING
TGL 2.000 $10.000 $6.000 $100.000 $0.100 $200.000 $1.000 $70.000 $125.000 $3,000.000
IRRIGATION SYSTEM (LOC A)
EA 1.000 $40,000.000 $6,400.000 $25,000.000 $24,000.000 $15,500.000 $30,000.000 $100,000.000 $25,000.000 $85,000.000
IRRIGATION SYSTEM (LOC B)
EA 1.000 $22,000.000 $10,600.000 $15,000.000 $24,000.000 $19,000.000 $35,000.000 $150,000.000 $25,000.000 $85,000.000
WILDFLOWER SEEDING
AC 18.890 $1,030.000 $1,760.000 $1,100.000 $566.000 $1,820.000 $1,000.000 $1,250.000 $5,000.000 $6,385.000
MULCH
CY 66.000 $56.000 $20.000 $65.000 $75.200 $50.000 $50.000 $100.000 $100.000 $32.500
PLANT BED PREP
SY 781.000 $6.000 $4.000 $6.000 $31.670 $6.000 $5.000 $50.000 $20.000 $8.350
PLANT MATERIAL (1 GAL)
EA 7,255.000 $8.000 $9.000 $10.000 $9.850 $8.300 $9.000 $7.000 $20.000 $14.000
PLANT MATERIAL (15 GAL) (TREE)
EA 2.000 $174.000 $180.000 $250.000 $342.600 $200.000 $300.000 $1,000.000 $1,500.000 $233.000
PLANT MATERIAL (100 GAL) (TREE)
EA 1.000 $1,000.000 $1,600.000 $2,000.000 $2,320.750 $1,150.000 $1,000.000 $10,000.000 $18,000.000 $1,019.000
PLANT MATERIAL (5 GAL) (SHRUB)
EA 36.000 $27.000 $30.000 $40.000 $42.300 $32.000 $50.000 $55.000 $100.000 $70.050
LANDSCAPE ESTABLISH
MO 24.000 $2,500.000 $1,000.000 $1,500.000 $1,500.000 $1,900.000 $1,500.000 $3,000.000 $4,000.000 $700.000
IRRIG SYS OPER AND MAINT
MO 24.000 $2,250.000 $1,000.000 $1,000.000 $850.000 $1,000.000 $1,000.000 $2,500.000 $2,500.000 $7,192.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 6.000 $170.000 $250.000 $250.000 $369.000 $350.000 $1,500.000 $1,000.000 $800.000 $255.850
BEDDING MATERIAL (6 IN)
CY 4.000 $230.000 $45.000 $200.000 $356.000 $355.000 $1,000.000 $200.000 $800.000 $285.000
MOBILIZATION
LS 1.000 $37,987.000 $22,555.000 $30,000.000 $37,500.000 $35,000.000 $30,000.000 $25,000.000 $50,000.000 $40,770.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $1,500.000 $3,000.000 $3,000.000 $1,900.000 $3,750.000 $3,500.000 $1.000 $6,500.000 $4,640.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 356.000 $4.060 $0.100 $1.000 $0.100 $2.500 $5.000 $1.000 $5.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 356.000 $1.070 $0.100 $1.000 $0.100 $1.300 $1.000 $1.000 $5.000 $3.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 818.000 $8.000 $0.100 $8.000 $0.100 $6.500 $3.000 $1.000 $10.000 $4.650
BIODEG EROSN CONT LOGS (REMOVE)
LF 818.000 $1.000 $0.100 $2.000 $0.100 $1.000 $1.000 $1.000 $8.000 $3.500
Totals: $355,991.980 $224,026.700 $288,954.000 $300,791.110 $309,324.100 $336,390.000 $608,789.500 $645,244.000 $707,068.300
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $7,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $8,998.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $35,000.00
Total: $51,998.00