BOWIE IH 30 (0610-05-060)

Items: 102

County: BOWIE
Length: 1.0900 MILES
Highway: IH 30
District: ATLANTA
Control Number: 0610-05-060
DBE Goal: 0.0%
Project: F 2026(876)
Guaranty: $100,000.00
Time: 337 WORKING DAYS
Engineer's Estimate: $12,397,796.00
Date: 08/06/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263212
Type: CONSTRUCT TRUCK PARKING
Project ID: A00203348
Contract Type: FEDERAL
Project Description: CONSTRUCT TRUCK PARKING AREAS ON NORTH AND SOUTH SIDE OF IH 30 IN BOWIE COUNTY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$12,397,796.00
$10,625,436.47
Over/Under Est: -14.3% -$1,772,359.53
Over/Under Est: -11.55% -$1,432,145.19
Amt Left: 3.2% $340,214.34
$11,520,690.13
Over/Under Est: -7.07% -$877,105.87
Amt Left: 8.43% $895,253.66
Delta: -5.06% -$555,039.32
Over/Under Est: 10.17% $1,260,451.40
Amt Left: 28.54% $3,032,810.93
Delta: -18.55% -$2,137,557.27

Bid Items & Bid Tabulations

102 Total 0 of 102
BOWIE  |  IH 30  |  ATLANTA  |  0610-05-060  |  08/06/2026 1:00 PM CDT  |  $12,397,796.00  |  F 2026(876)  |  CONSTRUCT TRUCK PARKING  |  337 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
DRAKE COMPANIES LLC
HIGHWAY 19 CONSTRUCTION LLC
PREPARING ROW
AC 46.100 $10,550.000 $7,700.000 $7,500.000 $2,500.000 $7,000.000
REMOV CONC (PAV)
SY 22,682.000 $10.000 $5.500 $10.000 $5.250 $10.000
REMOV CONC (RIPRAP)
SY 1,954.000 $9.000 $12.000 $7.000 $9.000 $25.000
REMOV CONC (MEDIANS)
SY 200.000 $17.000 $15.000 $10.000 $7.850 $25.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 2,042.000 $12.000 $12.000 $6.000 $8.800 $25.000
REMOV CONC (FOUNDATIONS)
SY 572.000 $60.000 $15.000 $32.000 $11.000 $25.000
REMOV CONC (MISC)
SY 870.000 $36.000 $15.000 $20.000 $7.500 $25.000
RMV (10"-14") TRT/UNTRT BASE & ASPH PAV
SY 11,549.000 $10.000 $11.000 $7.000 $9.700 $5.000
EXCAV (ROADWAY)
CY 3,711.000 $10.000 $9.500 $8.000 $6.500 $10.000
EMBANK (VEH)(DC)(TY C)
CY 70,340.000 $20.000 $11.500 $14.000 $11.250 $15.000
FURN & PLACE TOPSOIL (4")
SY 22,250.000 $1.000 $1.500 $2.000 $2.000 $1.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 22,346.000 $0.500 $0.520 $0.570 $0.530 $0.650
BOND FBR MTRX SEED (TEMP)(WARM)
SY 11,173.000 $0.750 $0.500 $0.560 $0.500 $0.350
BOND FBR MTRX SEED (TEMP)(COOL)
SY 11,173.000 $0.750 $0.500 $0.560 $0.500 $0.350
FL BS (CMP IN PLC)(TY E GR 4) (4")
SY 80,093.000 $8.000 $2.650 $3.000 $2.000 $19.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 1,665.000 $350.000 $380.000 $443.000 $415.000 $350.000
LIME TRT (NEW BASE)(8")
SY 30,873.000 $3.000 $3.000 $2.000 $4.000 $3.500
LIME TRT (NEW BASE)(10")
SY 80,093.000 $3.000 $3.250 $2.000 $3.750 $3.500
CEMENT
TON 1,665.000 $225.000 $240.000 $250.000 $235.000 $250.000
CEMENT TRT (NEW BASE)(8")
SY 30,873.000 $3.000 $2.000 $2.000 $4.000 $2.500
CEMENT TRT (NEW BASE)(10")
SY 80,093.000 $3.000 $2.250 $2.000 $3.750 $2.500
PRIME COAT (MC-30)
GAL 27,743.000 $5.000 $5.500 $6.400 $5.250 $6.000
FOG SEAL (CSS-1H)
GAL 22,426.000 $3.500 $4.250 $2.000 $3.000 $5.250
ASPH (AC-20-5TR)
GAL 15,440.000 $4.000 $5.000 $5.600 $4.700 $5.000
AGGR (TY-PB, GR-4)(SAC-A)
CY 256.000 $72.000 $215.000 $285.000 $190.000 $180.000
SP MIXES SP-C PG76-22
TON 15,759.000 $122.000 $132.000 $130.000 $134.000 $126.000
SP MIXES SP-D SAC-A PG76-22
TON 3,110.000 $125.000 $133.000 $132.000 $134.000 $126.000
TACK COAT
GAL 18,524.000 $4.000 $4.500 $4.000 $4.500 $6.000
TRENCH EXCAVATION PROTECTION
LF 764.000 $5.000 $10.000 $10.000 $8.000 $5.000
