PREPARING ROW
|
STA
|
105.100
|
$2,497.000
|
$1,370.000
|
$2,300.000
|
$850.000
|
$700.000
|
$1,572.412
|
$1,300.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,373.000
|
$9.200
|
$20.000
|
$12.000
|
$12.000
|
$16.800
|
$15.433
|
$22.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
5,258.000
|
$7.990
|
$30.000
|
$2.000
|
$15.000
|
$19.500
|
$20.811
|
$20.000
|
|
|
BLADING
|
HR
|
30.000
|
$134.850
|
$109.310
|
$107.000
|
$100.000
|
$130.000
|
$99.000
|
$140.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
86,693.000
|
$1.250
|
$3.000
|
$1.500
|
$3.000
|
$1.150
|
$1.436
|
$3.500
|
|
|
BROADCAST SEED (PERM) (URBAN) (SANDY)
|
SY
|
86,693.000
|
$0.630
|
$0.180
|
$0.250
|
$0.150
|
$0.200
|
$0.168
|
$0.200
|
|
|
VEGETATIVE WATERING
|
MG
|
1.500
|
$23.470
|
$500.000
|
$48.000
|
$500.000
|
$785.000
|
$1,512.500
|
$400.000
|
|
|
PROOF ROLLING
|
HR
|
14.000
|
$86.310
|
$77.700
|
$84.000
|
$80.000
|
$95.000
|
$93.500
|
$68.000
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
5,778.000
|
$47.130
|
$65.000
|
$57.000
|
$62.000
|
$84.500
|
$74.170
|
$70.000
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
6,596.000
|
$3.600
|
$4.000
|
$5.100
|
$4.200
|
$4.500
|
$6.138
|
$3.500
|
|
|
ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR)
|
GAL
|
21,612.000
|
$2.830
|
$4.400
|
$4.900
|
$4.720
|
$4.500
|
$3.784
|
$4.000
|
|
|
AGGR (TY-PB GR-4)
|
CY
|
884.000
|
$94.840
|
$90.000
|
$150.250
|
$215.250
|
$135.000
|
$94.556
|
$85.000
|
|
|
SUPERPAVE MIXTURES SP-D SAC-B PG70-22
|
TON
|
5,248.000
|
$116.100
|
$105.000
|
$96.000
|
$93.450
|
$97.000
|
$96.146
|
$108.000
|
|
|
PLANE ASPH CONC PAV (1.5")
|
SY
|
31,933.000
|
$1.290
|
$3.000
|
$1.900
|
$2.100
|
$3.000
|
$3.513
|
$2.500
|
|
|
DRILL SHAFT (TRF SIG POLE) (36 IN)
|
LF
|
198.000
|
$334.240
|
$167.180
|
$179.300
|
$322.500
|
$195.000
|
$315.000
|
$280.000
|
|
|
CMP AR (GAL STL DES 4)
|
LF
|
39.000
|
$109.060
|
$204.620
|
$160.700
|
$80.000
|
$150.000
|
$127.449
|
$148.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)
|
LF
|
10.000
|
$200.440
|
$486.160
|
$1,800.000
|
$600.000
|
$680.000
|
$600.600
|
$415.000
|
|
|
CONC BOX CULV (4 FT X 2 FT)
|
LF
|
22.000
|
$247.840
|
$264.650
|
$750.000
|
$600.000
|
$515.000
|
$454.367
|
$460.000
|
|
|
CONC BOX CULV (5 FT X 5 FT)
|
LF
|
19.000
|
$388.410
|
$369.280
|
$1,700.000
|
$650.000
|
$600.000
|
$526.103
|
$750.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
32.000
|
$110.000
|
$254.710
|
$103.050
|
$180.000
|
$140.000
|
$124.646
|
$250.000
|
|
|
SET (TY I)(S=3 FT)(HW=2FT)(3:1)(C)
|
EA
|
2.000
|
$4,000.000
|
$5,129.820
|
$4,148.000
|
$4,250.000
|
$5,000.000
|
$4,396.487
|
$2,900.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 2 FT)(3:1) (C)
|
EA
|
2.000
|
$5,891.810
|
$5,379.360
|
$6,407.650
|
$5,500.000
|
$5,600.000
|
$4,977.263
|
$3,800.000
|
|
|
SET (TY I)(S= 5 FT)(HW= 5 FT)(3:1) (C)
|
EA
|
2.000
|
$8,500.000
|
$6,754.860
|
$9,198.450
|
$6,500.000
|
$8,000.000
|
$6,991.950
|
$6,300.000
|
|
|
SET (TY II) (30 IN) (RCP) (3: 1) (P)
|
EA
|
2.000
|
$2,500.000
|
$1,808.330
|
$1,607.750
|
$1,800.000
|
$3,500.000
|
$2,984.625
|
$3,100.000
|
|
|
SET (TY II) (DES 4) (CMP) (3: 1) (C)
|
EA
|
6.000
|
$2,026.670
|
$1,688.310
|
$1,279.500
|
