REMOVING CONCRETE(MOW STRIP)
|
LF
|
34,831.000
|
$6.000
|
$5.300
|
$8.000
|
$6.000
|
$5.000
|
$12.800
|
|
|
REMOVE STAB BASE & ASPH PAV (13"-18")
|
SY
|
245.000
|
$20.000
|
$31.000
|
$80.000
|
$15.050
|
$34.000
|
$19.900
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
124.000
|
$15.000
|
$82.000
|
$160.000
|
$53.540
|
$135.000
|
$154.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
158.000
|
$20.000
|
$59.000
|
$45.000
|
$32.180
|
$240.000
|
$115.500
|
|
|
BLADING
|
HR
|
8.000
|
$200.000
|
$122.000
|
$250.000
|
$174.460
|
$190.000
|
$180.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
326.000
|
$1.750
|
$7.400
|
$8.000
|
$8.000
|
$8.000
|
$2.780
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
326.000
|
$0.700
|
$3.850
|
$2.000
|
$1.500
|
$4.000
|
$3.930
|
|
|
VEGETATIVE WATERING
|
MG
|
5.000
|
$20.000
|
$190.000
|
$50.000
|
$201.000
|
$25.000
|
$154.000
|
|
|
PROOF ROLLING
|
HR
|
2.000
|
$200.000
|
$132.000
|
$100.000
|
$126.100
|
$100.000
|
$180.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
|
SY
|
19,673.000
|
$60.000
|
$44.200
|
$54.880
|
$72.000
|
$55.000
|
$71.350
|
|
|
PLANE ASPH CONC PAV (3")
|
SY
|
331,008.000
|
$1.900
|
$2.640
|
$1.580
|
$3.310
|
$4.000
|
$3.780
|
|
|
PLANE ASPH CONC PAV (3"- 5")
|
SY
|
5,315.000
|
$10.000
|
$2.640
|
$1.580
|
$3.300
|
$8.250
|
$3.780
|
|
|
PLANE ASPH CONC PAV (1" TO 4")
|
SY
|
12,312.000
|
$15.000
|
$3.600
|
$1.580
|
$2.430
|
$4.500
|
$3.780
|
|
|
CONC STR REPR(RAPID VERT AND OVERHEAD)
|
SF
|
8.000
|
$250.000
|
$945.000
|
$242.000
|
$1,050.000
|
$2,200.000
|
$1,250.000
|
|
|
RIPRAP (CONC) (CL A )
|
CY
|
817.000
|
$600.000
|
$380.000
|
$565.000
|
$433.790
|
$250.000
|
$824.340
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
372.000
|
$600.000
|
$478.000
|
$575.000
|
$538.000
|
$400.000
|
$843.170
|
|
|
CLEANING AND SEALING JOINTS
|
LF
|
1,624.000
|
$40.000
|
$11.750
|
$11.750
|
$11.750
|
$11.750
|
$11.750
|
|
|
HEADER TYPE EXPANSION JOINT
|
CF
|
394.800
|
$300.000
|
$350.000
|
$349.570
|
$349.570
|
$350.000
|
$349.570
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,557,535.570
|
$448,000.000
|
$500,000.000
|
$1,592,220.230
|
$772,000.000
|
$1,793,371.990
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
15.000
|
$10,000.000
|
$8,457.000
|
$2,000.000
|
$2,110.000
|
$58,000.000
|
$3,435.810
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
9,566.000
|
$6.000
|
$4.500
|
$6.500
|
$4.500
|
$6.000
|
$4.720
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
9,566.000
|
$1.750
|
$1.000
|
$1.000
|
$1.100
|
$3.000
|
$1.050
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
104,435.000
|
$0.200
|
$0.160
|
$0.100
|
$0.410
|
$0.400
|
$0.150
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
4,826.000
|
$26.000
|
$23.450
|
$28.000
|
$23.470
|
$24.000
|
$23.940
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
6.000
|
$2,200.000
|
$2,520.000
|
$3,500.000
|
$1,916.040
|
$2,500.000
|
$1,954.360
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
24.000
|
$1,450.000
|
$1,415.000
|
$1,500.000
|
$1,414.490
|
$1,300.000
|
$1,442.780
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
4,337.500
|
$3.000
|
$4.000
|
$1.750
|
$4.000
|
$1.000
|
$4.080
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
22.000
|
$320.000
|
$275.000
|
$400.000
|
$274.900
|
$150.000
|
$280.400
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
6.000
|
$200.000
|
$92.000
|
$800.000
|
$91.630
|
$150.000
|
$93.460
|
|
|
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
|
EA
|
1.000
|
$250.000
|
$184.000
|
$150.000
