PREPARING ROW
|
STA
|
3.000
|
$10,000.000
|
$35,000.000
|
$15,000.000
|
$8,500.000
|
$10,000.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
50.000
|
$50.000
|
$80.000
|
$220.000
|
$400.000
|
$300.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
793.000
|
$5.000
|
$10.000
|
$6.000
|
$25.000
|
$50.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
100.000
|
$8.000
|
$5.500
|
$5.750
|
$5.000
|
$10.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY C)
|
SY
|
233.000
|
$9.000
|
$5.500
|
$5.750
|
$5.000
|
$15.000
|
|
|
SOIL RETENTION BLANKETS (CL 2) (TY G)
|
SY
|
460.000
|
$5.500
|
$7.250
|
$7.450
|
$5.000
|
$25.000
|
|
|
FLEX PAVEMENT STRUCTURE REPAIR (8"-15")
|
SY
|
4.000
|
$200.000
|
$1,900.000
|
$3,370.000
|
$2,500.000
|
$1,200.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
2.000
|
$550.000
|
$1,000.000
|
$4,410.000
|
$10,000.000
|
$2,500.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
4.100
|
$1,100.000
|
$3,600.000
|
$13,177.000
|
$10,000.000
|
$4,500.000
|
|
|
PENETRATING CONCRETE SURFACE TREATMENT
|
SY
|
55.000
|
$20.000
|
$100.000
|
$395.000
|
$30.000
|
$120.000
|
|
|
CONC STR REPAIR (VERTICAL & OVERHEAD)
|
SF
|
44.000
|
$283.000
|
$370.000
|
$540.000
|
$1,000.000
|
$300.000
|
|
|
RIPRAP (CONC) (CL A )
|
CY
|
9.000
|
$800.000
|
$1,200.000
|
$1,800.000
|
$1,000.000
|
$800.000
|
|
|
RIPRAP (CONC)(CL C)
|
CY
|
2.000
|
$1,000.000
|
$2,200.000
|
$2,000.000
|
$4,000.000
|
$2,400.000
|
|
|
RIPRAP (STONE PROTECTION)(21 IN)
|
CY
|
261.000
|
$250.000
|
$290.000
|
$175.000
|
$300.000
|
$260.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
50.000
|
$800.000
|
$900.000
|
$1,000.000
|
$450.000
|
$860.000
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL3)
|
LF
|
184.000
|
$65.000
|
$60.000
|
$96.000
|
$65.000
|
$120.000
|
|
|
RETROFIT RAIL (TY T222)
|
LF
|
524.700
|
$250.000
|
$310.000
|
$425.000
|
$400.000
|
$410.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$77,000.000
|
$100,000.000
|
$115,000.000
|
$110,000.000
|
$150,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
6.000
|
$10,000.000
|
$8,000.000
|
$6,000.000
|
$7,149.368
|
$8,000.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
200.000
|
$5.000
|
$5.500
|
$5.750
|
$2.321
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
200.000
|
$1.800
|
$1.000
|
$3.000
|
$0.633
|
$2.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
200.000
|
$9.000
|
$7.750
|
$8.000
|
$3.501
|
$15.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
200.000
|
$3.500
|
$1.000
|
$3.000
|
$0.856
|
$4.000
|
|
|
PTB(FRN&INSTL)(SSCB OR CSB)(TY1)OR(STL)
|
LF
|
120.000
|
$75.000
|
$100.000
|
$150.000
|
$240.000
|
$170.000
|
|
|
PTB(MOVE)(SSCB OR CSB)(TY1)OR(STL)
|
LF
|
60.000
|
$15.000
|
$50.000
|
$130.000
|
$125.000
|
$170.000
|
|
|
PTB(REMOVE)(SSCB OR CSB)(TY1)OR(STL)
|
LF
|
120.000
|
$32.000
|
$70.000
|
$130.000
|
$125.000
|
$170.000
|
|
|
PORT CTB (FURN & INST)(TL-3 LPCB)
|
LF
|
270.000
|
$60.000
|
$200.000
|
$230.000
|
$240.000
|
$150.000
|
|
|
PORT CTB (MOVE) (TL-3 LPCB)
|
LF
|
270.000
|
$16.000
|
$50.000
|
$35.000
|
$125.000
|
$150.000
|
|
|
PORT CTB (REMOVE) (TL-3 LPCB)
|
LF
|
270.000
|
$32.000
|
$50.000
|
$50.000
|
$125.000
|
$150.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,100.000
|
$40.000
|
$33.000
|
$38.000
|
$40.000