$1,250.000
|
$2,725.000
|
$2,415.000
|
$4,500.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
6.000
|
$1,750.000
|
$1,273.580
|
$315.200
|
$900.000
|
$1,150.000
|
$1,010.625
|
$1,500.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
2.000
|
$1,100.000
|
$1,273.870
|
$235.650
|
$900.000
|
$1,150.000
|
$1,010.625
|
$1,500.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$312,990.330
|
$340,000.000
|
$340,000.000
|
$350,000.000
|
$385,000.000
|
$367,734.746
|
$390,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
14.000
|
$8,315.750
|
$7,000.000
|
$10,000.000
|
$9,500.000
|
$6,000.000
|
$11,739.457
|
$3,000.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
720.000
|
$20.350
|
$13.850
|
$37.000
|
$14.000
|
$43.850
|
$11.550
|
$37.040
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
720.000
|
$7.170
|
$4.750
|
$6.100
|
$6.000
|
$18.300
|
$2.100
|
$15.430
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,500.000
|
$2.380
|
$2.530
|
$3.200
|
$2.750
|
$5.700
|
$2.363
|
$4.800
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,500.000
|
$0.640
|
$0.510
|
$1.600
|
$0.600
|
$1.800
|
$1.050
|
$1.510
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
720.000
|
$3.700
|
$7.680
|
$4.250
|
$6.500
|
$9.450
|
$4.725
|
$7.970
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
720.000
|
$1.470
|
$1.520
|
$1.600
|
$2.500
|
$3.000
|
$1.313
|
$2.510
|
|
|
CONSTRUCTING DETOURS
|
SY
|
3,058.000
|
$44.670
|
$40.000
|
$34.650
|
$38.000
|
$38.350
|
$41.888
|
$40.000
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
330.000
|
$87.910
|
$129.500
|
$88.000
|
$95.000
|
$75.000
|
$56.100
|
$50.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
9,690.000
|
$33.170
|
$9.630
|
$26.650
|
$18.000
|
$25.000
|
$29.700
|
$65.000
|
|
|
PORT CTB (MOVE)(SGL SLP)(TY 1)
|
LF
|
7,450.000
|
$4.790
|
$6.540
|
$10.000
|
$10.000
|
$9.000
|
$9.900
|
$10.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
9,690.000
|
$6.530
|
$9.630
|
$10.050
|
$16.000
|
$11.000
|
$15.400
|
$10.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
208.000
|
$43.560
|
$89.300
|
$175.000
|
$80.000
|
$132.000
|
$47.630
|
$70.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
28.000
|
$11,996.860
|
$8,192.400
|
$6,000.000
|
$7,000.000
|
$8,000.000
|
$6,667.500
|
$6,350.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
20.000
|
$1,491.200
|
$854.720
|
$851.250
|
$900.000
|
$1,300.000
|
$840.000
|
$800.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
28.000
|
$815.040
|
$314.800
|
$573.900
|
$600.000
|
$600.000
|
$210.000
|
$200.000
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
2.000
|
$185.000
|
$200.000
|
$212.200
|
$241.870
|
$275.000
|
$236.250
|
$225.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
190.000
|
$14.090
|
$14.640
|
$15.150
|
$17.200
|
$17.000
|
$16.800
|
$20.000
|
|
|
CONDT (PVC) (SCH 80) (3")
|
LF
|
340.000
|
$20.810
|
$15.260
|
$15.800
|
$18.270
|
$17.500
|
$17.850
|
$21.000
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
1,522.000
|
$1.490
|
$1.090
|
$1.100
|
$1.230
|
$1.250
|
$1.208
|
$1.750
|
|
|
TRAY CABLE (4 CONDR) (12 AWG)
|
LF
|
1,386.000
|
$2.750
|
$1.610
|
$1.650
|
$2.680
|
$1.900
|
$2.625
|
$2.500