|
$183.270
|
$150.000
|
$186.940
|
|
|
CABLE BARRIER SYSTEM (TL-4)
|
LF
|
28,030.000
|
$15.500
|
$13.850
|
$14.950
|
$14.470
|
$16.000
|
$13.360
|
|
|
CABLE BARRIER TERMINAL SECTION (TL-4)
|
EA
|
18.000
|
$4,500.000
|
$2,160.000
|
$3,450.000
|
$2,160.130
|
$5,500.000
|
$2,203.330
|
|
|
REMOVE CABLE BARRIER
|
LF
|
28,030.000
|
$4.500
|
$4.500
|
$3.900
|
$4.500
|
$4.000
|
$4.590
|
|
|
REMOVE CABLE BARRIER TERMINAL SECTION
|
EA
|
18.000
|
$700.000
|
$281.000
|
$515.000
|
$280.350
|
$400.000
|
$285.960
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
28.000
|
$3,400.000
|
$3,470.000
|
$3,300.000
|
$3,469.770
|
$2,775.000
|
$3,539.170
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
24.000
|
$300.000
|
$275.000
|
$300.000
|
$274.900
|
$200.000
|
$280.400
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
6.000
|
$500.000
|
$695.000
|
$600.000
|
$695.000
|
$1,000.000
|
$695.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
|
EA
|
20.000
|
$30.000
|
$25.000
|
$65.000
|
$25.000
|
$40.000
|
$25.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 2(WC)GND
|
EA
|
2.000
|
$50.000
|
$85.000
|
$150.000
|
$85.000
|
$150.000
|
$85.000
|
|
|
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
|
EA
|
27.000
|
$30.000
|
$25.000
|
$65.000
|
$25.000
|
$40.000
|
$25.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
84.000
|
$40.000
|
$22.800
|
$65.000
|
$35.000
|
$30.000
|
$35.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
10.000
|
$35.000
|
$31.550
|
$65.000
|
$35.000
|
$30.000
|
$35.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
37.000
|
$50.000
|
$22.800
|
$65.000
|
$35.000
|
$30.000
|
$35.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
|
LF
|
36,436.000
|
$1.000
|
$0.280
|
$0.550
|
$0.450
|
$0.450
|
$0.550
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
160,584.000
|
$0.850
|
$0.240
|
$0.550
|
$0.400
|
$0.400
|
$0.550
|
|
|
WK ZN PAV MRK NON-REMOV (W)(ENTR GORE)
|
EA
|
22.000
|
$600.000
|
$498.000
|
$450.000
|
$750.000
|
$750.000
|
$450.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)(EXIT GORE)
|
EA
|
22.000
|
$600.000
|
$498.000
|
$750.000
|
$750.000
|
$750.000
|
$750.000
|
|
|
WK ZN PAV MRK NON-REMOV(W)36"(YLD TRI)
|
EA
|
58.000
|
$4.000
|
$35.500
|
$25.000
|
$65.000
|
$65.000
|
$25.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
158,232.000
|
$0.850
|
$0.240
|
$0.550
|
$0.400
|
$0.400
|
$0.550
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
13,662.000
|
$1.850
|
$1.150
|
$0.770
|
$1.500
|
$1.000
|
$1.760
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
4,104.000
|
$1.850
|
$1.150
|
$0.770
|
$1.500
|
$1.000
|
$1.760
|
|
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
|
LF
|
327.000
|
$3.500
|
$1.460
|
$3.500
|
$1.500
|
$1.500
|
$3.500
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
236.000
|
$4.500
|
$3.900
|
$5.000
|
$4.000
|
$4.000
|
$5.000
|
|
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
|
EA
|
11.000
|
$750.000
|
$753.000
|
$550.000
|
$800.000
|
$800.000
|
$550.000
|
|
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
|
EA
|
11.000
|
$750.000
|
$1,345.000
|
$850.000
|
$800.000
|
$800.000
|
$850.000
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
|
EA
|
58.000
|
$60.000
|
$48.000
|
$25.000
|
$70.000
|
$70.000
|
$25.000
|
|
|
PAVEMENT SEALER 6"
|
LF
|
178,196.000
|
$0.250
|
$0.360
|
$0.450
|
$0.150
|
$0.150
|
$0.450
|
|
|
PAVEMENT SEALER 12"
|
LF
|
236.000
|
$1.000
|
$1.090
|
$2.500
|
$0.700
|
$0.700
|
$2.500
|
|
|
PAVEMENT SEALER (ENTR GORE)
|
EA
|
11.000
|
$300.000
|
$288.000
|
$250.000
|
