Show Job Controls
Bid Cobra

CAMERON SH 4 (0039-10-095)

Items: 40

County: CAMERON
Length: 0.0000 MILES (49.0969 MILES)
Highway: SH 4
District: PHARR
Control Number: 0039-10-095
DBE Goal: 0.0%
Project: F 2026(964)
Guaranty: $100,000.00
Time: 206 WORKING DAYS
Engineer's Estimate: $4,670,785.30
Date: 09/03/2026 1:00 PM CDT (16 days ago)
Contract Number: 9263213
Type: PREVENTIVE MAINTENANCE
Project ID: A00197627
Contract Type: FEDERAL
Project Description: SEAL COAT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$4,670,785.30
Over/Under Est: -2.8% -$130,551.37
Over/Under Est: -2.55% -$119,119.31
Amt Left: 0.25% $11,432.06
$4,786,293.27
Over/Under Est: 2.47% $115,507.97
Amt Left: 5.42% $246,059.34
Delta: -5.15% -$234,627.28

Bid Items & Bid Tabulations

40 Total 0 of 40
CAMERON  |  SH 4  |  PHARR  |  0039-10-095  |  09/03/2026 1:00 PM CDT  |  $4,670,785.30  |  F 2026(964)  |  PREVENT MAINT  |  206 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RONALD R. WAGNER & CO., LP
CLARK CONSTRUCTION OF TEXAS, INC.
CK NEWBERRY, LLC
ASPH (SPG 79-13)
GAL 462,424.000 $2.890 $3.682 $2.830 $3.150
AGGR (TY-PD, GR-4P)(SAC-B)
CY 10,881.000 $136.720 $106.050 $123.100 $165.000
MOBILIZATION
LS 1.000 $452,350.000 $820,628.430 $921,719.000 $475,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $5,000.000 $0.010 $10,000.000 $15,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 206.000 $100.000 $0.010 $50.000 $1.000
TMA (STATIONARY)
DAY 206.000 $60.000 $0.010 $1.000 $1.000
TMA (MOBILE OPERATION)
DAY 206.000 $100.000 $0.010 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 2,920.000 $5.000 $5.000 $1.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 2,920.000 $1.000 $5.000 $1.500 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 8,880.000 $1.000 $0.010 $0.010 $0.010
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 30,401.000 $1.000 $0.010 $0.010 $0.010
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 4,568.000 $5.760 $5.500 $5.500 $5.500
RE PM TY II (W) 6" (BRK)
LF 22,335.000 $0.280 $0.180 $0.180 $0.200
RE PM TY II (W) 6" (DOT)
LF 2,340.000 $0.500 $0.180 $0.180 $0.200
RE PM TY II (W) 6" (SLD)
LF 53,510.000 $0.230 $0.180 $0.180 $0.200
RE PM TY II (W) 8" (SLD)
LF 13,483.000 $0.420 $0.280 $0.280 $0.300
RE PM TY II (W) 12" (SLD)
LF 551.000 $0.790 $0.360 $0.360 $0.350
RE PM TY II (Y) 6" (BRK)
LF 62,823.000 $0.400 $0.180 $0.180 $0.200
RE PM TY II (Y) 6" (SLD)
LF 238,705.000 $0.280 $0.150 $0.150 $0.150
RE PM TY II (Y) 12" (SLD)
LF 2,692.000 $1.500 $0.360 $0.360 $0.350
RE PM TY III (W)(6")(SLD)
LF 226.000 $2.160 $10.000 $10.000 $10.000
RE PM TY III (Y)(6")(SLD)
LF 226.000 $2.190 $10.000 $10.000 $10.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 462,365.000 $0.600 $0.600 $0.600 $0.600
PREFAB PM TY C (W)(ARROW)
EA 69.000 $160.000 $125.000 $125.000 $125.000
PREFAB PM TY C (W)(DBL ARROW)
EA 2.000 $280.000 $300.000 $300.000 $300.000
PREFAB PM TY C (W)(WORD)
EA 48.000 $217.100 $200.000 $200.000 $200.000
REFL PAV MRKR TY I-C
EA 28,199.000 $4.500 $3.750 $3.750 $3.750
REFL PAV MRKR TY II-A-A
EA 7,616.000 $4.000 $5.000 $5.000 $5.000
TRAFFIC BUTTON TY Y
EA 54,411.000 $2.500 $1.750 $1.750 $1.750
TRAFFIC BUTTON TY B
EA 85,130.000 $2.500 $1.500 $1.500 $1.500
ELIM EXT PM & MRKS (6")
LF 462,365.000 $0.500 $0.140 $0.140 $0.150
ELIM EXT PM & MRKS (8")
LF 13,483.000 $0.750 $0.280 $0.280 $0.300
ELIM EXT PM & MRKS (12")
LF 3,243.000 $1.580 $0.350 $0.350 $0.350
ELIM EXT PM & MRKS (24")
LF 4,568.000 $2.750 $0.450 $0.450 $0.450
ELIM EXT PM & MRKS (ARROW)
EA 69.000 $40.000 $25.000 $25.000 $25.000
ELIM EXT PM & MRKS (UTURN ARROW)
EA 2.000 $65.000 $25.000 $25.000 $25.000
ELIM EXT PM & MRKS (WORD)
EA 48.000 $48.000 $25.000 $25.000 $25.000
PAV SURF PREP FOR MRK (24")
LF 71.000 $0.500 $0.010 $0.010 $0.010
PAV SURF PREP FOR MRK (ARROW)
EA 3.000 $5.600 $0.010 $0.010 $0.010
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $5.600 $0.010 $0.010 $0.010
Totals: $4,670,785.300 $4,540,233.928 $4,551,665.990 $4,786,293.270
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $90,470.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $226,175.00
Total: $316,645.00