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
9.000
|
$2,008.500
|
$725.130
|
$750.050
|
$833.120
|
$840.000
|
$813.750
|
$750.000
|
|
|
GROUND BOX TY D (162922)W/APRON
|
EA
|
4.000
|
$1,037.000
|
$926.160
|
$958.000
|
$1,021.250
|
$1,100.000
|
$997.500
|
$900.000
|
|
|
ZINC-COAT STL WIRE STRAND (3/16")
|
LF
|
1,471.000
|
$3.830
|
$4.810
|
$5.000
|
$4.300
|
$5.550
|
$4.200
|
$2.000
|
|
|
ZINC-COAT STL WIRE STRAND (5/16")
|
LF
|
1,471.000
|
$3.890
|
$4.820
|
$5.000
|
$4.300
|
$5.550
|
$4.200
|
$2.250
|
|
|
REMOVE ELECTRICAL SERVICES
|
EA
|
1.000
|
$515.000
|
$1,146.670
|
$1,186.050
|
$430.000
|
$1,325.000
|
$420.000
|
$600.000
|
|
|
ELC SRV TY D 120/240 070(NS)AL(E)TP(O)
|
EA
|
4.000
|
$5,910.170
|
$4,200.000
|
$4,344.350
|
$3,762.500
|
$4,850.000
|
$3,675.000
|
$4,800.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
25.000
|
$524.080
|
$568.000
|
$602.600
|
$510.620
|
$560.000
|
$498.750
|
$475.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
43.000
|
$495.760
|
$400.000
|
$424.350
|
$456.870
|
$500.000
|
$446.250
|
$425.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
1.000
|
$77.670
|
$100.000
|
$156.100
|
$104.270
|
$115.000
|
$101.850
|
$97.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
24.000
|
$69.150
|
$53.840
|
$57.100
|
$55.900
|
$61.600
|
$54.600
|
$52.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
25,299.000
|
$0.540
|
$0.520
|
$0.800
|
$0.670
|
$0.600
|
$0.662
|
$0.650
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
25,104.000
|
$0.580
|
$0.520
|
$0.800
|
$0.670
|
$0.600
|
$0.662
|
$0.650
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
1,883.000
|
$1.010
|
$1.010
|
$1.800
|
$6.000
|
$0.700
|
$2.475
|
$1.850
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
13,305.000
|
$0.880
|
$0.910
|
$1.000
|
$0.820
|
$1.100
|
$0.809
|
$0.790
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
108.000
|
$5.790
|
$6.520
|
$6.350
|
$8.600
|
$7.650
|
$8.400
|
$8.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
19.000
|
$121.740
|
$123.230
|
$122.000
|
$164.570
|
$145.000
|
$143.850
|
$137.000
|
|
REFL PAV MRK TY I(W)(LNDP ARW)(100MIL)
|
EA
|
12.000
|
$475.000
|
$328.280
|
$265.200
|
$405.270
|
$385.000
|
$395.850
|
$377.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
19.000
|
$153.590
|
$156.570
|
$159.150
|
$164.570
|
$185.000
|
$160.650
|
$153.000
|
|
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
|
EA
|
10.000
|
$57.970
|
$45.460
|
$26.500
|
$47.300
|
$53.000
|
$46.200
|
$44.000
|
|
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
|
EA
|
4.000
|
$335.840
|
$459.600
|
$424.350
|
$369.800
|
$540.000
|
$361.200
|
$344.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
44,545.000
|
$0.180
|
$0.160
|
$0.200
|
$0.180
|
$0.200
|
$0.179
|
$0.170
|
|
|
PAVEMENT SEALER 8"
|
LF
|
13,305.000
|
$0.270
|
$0.290
|
$0.400
|
$0.430
|
$0.350
|
$0.420
|
$0.400
|
|
|
PAVEMENT SEALER 24"
|
LF
|
108.000
|
$2.820
|
$3.030
|
$3.200
|
$3.580
|
$3.550
|
$3.497
|
$3.300
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
19.000
|
$45.000
|
$55.560
|
$58.350
|
$67.720
|
$65.000
|
$66.150
|
$63.000
|
|
|
PAVEMENT SEALER (WORD)
|
EA
|
19.000
|
$47.850
|
$78.790
|
$68.950
|
$67.720
|
$92.450
|
$66.150
|
$63.000
|
|
|