$200.000
|
$200.000
|
$250.000
|
|
|
PAVEMENT SEALER (EXIT GORE)
|
EA
|
11.000
|
$300.000
|
$410.000
|
$450.000
|
$200.000
|
$200.000
|
$450.000
|
|
|
PAVEMENT SEALER (YLD TRI)
|
EA
|
58.000
|
$20.000
|
$30.000
|
$15.000
|
$10.000
|
$10.000
|
$15.000
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
18,218.000
|
$0.800
|
$0.760
|
$0.900
|
$0.750
|
$0.750
|
$0.900
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
80,685.000
|
$0.700
|
$0.760
|
$0.900
|
$0.650
|
$0.650
|
$0.900
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
79,113.000
|
$0.700
|
$0.760
|
$0.900
|
$0.650
|
$0.650
|
$0.900
|
|
PREFAB PAV MRK TY B (W)(6")(BRK)CNTST
|
LF
|
180.000
|
$28.000
|
$33.500
|
$30.000
|
$50.000
|
$50.000
|
$30.000
|
|
REFL PAV MRKR TY I-R
|
EA
|
252.000
|
$10.000
|
$4.600
|
$15.000
|
$6.500
|
$6.500
|
$15.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
1,522.000
|
$5.000
|
$3.960
|
$5.000
|
$4.000
|
$4.000
|
$5.000
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
178,196.000
|
$1.000
|
$0.670
|
$0.200
|
$0.500
|
$0.500
|
$0.200
|
|
|
ELIM EXT PAV MRK & MRKS (10")
|
LF
|
180.000
|
$4.000
|
$1.680
|
$0.750
|
$1.500
|
$1.500
|
$0.750
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
300.000
|
$4.000
|
$1.850
|
$0.950
|
$2.000
|
$2.000
|
$0.950
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
18.000
|
$80.000
|
$70.000
|
$100.000
|
$100.000
|
$100.000
|
$100.000
|
|
|
ELIM EXT PAV MRK & MRKS (ENTR GORE)
|
EA
|
11.000
|
$250.000
|
$390.000
|
$300.000
|
$350.000
|
$350.000
|
$300.000
|
|
|
ELIM EXT PAV MRK & MRKS (EXIT GORE)
|
EA
|
11.000
|
$250.000
|
$390.000
|
$300.000
|
$350.000
|
$350.000
|
$300.000
|
|
|
ELIM EXT PAV MRK & MRKS (36")(YLD TRI)
|
EA
|
58.000
|
$20.000
|
$25.000
|
$15.000
|
$35.000
|
$35.000
|
$15.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
180.000
|
$0.350
|
$0.100
|
$0.020
|
$2.000
|
$2.000
|
$0.020
|
|
|
LITTER REMOVAL
|
CYC
|
15.000
|
$2,000.000
|
$1,200.000
|
$3,500.000
|
$2,010.000
|
$2,500.000
|
$2,417.270
|
|
|
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
|
MI
|
161.000
|
$100.000
|
$127.000
|
$121.000
|
$490.000
|
$200.000
|
$643.180
|
|
|
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
|
CYC
|
15.000
|
$2,500.000
|
$1,835.000
|
$4,200.000
|
$5,500.000
|
$2,500.000
|
$8,250.000
|
|
|
CONCRETE RAIL REPAIR (IN-KIND)
|
LF
|
12.000
|
$100.000
|
$1,400.000
|
$675.000
|
$1,400.000
|
$2,800.000
|
$1,800.000
|
|
|
D-GR HMA TY-B PG64-22 (EXEMPT)
|
TON
|
352.000
|
$120.000
|
$120.000
|
$243.470
|
$185.000
|
$255.000
|
$136.000
|
|
|
D-GR HMA TY-D PG70-22 (LEVEL-UP)
|
TON
|
24,210.000
|
$140.000
|
$100.000
|
$134.890
|
$107.270
|
$118.000
|
$147.000
|
|
|
TACK COAT
|
GAL
|
306.000
|
$4.000
|
$3.650
|
$3.170
|
$2.900
|
$3.350
|
$6.800
|
|
|
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
|
TON
|
40,152.000
|
$140.000
|
$139.000
|
$164.850
|
$145.000
|
$183.000
|
$204.200
|
|
|
BONDING COURSE
|
GAL
|
41,897.000
|
$5.000
|
$3.550
|
$4.600
|
$5.000
|
$3.350
|
$4.440
|
|
|
UNDERSEAL COURSE
|
GAL
|
67,367.000
|
$4.500
|
$3.550
|
$4.600
|
$5.000
|
$3.850
|
$4.890
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
206.000
|
$100.000
|
$100.000
|
$77.000
|
$90.000
|
$145.000
|
$150.000
|
|
|
TMA (STATIONARY)
|
DAY
|
206.000
|
$200.000
|
$200.000
|
$225.000
|
$230.000
|
$300.000
|
$350.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
138.000
|
$300.000
|
$400.000
|
$250.000
|
$230.000
|
$300.000
|
$750.000
|
|
Totals: |
$16,458,260.170
|
$13,319,023.160
|
$15,618,002.681
|
$15,938,140.486
|
$17,436,616.150
|
$20,535,040.176
|