PREPARING ROW
|
STA
|
18.000
|
$7,000.000
|
$5,000.000
|
$900.000
|
$2,000.000
|
|
|
REMOVING CONC (RIPRAP)
|
CY
|
77.000
|
$96.000
|
$30.000
|
$176.000
|
$150.000
|
|
|
REMOVING CONC (SIDEWALK OR RAMP)
|
SY
|
228.000
|
$15.000
|
$30.000
|
$20.000
|
$15.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
178.000
|
$5.000
|
$30.000
|
$1.000
|
$10.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
167.000
|
$10.000
|
$50.000
|
$65.000
|
$15.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
16.000
|
$13.000
|
$100.000
|
$100.000
|
$100.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
906.000
|
$1.500
|
$6.000
|
$5.500
|
$5.500
|
|
|
BROADCAST SEED (PERM) (URBAN) (CLAY)
|
SY
|
906.000
|
$0.500
|
$1.000
|
$1.100
|
$2.500
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
453.000
|
$0.500
|
$1.000
|
$1.100
|
$2.700
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
453.000
|
$0.500
|
$1.000
|
$1.100
|
$2.700
|
|
|
VEGETATIVE WATERING
|
MG
|
37.000
|
$25.000
|
$40.000
|
$100.000
|
$50.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY C)
|
SY
|
906.000
|
$2.000
|
$4.000
|
$1.760
|
$4.500
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
|
SY
|
20.000
|
$75.000
|
$150.000
|
$825.000
|
$100.000
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
481.000
|
$2.000
|
$15.000
|
$15.070
|
$16.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
2.700
|
$125.000
|
$1,800.000
|
$1,500.000
|
$600.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
200.000
|
$290.000
|
$150.000
|
$285.000
|
$300.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
77.000
|
$440.000
|
$425.000
|
$528.000
|
$450.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
13.000
|
$490.000
|
$450.000
|
$594.000
|
$450.000
|
|
|
ELASTOMERIC BEARING (LAMINATED)
|
EA
|
140.000
|
$2,125.000
|
$425.000
|
$2,600.000
|
$2,000.000
|
|
|
CLEANING AND SEALING EXISTING JOINTS
|
LF
|
536.000
|
$65.000
|
$25.000
|
$40.000
|
$30.000
|
|
|
LATEX - MODIFIED CONC OVERLAY (2 IN)
|
SY
|
4,919.000
|
$105.000
|
$85.000
|
$87.000
|
$100.000
|
|
|
RAIL (TY T402)
|
LF
|
20.000
|
$106.000
|
$350.000
|
$800.000
|
$180.000
|
|
|
RAIL (HANDRAIL)(TY E)
|
LF
|
142.000
|
$100.000
|
$185.000
|
$160.000
|
$200.000
|
|
|
HYDRO-DEMOLITION (2 IN)
|
SY
|
4,919.000
|
$80.000
|
$77.000
|
$52.500
|
$130.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$172,581.000
|
$135,000.000
|
$145,000.000
|
$180,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$8,000.000
|
$6,000.000
|
$2,800.000
|
$1,500.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
80.000
|
$25.000
|
$35.000
|
$18.700
|
$22.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
80.000
|
$10.000
|
$15.000
|
$2.200
|
$5.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
1,339.000
|
$7.500
|
$7.000
|
$6.330
|
$7.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,339.000
|
$1.400
|
$3.000
|
$1.380
|
$2.500
|
|
|
CONC SIDEWALKS (4")
|
SY
|
322.000
|
$50.000
|
$50.000
|
$64.000
|
$52.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
39.000
|
$22.000
|
$55.660
|
$55.060
|
$55.000
|
|
|
MTL BEAM GD FEN TRANS (TL2)
|
EA
|
4.000
|
$1,140.000
|
$1,284.800
|
$1,229.800
|
$1,350.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,280.000
|
$1,892.000
|
$1,424.500
|
$1,900.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
178.000
|
$3.000
|
$3.740
|
$4.400
|
$4.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
1.000
|
$250.000
|
$291.500
|
$220.000
|
$300.000
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
1.000
|
$250.000
|
$291.500
|
$220.000
|
$300.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$2,700.000
|
$3,528.800
|
$3,655.300
|
$3,500.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
14.000
|
$30.000
|
$50.000
|
$100.000
|
$50.000
|
|
|
IN SM RD SN SUP&AM (RAIL MOUNT)
|
EA
|
2.000
|
$3,200.000
|
$2,420.000
|
$2,500.000
|
$2,500.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND
|
EA
|
12.000
|
$70.000
|
$125.000
|
$50.000
|
$20.000
|
|
|
WK ZN PAV MRK REMOV (W)12"(SLD)
|
LF
|
140.000
|
$3.000
|
$5.500
|
$5.500
|
$12.000
|
|
RE PV MRK TY I(BLACK)4"(SHADOW)(100MIL)
|
LF
|
553.000
|
$10.500
|
$3.300
|
$3.300
|
$4.750
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
553.000
|
$0.400
|
$3.300
|
$3.300
|
$1.500
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
2,212.000
|
$0.350
|
$1.650
|
$1.650
|
$1.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
28.000
|
$3.000
|
$22.000
|
$22.000
|
$7.250
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
28.000
|
$4.000
|
$22.000
|
$22.000
|
$7.250
|
|
|
REPAIR METAL RAIL (C4)
|
LF
|
100.000
|
$250.000
|
$105.000
|
$104.000
|
$160.000
|
|
|
REP STL BRIDGE MEMBER (ROCKER)
|
EA
|
7.000
|
$1,000.000
|
$5,500.000
|
$4,400.000
|
$15,000.000
|
|
|
CONCRETE BEAM REPAIR
|
EA
|
20.000
|
$1,750.000
|
$4,200.000
|
$2,500.000
|
$10,000.000
|
|
|
TACK COAT
|
GAL
|
97.000
|
$3.000
|
$8.000
|
$3.190
|
$10.000
|
|
|
D-GR HMA TY-C SAC-B PG70-22 (EXEMPT)
|
TON
|
54.000
|
$90.000
|
$225.000
|
$495.000
|
$200.000
|
|
|
INSTALL BRIDGE IDENTIFICATION NUMBERS
|
EA
|
2.000
|
$220.000
|
$700.000
|
$500.000
|
$200.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$10,000.000
|
$15,000.000
|
$11,500.000
|
$10,000.000
|
|
Totals: |
$1,905,785.500
|
$1,567,047.860
|
$1,699,946.990
|
$2,273,493.950
|