PAVEMENT SEALER (MED NOSE)
|
EA
|
4.000
|
$149.040
|
$227.270
|
$159.150
|
$262.300
|
$265.000
|
$256.200
|
$244.000
|
|
|
PAVEMENT SEALER (LNDP ARROW)
|
EA
|
12.000
|
$142.000
|
$156.570
|
$132.600
|
$142.970
|
$185.000
|
$139.650
|
$133.000
|
|
|
PAVEMENT SEALER (YLD TRI)
|
EA
|
10.000
|
$16.000
|
$10.100
|
$15.900
|
$35.470
|
$11.850
|
$34.650
|
$33.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
19,445.000
|
$0.480
|
$0.380
|
$0.550
|
$0.430
|
$0.450
|
$0.420
|
$0.400
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
25,100.000
|
$0.520
|
$0.380
|
$0.550
|
$0.430
|
$0.450
|
$0.420
|
$0.400
|
|
REFL PAV MRKR TY I-C
|
EA
|
671.000
|
$3.630
|
$4.800
|
$5.300
|
$4.510
|
$5.500
|
$4.410
|
$4.200
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,191.000
|
$3.360
|
$4.800
|
$5.300
|
$4.050
|
$5.500
|
$3.959
|
$3.800
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
14,455.000
|
$0.460
|
$0.480
|
$0.550
|
$0.570
|
$0.600
|
$0.557
|
$0.530
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
44,545.000
|
$1.000
|
$0.050
|
$0.010
|
$0.110
|
$0.100
|
$0.105
|
$0.100
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
13,305.000
|
$1.000
|
$0.050
|
$0.020
|
$0.250
|
$0.100
|
$0.252
|
$0.240
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
108.000
|
$1.430
|
$0.510
|
$0.050
|
$2.150
|
$0.600
|
$2.100
|
$2.000
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
31.000
|
$35.000
|
$10.100
|
$5.300
|
$59.120
|
$12.000
|
$57.750
|
$55.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
19.000
|
$50.000
|
$10.100
|
$5.300
|
$59.120
|
$12.000
|
$57.750
|
$55.000
|
|
|
PAV SURF PREP FOR MRK (36")(YLD TRI)
|
EA
|
10.000
|
$30.000
|
$5.050
|
$2.100
|
$23.650
|
$6.000
|
$23.100
|
$22.000
|
|
|
PAV SURF PREP FOR MRK (MED NOSE)
|
EA
|
3.000
|
$75.000
|
$35.350
|
$15.900
|
$154.800
|
$42.000
|
$151.200
|
$144.000
|
|
|
INSTALL HWY TRF SIG (FLASH BEACON)
|
EA
|
4.000
|
$4,932.570
|
$5,432.820
|
$5,619.500
|
$7,525.000
|
$6,300.000
|
$7,350.000
|
$2,600.000
|
|
|
REMOVING TRAFFIC SIGNALS
|
EA
|
1.000
|
$4,154.550
|
$1,847.180
|
$1,910.650
|
$5,375.000
|
$2,135.000
|
$5,250.000
|
$2,250.000
|
|
|
VEH SIG SEC (12")LED(YEL)
|
EA
|
28.000
|
$250.260
|
$295.380
|
$305.550
|
$247.250
|
$340.000
|
$241.500
|
$250.000
|
|
|
VEH SIG SEC (12")LED(RED)
|
EA
|
16.000
|
$223.910
|
$295.380
|
$305.550
|
$247.250
|
$340.000
|
$241.500
|
$250.000
|
|
|
TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
|
LF
|
2,942.000
|
$2.050
|
$1.280
|
$1.350
|
$2.410
|
$1.500
|
$2.363
|
$2.150
|
|
|
INS TRF SIG PL AM (S)STR(TY B)
|
EA
|
8.000
|
$4,000.000
|
$3,816.410
|
$3,947.550
|
$4,837.500
|
$4,400.000
|
$4,725.000
|
$5,000.000
|
|
|
INS TRF SIG PL AM (S)STR(TY B)LUM
|
EA
|
7.000
|
$4,590.150
|
$5,205.130
|
$5,384.000
|
$6,450.000
|
$6,000.000
|
$6,300.000
|
$6,500.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
8.000
|
$79.230
|
$130.100
|
$38.000
|
$500.000
|
$175.000
|
$1,100.000
|
$425.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
116.000
|
$196.000
|
$354.550
|
$294.000
|
$200.000
|
$355.000
|
$660.000
|
$625.000
|
|
Totals: |
$3,591,226.875
|
$3,461,234.910
|
$3,465,321.250
|
$3,567,410.010
|
$3,614,031.000
|
$3,732,591.197
|
$4,071,220.500
|