CARSON IH 40 (0275-03-072)

Items: 128

County: CARSON
Length: 0.5540 MILES
Highway: IH 40
District: AMARILLO
Control Number: 0275-03-072
DBE Goal: 0.0%
Project: BR 2026(969)
Guaranty: $100,000.00
Time: 301 WORKING DAYS
Engineer's Estimate: $10,704,179.35
Date: 09/03/2026 1:00 PM CDT (16 days ago)
Contract Number: 9263204
Type: BRIDGE REPLACEMENT
Project ID: A00184830
Contract Type: FEDERAL
Project Description: REPLACE EXISTING BRIDGE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$10,704,179.35
$9,899,342.51
Over/Under Est: -7.52% -$804,836.84
Over/Under Est: 3.73% $399,455.69
Amt Left: 12.17% $1,204,292.53
$11,346,486.00
Over/Under Est: 6% $642,306.65
Amt Left: 14.62% $1,447,143.49
Delta: -2.19% -$242,850.96
Over/Under Est: 20.85% $2,231,516.85
Amt Left: 30.67% $3,036,353.69
Delta: -14.01% -$1,589,210.20
$12,984,816.07
Over/Under Est: 21.31% $2,280,636.72
Amt Left: 31.17% $3,085,473.56
Delta: -0.38% -$49,119.87
Over/Under Est: 21.69% $2,321,924.37
Amt Left: 31.59% $3,126,761.21
Delta: -0.32% -$41,287.65
$13,990,306.25
Over/Under Est: 30.7% $3,286,126.90
Amt Left: 41.33% $4,090,963.74
Delta: -7.40% -$964,202.53

