PREPARING ROW
|
STA
|
6.000
|
$13,000.000
|
$40,000.000
|
$5,000.000
|
$23,257.000
|
$13,500.000
|
$16,000.000
|
$7,000.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
1,446.000
|
$7.000
|
$5.000
|
$5.000
|
$7.320
|
$20.000
|
$15.000
|
$25.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
308.000
|
$10.000
|
$5.000
|
$4.000
|
$4.340
|
$29.000
|
$15.000
|
$30.000
|
|
|
REMOVING CONC (SIDEWALKS)
|
SY
|
35.000
|
$11.000
|
$5.000
|
$5.000
|
$12.360
|
$46.000
|
$16.000
|
$50.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
200.000
|
$6.500
|
$8.000
|
$35.000
|
$12.000
|
$44.000
|
$30.000
|
$30.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
1,785.000
|
$20.000
|
$13.500
|
$45.000
|
$30.000
|
$37.000
|
$25.000
|
$25.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
405.000
|
$15.000
|
$13.500
|
$45.000
|
$30.000
|
$76.000
|
$27.000
|
$25.000
|
|
|
EMBANK(FINAL)(DC)(TY E)(CSBE)
|
CY
|
1,600.000
|
$45.000
|
$70.000
|
$70.000
|
$75.000
|
$71.000
|
$80.000
|
$60.000
|
|
|
BLOCK SODDING
|
SY
|
2,112.000
|
$4.800
|
$5.000
|
$4.500
|
$6.320
|
$5.500
|
$6.000
|
$6.000
|
|
|
STRAW OR HAY MULCH
|
SY
|
2,112.000
|
$0.200
|
$1.000
|
$0.300
|
$2.840
|
$1.500
|
$0.900
|
$3.000
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
SY
|
1,056.000
|
$0.100
|
$1.000
|
$0.250
|
$2.220
|
$1.000
|
$0.450
|
$2.250
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
SY
|
1,056.000
|
$0.100
|
$1.000
|
$0.250
|
$2.220
|
$1.000
|
$0.450
|
$2.250
|
|
|
FERTILIZER
|
AC
|
0.880
|
$670.000
|
$2,500.000
|
$750.000
|
$2,321.160
|
$2,000.000
|
$1,500.000
|
$2,500.000
|
|
|
VEGETATIVE WATERING
|
MG
|
106.000
|
$30.000
|
$60.000
|
$20.000
|
$21.000
|
$27.000
|
$50.000
|
$30.000
|
|
|
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
|
TON
|
17.000
|
$290.000
|
$300.000
|
$185.000
|
$260.000
|
$260.000
|
$280.000
|
$350.000
|
|
|
LIME TRT (SUBGRADE)(8")
|
SY
|
966.000
|
$6.750
|
$5.000
|
$8.000
|
$12.000
|
$26.000
|
$12.000
|
$10.000
|
|
|
CONC PVMT (CONT REINF - CRCP) (8")
|
SY
|
860.000
|
$100.000
|
$75.000
|
$98.000
|
$115.000
|
$104.000
|
$75.000
|
$88.000
|
|
|
CONC PAV (CONT REINF)(FAST TRK)(11")
|
SY
|
667.000
|
$110.000
|
$98.500
|
$110.000
|
$137.000
|
$140.000
|
$200.000
|
$115.000
|
|
|
CEM STABIL BKFL
|
CY
|
26.000
|
$50.000
|
$70.000
|
$90.000
|
$60.000
|
$60.000
|
$80.000
|
$50.000
|
|
|
CEMENT STAB BACKFILL (INLET OR MH)
|
CY
|
58.000
|
$50.000
|
$70.000
|
$90.000
|
$60.000
|
$60.000
|
$80.000
|
$50.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
580.000
|
$3.000
|
$2.000
|
$4.000
|
$1.000
|
$2.000
|
$2.000
|
$5.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,227.000
|
$15.000
|
$30.000
|
$3.000
|
$13.000
|
$27.000
|
$2.000
|
$50.000
|
|
|
DRILL SHAFT (30 IN)
|
LF
|
1,260.000
|
$200.000
|
$285.000
|
$300.000
|
$260.000
|
$235.000
|
$300.000
|
$450.000
|
|
|
CL C CONC (ABUT)
|
CY
|
39.200
|
$1,000.000
|
$1,100.000
|
$1,500.000
|
$1,320.000
|
$1,600.000
|
$1,500.000
|
$1,900.000
|
|
|
CL C CONC (CAP)
|
CY
|
35.800
|
$1,200.000
|
$1,150.000
|
$1,500.000
|
$2,230.000
|
$1,700.000
|
$2,000.000
|
$1,750.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
42.600
|
$1,200.000
|
$1,000.000
|
$1,500.000
|
$1,500.000
|
$1,850.000
|
$1,500.000
|
$1,750.000
|
|
|
REINF CONC SLAB (SLAB BEAM)
|
SF
|
7,546.000
|
$20.000
|
$16.500
|
$20.000
|
$19.000
|
$23.000
|
$17.000
|
$22.000
|
|
|
APPROACH SLAB
|
CY
|
113.000
|
$650.000
|
$550.000
|
$900.000
|
$585.000
|
$690.000
|
$850.000
|
$800.000
|
|
|