|
$42.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,700.000
|
$3,700.000
|
$2,000.000
|
$2,500.000
|
$4,500.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,900.000
|
$2,400.000
|
$2,200.000
|
$2,500.000
|
$5,200.000
|
|
|
TL-3 31" SHORT RADIUS (COMPLETE)
|
EA
|
2.000
|
$22,000.000
|
$20,000.000
|
$22,000.000
|
$20,000.000
|
$25,000.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
350.000
|
$5.000
|
$5.500
|
$10.000
|
$5.000
|
$30.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
3.000
|
$350.000
|
$400.000
|
$400.000
|
$350.000
|
$1,000.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$4,000.000
|
$4,000.000
|
$4,100.000
|
$3,500.000
|
$5,000.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$400.000
|
$400.000
|
$400.000
|
$243.581
|
$2,000.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$3,400.000
|
$1,700.000
|
$1,800.000
|
$15,000.000
|
$4,500.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
4.000
|
$2,400.000
|
$1,000.000
|
$600.000
|
$1,500.000
|
$3,500.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
2.000
|
$35,000.000
|
$40,000.000
|
$25,000.000
|
$34,000.000
|
$32,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
4.000
|
$15,000.000
|
$10,000.000
|
$9,945.000
|
$7,000.000
|
$24,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
5.000
|
$800.000
|
$900.000
|
$745.000
|
$680.000
|
$800.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
3.000
|
$1,050.000
|
$1,100.000
|
$831.000
|
$765.000
|
$1,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
1.000
|
$1,300.000
|
$1,100.000
|
$890.000
|
$815.000
|
$1,500.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
11.000
|
$50.000
|
$40.000
|
$45.000
|
$77.000
|
$150.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
7,240.000
|
$2.000
|
$1.250
|
$1.100
|
$1.050
|
$2.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
9,414.000
|
$2.500
|
$1.250
|
$1.100
|
$1.050
|
$2.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
132.000
|
$3.500
|
$9.500
|
$6.000
|
$1.050
|
$12.000
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
|
LF
|
1,380.000
|
$1.000
|
$3.250
|
$1.100
|
$1.050
|
$7.000
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
|
LF
|
330.000
|
$1.100
|
$3.250
|
$1.100
|
$1.050
|
$10.000
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
|
LF
|
1,300.000
|
$0.900
|
$3.250
|
$1.100
|
$1.050
|
$12.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
104.000
|
$10.000
|
$4.500
|
$7.750
|
$6.750
|
$75.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
3,010.000
|
$4.000
|
$2.000
|
$0.900
|
$0.800
|
$5.000
|
|
|
CRACK CLEANING AND SEALING (JCP)
|
LF
|
100.000
|
$29.000
|
$10.000
|
$25.000
|
$45.000
|
$85.000
|
|
|
INSTALL FTB
|
LF
|
350.000
|
$59.000
|
$275.000
|
$50.000
|
$25.000
|
$75.000
|
|
|
REMOVE FTB
|
LF
|
350.000
|
$29.000
|
$9.000
|
$15.000
|
$10.000
|
$25.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
60.000
|
$300.000
|
$100.000
|
$150.000
|
$150.000
|
$50.000
|
|
|
TMA (STATIONARY)
|
DAY
|
117.000
|
$500.000
|
$200.000
|
$400.000
|
$192.000
|
$500.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
2.000
|
$900.000
|
$2,800.000
|
$2,000.000
|
$1,000.000
|
$1,200.000
|
|
Totals: |
$939,269.000
|
$1,151,580.500
|
$1,152,117.350
|
$1,186,292.370
|
$1,423,414.000
|