DRILL SHAFT (SIGN MTS) (24 IN)
LF 12.000 $190.000 $225.000 $150.000 $225.000 $205.000
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 200.000 $872.000 $770.000 $780.000 $1,020.000 $928.000
CL C CONC (COLLAR)
EA 1.000 $1,425.000 $1,500.000 $1,300.000 $1,500.000 $2,500.000
RIPRAP (CONC)(5 IN)
CY 207.000 $650.000 $585.000 $472.000 $600.000 $750.000
RIPRAP (CONC)(CL B)
CY 26.000 $475.000 $700.000 $505.000 $630.000 $700.000
RIPRAP (MOW STRIP)(4 IN)
CY 16.000 $565.000 $650.000 $535.000 $600.000 $600.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 20.000 $219.000 $185.000 $300.000 $295.000 $180.000
RC PIPE (CL III)(18 IN)
LF 168.000 $75.000 $55.000 $60.000 $60.000 $55.000
RC PIPE (CL III)(24 IN)
LF 672.000 $89.000 $75.000 $72.000 $75.000 $70.000
RC PIPE (CL III)(30 IN)
LF 1,012.000 $100.000 $105.000 $100.000 $100.000 $110.000
RC PIPE (CL III)(42 IN)
LF 548.000 $205.000 $190.000 $175.000 $175.000 $250.000
INLET(COMPL)(PAZD)(FG)(4FTX4FT-4FTX4FT)
EA 1.000 $9,000.000 $9,500.000 $7,500.000 $8,500.000 $5,000.000
HEADWALL (CH - FW - 0) (DIA= 30 IN)
EA 1.000 $5,530.000 $9,000.000 $11,000.000 $10,500.000 $9,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 6.000 $1,270.000 $875.000 $950.000 $1,100.000 $700.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $2,145.000 $1,200.000 $1,315.000 $1,570.000 $750.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 7.000 $3,189.000 $2,900.000 $2,500.000 $2,875.000 $1,250.000
SET (TY II) (42 IN) (RCP) (4: 1) (C)
EA 2.000 $5,220.000 $7,000.000 $5,830.000 $5,975.000 $7,000.000
REMOV STR (INLET)
EA 8.000 $1,018.000 $500.000 $675.000 $550.000 $1,000.000
REMOV STR (HEADWALL)
EA 15.000 $1,288.000 $500.000 $715.000 $785.000 $500.000
REMOV STR (PIPE)
LF 905.000 $18.000 $10.000 $12.000 $12.500 $50.000
MOBILIZATION
LS 1.000 $1,128,000.000 $500,000.000 $800,000.000 $900,000.000 $1,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $5,000.000 $2,500.000 $2,300.000 $5,500.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $10,000.000 $6,600.000 $19,000.000 $15,000.000
TMA (STATIONARY)
DAY 177.000 $140.000 $200.000 $250.000 $150.000 $250.000
TMA (MOBILE OPERATION)
DAY 26.000 $330.000 $200.000 $350.000 $275.000 $1,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 315.000 $49.000 $38.500 $42.000 $38.000 $45.000
ROCK FILTER DAMS (REMOVE)
LF 315.000 $12.000 $9.000 $10.000 $10.000 $10.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 278.000 $30.000 $38.500 $44.000 $38.000 $35.000
CONSTRUCTION EXITS (REMOVE)
SY 278.000 $8.000 $6.000 $10.000 $7.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 9,203.000 $4.000 $4.000 $4.000 $3.900 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 9,203.000 $1.000 $0.400 $0.660 $0.500 $1.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 300.000 $9.000 $7.000 $5.500 $7.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 300.000 $1.250 $0.250 $1.100 $0.500 $1.000
PTB (FUR&INST)(SGL SLP)(TY 1) OR (STL)
LF 15,630.000 $42.000 $65.000 $63.000 $74.000 $90.000
PTB (MOVE)(SGL SLP)(TY 1) OR (STL)
LF 7,605.000 $15.000 $6.000 $2.500 $5.000 $25.000
PTB (REMOVE)(SGL SLP)(TY 1) OR (STL)
LF 15,630.000 $20.000 $9.000 $10.000 $7.000 $35.000
MTL W-BEAM GD FEN (TIM POST)