RETAINING WALL (SPREAD FOOTING)
|
SF
|
2,802.000
|
$95.000
|
$35.000
|
$80.000
|
$92.000
|
$125.000
|
$135.000
|
$110.000
|
|
|
PRESTR CONC SLAB BEAM (4SB15)
|
LF
|
148.520
|
$210.000
|
$260.000
|
$250.000
|
$248.000
|
$250.000
|
$210.000
|
$235.000
|
|
|
PRESTR CONC SLAB BEAM (5SB15)
|
LF
|
1,336.680
|
$215.000
|
$260.000
|
$250.000
|
$214.000
|
$250.000
|
$210.000
|
$240.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
3.000
|
$550.000
|
$385.000
|
$600.000
|
$767.000
|
$850.000
|
$1,500.000
|
$900.000
|
|
|
RIPRAP (CONC)(CL B)(RR8&RR9)
|
CY
|
101.000
|
$435.000
|
$405.000
|
$400.000
|
$760.000
|
$670.000
|
$850.000
|
$800.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
17.000
|
$550.000
|
$380.000
|
$600.000
|
$793.000
|
$900.000
|
$1,400.000
|
$1,000.000
|
|
|
STR STEEL (MISC NON - BRIDGE)
|
LB
|
380.000
|
$15.000
|
$25.000
|
$15.000
|
$24.000
|
$22.000
|
$25.000
|
$32.000
|
|
|
RAIL (TY T223)
|
LF
|
214.000
|
$175.000
|
$150.000
|
$100.000
|
$187.000
|
$164.000
|
$210.000
|
$200.000
|
|
|
RAIL (TY C223)
|
LF
|
200.000
|
$140.000
|
$250.000
|
$130.000
|
$250.000
|
$248.000
|
$290.000
|
$235.000
|
|
|
RAIL (TY PR11)
|
LF
|
256.000
|
$140.000
|
$150.000
|
$105.000
|
$108.000
|
$156.000
|
$130.000
|
$200.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
102.000
|
$215.000
|
$205.000
|
$175.000
|
$187.000
|
$246.000
|
$225.000
|
$280.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
68.000
|
$100.000
|
$85.000
|
$140.000
|
$212.000
|
$192.000
|
$160.000
|
$95.000
|
|
|
INLET (COMPL)(TY BB)
|
EA
|
2.000
|
$12,000.000
|
$3,500.000
|
$5,000.000
|
$4,200.000
|
$5,000.000
|
$6,200.000
|
$8,500.000
|
|
|
ADJUSTING INLET (CAP)
|
EA
|
2.000
|
$1,500.000
|
$750.000
|
$700.000
|
$2,600.000
|
$900.000
|
$2,500.000
|
$300.000
|
|
|
REMOV STR (INLET)
|
EA
|
1.000
|
$740.000
|
$500.000
|
$400.000
|
$690.000
|
$900.000
|
$2,000.000
|
$900.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$150,000.000
|
$65,000.000
|
$133,000.000
|
$72,000.000
|
$55,000.000
|
$130,000.000
|
$40,000.000
|
|
|
REMOVE STR (RAIL)
|
LF
|
165.000
|
$30.000
|
$12.000
|
$10.000
|
$10.000
|
$10.000
|
$15.000
|
$30.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$229,966.000
|
$215,000.000
|
$250,000.000
|
$280,000.000
|
$270,000.000
|
$300,000.000
|
$275,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$8,050.000
|
$2,500.000
|
$2,000.000
|
$2,400.000
|
$1,400.000
|
$2,100.000
|
$4,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
89.000
|
$38.000
|
$30.000
|
$35.000
|
$48.610
|
$38.000
|
$55.000
|
$50.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
89.000
|
$15.000
|
$10.000
|
$20.000
|
$17.570
|
$15.000
|
$20.000
|
$18.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
333.000
|
$40.000
|
$30.000
|
$35.000
|
$43.950
|
$37.000
|
$50.000
|
$45.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
333.000
|
$10.000
|
$10.000
|
$20.000
|
$13.710
|
$12.000
|
$12.000
|
$14.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
959.000
|
$4.000
|
$4.000
|
$4.000
|
$5.000
|
$5.000
|
$5.000
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
959.000
|
$0.700
|
$1.000
|
$1.500
|
$1.460
|
$1.500
|
$1.000
|
$1.500
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
90.000
|
$5.000
|
$6.000
|
$4.500
|
$6.200
|
$6.000
|
$7.000
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
90.000
|
$1.100
|
$1.000
|
$1.500
|
$2.180
|
$1.500
|
$1.000
|
$2.000
|
|
|
CONC CURB (DOWEL)
|
LF
|
759.000
|
$12.000
|
$9.000
|
$20.000
|
$14.000
|
$24.000
|
$13.000
|
$4.000
|
|
|
CONC CURB (SLOTTED)
|
LF
|
27.000
|
$20.000
|
$15.000
|
$70.000
|
$18.000
|
$56.000
|
$15.000
|
$5.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
158.000
|
$55.000
|
$70.000
|
$111.390
|
$75.000
|
$115.000
|
$120.000
|
$80.000
|
|
|
CURB RAMPS (TY 1)
|
EA
|
1.000
|
$2,700.000
|
$1,650.000
|
$2,500.000
|
$1,570.000
|
$2,700.000
|
$3,500.000
|
$2,500.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
1.000
|
$2,200.000
|
$1,650.000
|
$2,500.000
|
$1,570.000
|
$2,700.000
|
$3,200.000
|
$2,500.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
138.000
|
$25.000
|
$45.000
|
$27.800
|
$27.760
|
$28.000
|
$28.000
|
$30.000
|
|
|
MTL BEAM GD FEN TRANS (TL2)
|
EA
|
4.000
|
$1,300.000
|
$2,000.000
|
$1,578.000
|
$1,578.000
|
$1,600.000
|
$1,600.000
|
$1,600.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,450.000
|
$1,500.000
|
$1,505.000
|
$1,505.000
|
$1,600.000
|
$1,550.000
|
$1,550.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
611.000
|
$3.000
|
$5.000
|
$1.670
|
$1.670
|
$9.000
|
$3.000
|
$10.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$3,400.000
|
$2,850.000
|
$3,115.000
|
$3,115.000
|
$3,000.000
|
$3,200.000
|
$3,000.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
9.000
|
$500.000
|
$850.000
|
$585.000
|
$585.000
|
$600.000
|
$600.000
|
$600.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
7.000
|
$22.000
|
$50.000
|
$25.000
|
$25.000
|
$25.000
|
$25.000
|
$25.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
|
EA
|
6.000
|
$35.000
|
$55.000
|
$25.000
|
$25.000
|
$32.000
|
$25.000
|
$32.000
|
|
|
PAVEMENT SEALER 6"
|
LF
|
2,208.000
|
$0.160
|
$0.200
|
$0.010
|
$0.010
|
$0.010
|
$0.010
|
$0.010
|
|
|
PAVEMENT SEALER 24"
|
LF
|
76.000
|
$0.270
|
$0.200
|
$0.010
|
$0.010
|
$0.010
|
$0.010
|
$0.010
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
14.000
|
$4.500
|
$15.000
|
$10.000
|
$10.000
|
$10.000
|
$10.000
|
$10.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
2,208.000
|
$0.050
|
$0.200
|
$0.050
|
$0.050
|
$0.050
|
$0.050
|
$0.050
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
76.000
|
$0.500
|
$0.250
|
$0.150
|
$0.150
|
$0.150
|
$0.150
|
$0.150
|
|
|
ASBESTOS ABATEMENT (COATINGS)
|
SF
|
400.000
|
$100.000
|
$30.000
|
$25.000
|
$17.000
|
$10.000
|
$30.000
|
$100.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
1.000
|
$9,000.000
|
$18,500.000
|
$9,000.000
|
$6,900.000
|
$10,000.000
|
$10,000.000
|
$18,000.000
|
|
MULTIPOLYMER PAV MRK (W)(6")(SLD)
|
LF
|
1,036.000
|
$0.650
|
$3.000
|
$2.750
|
$2.750
|
$2.800
|
$3.000
|
$3.000
|
|
MULTIPOLYMER PAV MRK (W)(24")(SLD)
|
LF
|
76.000
|
$7.500
|
$13.500
|
$12.500
|
$12.500
|
$12.500
|
$13.000
|
$12.500
|
|
MULTIPOLYMER PAV MRK (Y)(6")(SLD)
|
LF
|
1,172.000
|
$1.000
|
$3.500
|
$2.750
|
$2.750
|
$2.800
|
$3.000
|
$2.750
|
|
|
WATER MAIN PIPE (PVC) (12IN) (C-900)
|
LF
|
567.000
|
$130.000
|
$70.000
|
$120.000
|
$154.000
|
$152.000
|
$150.000
|
$100.000
|
|
|
WATER MAIN PIPE (STL) (12IN)
|
LF
|
190.000
|
$300.000
|
$250.000
|
$240.000
|
$310.000
|
$300.000
|
$320.000
|
$260.000
|
|
|
AIR RELEASE/VACUUM RELEASE VALVE (12IN)
|
EA
|
1.000
|
$6,500.000
|
$6,500.000
|
$960.000
|
$9,300.000
|
$3,000.000
|
$3,700.000
|
$4,000.000
|
|
|
ABAND/FILL EXIST WATER PIPE (12IN)
|
LF
|
475.000
|
$25.000
|
$20.000
|
$3.000
|
$19.000
|
$26.000
|
$14.000
|
$25.000
|
|
Totals: |
$2,586,488.600
|
$2,503,743.900
|
$2,671,421.130
|
$2,828,627.731
|
$2,979,189.540
|
$3,099,873.840
|
$3,157,184.540
|