LF 275.000 $27.000 $27.000 $34.000 $29.000 $35.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,170.000 $1,400.000 $1,650.000 $1,550.000 $2,750.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,280.000 $3,500.000 $3,740.000 $3,650.000 $3,500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $1,130.000 $1,625.000 $1,120.000 $2,200.000 $1,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $510.000 $850.000 $690.000 $900.000 $2,500.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $9,500.000 $10,000.000 $7,590.000 $9,800.000 $7,500.000
PIPE UNDERDRAINS (TY 9) (6")
LF 400.000 $35.000 $40.000 $50.000 $40.000 $50.000
HI MST IL POLE (150 FT)( 80 MPH)
EA 8.000 $54,250.000 $50,800.000 $50,845.000 $60,525.000 $55,025.000
LED HI MST IL ASM (6 FIXT) (TY A)
EA 8.000 $50,000.000 $31,400.000 $31,500.000 $45,000.000 $40,750.000
CONDT (PVC) (SCH 40) (2")
LF 3,769.000 $13.000 $15.250 $15.400 $8.250 $7.500
CONDT (PVC) (SCH 40) (2") (BORE)
LF 2,246.000 $27.000 $29.000 $30.000 $20.350 $18.500
ELEC CONDR (NO.6) BARE
LF 6,190.000 $3.000 $3.600 $3.600 $2.750 $2.500
ELEC CONDR (NO.6) INSULATED
LF 12,410.000 $3.000 $3.600 $3.600 $3.000 $2.750
GROUND BOX TY A (122311)
EA 8.000 $986.000 $1,350.000 $1,345.000 $1,100.000 $1,000.000
GROUND BOX TY A (122311)W/APRON
EA 19.000 $1,250.000 $2,175.000 $2,170.000 $1,295.000 $1,175.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 3.000 $9,770.000 $13,000.000 $12,900.000 $8,425.000 $7,658.000
ALUMINUM SIGNS (TY G)
EA 7.000 $1,000.000 $1,850.000 $1,860.000 $2,500.000 $150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 1.000 $656.000 $880.000 $732.000 $895.000 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 8.000 $787.000 $1,050.000 $915.000 $1,055.000 $1,100.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 4.000 $957.000 $1,150.000 $1,195.000 $1,200.000 $850.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 3.000 $1,264.000 $1,400.000 $1,540.000 $1,420.000 $800.000
IN SM RD SN SUP&AM TYS80(2)SA(P)
EA 7.000 $2,248.000 $3,050.000 $3,155.000 $3,060.000 $1,000.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 2.000 $368.000 $500.000 $660.000 $515.000 $700.000
REMOVE SM RD SN SUP&AM
EA 25.000 $130.000 $110.000 $87.000 $110.000 $100.000
RELOCATE LRSA
EA 1.000 $1,068.000 $7,000.000 $6,600.000 $5,000.000 $6,350.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 8.000 $43.000 $45.000 $27.500 $49.000 $35.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 37.000 $114.000 $140.000 $66.000 $140.000 $45.000
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 15,420.000 $1.500 $1.100 $1.250 $1.100 $1.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 2,070.000 $1.500 $1.300 $1.000 $1.320 $1.200
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,495.000 $1.000 $1.300 $1.000 $1.320 $1.200
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 2,120.000 $2.500 $4.950 $3.300 $4.950 $4.500
ALL-WTHER PM TY I (W)6"(SLD)(100MIL)
LF 10,570.000 $1.000 $1.650 $0.830 $1.650 $1.500
ALL-WTHER PM TY I (W)6"(BRK)(100MIL)
LF 3,310.000 $1.000 $1.650 $0.830 $1.650 $1.500
ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)
LF 1,825.000 $1.000 $1.650 $0.830 $1.650 $1.500
REFL PAV MRKR TY II-C-R
EA 286.000 $4.250 $6.500 $4.400 $6.600 $6.000
ELIM EXT PM & MRKS (6")
LF 13,220.000 $1.000 $0.570 $0.750 $0.570 $0.520
PERMEABLE CONCRETE EDGE DRAIN
LF 9,183.000 $67.000 $60.000 $55.000 $85.000 $40.000
Totals: $12,397,796.000 $10,625,436.470 $10,965,650.810 $11,520,690.130 $13,658,247.400
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $90,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $45,000.00
Total: $135,000.00