Bid Items & Bid Tabulations

128 Total 0 of 128
CARSON  |  IH 40  |  AMARILLO  |  0275-03-072  |  09/03/2026 1:00 PM CDT  |  $10,704,179.35  |  BR 2026(969)  |  BRIDGE REPL  |  301 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GILVIN-TERRILL, LTD.
L A FULLER & SONS CONSTRUCTION, LTD.
WEBBER, LLC
TEXAS STEEL INDUSTRIAL PLACING, LLC
J. LEE MILLIGAN, INC.
RAGLE CONSTRUCTION, INC.
EARTH BUILDERS, L.P.
REMOV CONC (RIPRAP)
SY 1,142.000 $15.000 $30.000 $29.950 $8.500 $20.000 $35.000 $13.000 $10.000
REMOV CONC (DRIVEWAYS)
SY 379.000 $20.000 $30.000 $32.700 $17.500 $20.000 $40.000 $22.000 $10.000
REMOV CONC (FOUNDATIONS)
SY 86.000 $30.000 $30.000 $54.200 $64.000 $35.000 $205.000 $108.000 $20.000
RMV (16"-20") TRT/UNTRT BASE & ASPH PAV
SY 10,788.000 $20.000 $20.000 $9.750 $15.000 $12.000 $16.000 $20.000 $30.000
EXCAV (ROADWAY)
CY 5,520.000 $14.000 $25.000 $10.650 $29.500 $20.000 $27.000 $60.000 $40.000
EXCAV (CHANNEL)
CY 14,726.000 $14.000 $25.000 $6.700 $10.000 $20.000 $20.000 $25.000 $30.000
EMBANK (FNL)(DC)(TY B)
CY 26,495.000 $24.000 $25.000 $23.500 $11.000 $25.000 $27.750 $40.000 $30.000
BROADCAST SEED (PERM_RURAL_CLAY)
AC 9.390 $1,000.000 $655.000 $888.970 $668.000 $655.000 $710.000 $1,254.240 $1,000.000
DRILL SEED (TEMP_WARM_COOL)
AC 9.900 $1,000.000 $530.000 $888.970 $540.000 $530.000 $570.000 $1,150.680 $1,000.000
FL BS(CMP IN PLC)(TY A,B OR D GR4)(12")
SY 17,579.000 $38.000 $35.000 $23.500 $35.000 $32.000 $38.980 $25.000 $45.000
CEMENT
TON 193.000 $300.000 $230.000 $265.000 $240.000 $250.000 $315.000 $360.000 $300.000
CEMENT TREAT (SUBGRADE) (8")
SY 17,579.000 $5.650 $10.000 $5.600 $2.750 $7.000 $9.000 $3.900 $7.000
PRIME COAT (MC-30)
GAL 4,396.000 $6.000 $10.200 $8.000 $6.950 $15.000 $5.600 $8.500 $10.000
EMULS ASPH (EROSN CONT)(MULTI)
GAL 542.000 $8.000 $10.200 $10.350 $3.900 $21.500 $11.500 $12.300 $30.000
SP MIXES SP-D SAC-A PG70-28
TON 6,539.000 $177.000 $160.000 $185.000 $200.050 $265.000 $180.000 $185.000 $225.000
SP MIXES SP-D SAC-B PG70-28 (LEVEL-UP)
TON 460.000 $300.000 $160.000 $230.000 $200.050 $295.000 $220.000 $202.000 $225.000
TACK COAT
GAL 9,235.000 $7.000 $6.000 $9.900 $8.750 $12.000 $6.000 $6.120 $8.000
PLANE ASPH CONC PAV(0" TO 2")
SY 3,789.000 $3.500 $6.000 $6.100 $6.250 $7.000 $15.000 $6.300 $10.000
CUT & RESTORING PAV
SY 92.000 $150.000 $150.000 $176.550 $315.000 $175.000 $140.000 $185.000 $250.000
CEM STABIL BKFL
CY 323.000 $240.000 $250.000 $255.300 $280.200 $250.000 $365.000 $129.000 $300.000
TRENCH EXCAVATION PROTECTION
LF 75.000 $30.000 $50.000 $9.950 $62.500 $150.000 $270.000 $15.000 $50.000
TEMPORARY SPL SHORING
SF 3,427.000 $50.000 $50.000 $43.500 $17.000 $70.000 $20.000 $33.000 $30.000
DRILL SHAFT (18 IN)
LF 174.000 $80.000 $100.000 $117.000 $140.000 $200.000 $290.000 $136.000 $100.000
DRILL SHAFT (36 IN)
LF 897.000 $325.000 $250.000 $325.000 $275.000 $400.000 $325.000 $277.000 $275.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 40.000 $275.000 $300.000 $316.250 $305.000 $400.000 $320.000 $275.000 $400.000
CL C CONC (ABUT)(HPC)
CY 81.000 $1,750.000 $1,750.000 $2,490.000 $1,975.000 $2,000.000 $1,600.000 $1,165.000 $2,500.000
CL C CONC (CAP)(HPC)
CY 34.600 $1,800.000 $1,750.000 $4,075.000 $1,656.500 $2,500.000 $1,500.000 $1,800.000 $2,500.000
CL C CONC (COLUMN)(HPC)
CY 54.600 $2,000.000 $1,750.000 $1,865.000 $1,595.000 $2,500.000 $2,150.000 $3,400.000 $2,500.000
CL C CONC (RAIL FOUNDATION)
CY 98.000 $840.000 $600.000 $1,035.000 $610.000 $550.000 $1,025.000 $788.000 $2,000.000
REINF CONC SLAB
SF 11,880.000 $40.500 $35.000 $42.000 $35.000 $33.000 $56.000 $33.000 $45.000
APPROACH SLAB
CY 156.000 $900.000 $1,500.000 $1,013.900 $760.000 $650.000 $1,290.000 $733.000 $1,500.000
RETAINING WALL (MSE)
SF 6,260.000 $104.000 $100.000 $79.950 $172.000 $135.000 $165.000 $130.000 $185.000
PRESTR CONC GIRDER (TX34)
LF 2,166.520 $280.000 $300.000 $430.000 $270.000 $230.000 $375.000 $280.000 $325.000
RIPRAP (CONC)(4 IN)
CY 594.000 $830.000 $530.000 $860.000 $710.000 $525.000 $565.000 $691.000 $800.000
RIPRAP (CONC)(5 IN)
CY 107.000 $860.000 $560.000 $720.000 $655.000 $575.000 $755.000 $741.000 $850.000
RIPRAP (CONC)(FLUME)
CY 36.000 $860.000 $800.000 $1,380.250 $890.000 $650.000 $1,140.000 $713.000 $1,250.000
RIPRAP (MOW STRIP)(4 IN)
CY 72.000 $760.000 $600.000 $945.150 $715.000 $650.000 $700.000 $649.000 $800.000
RAIL (TY SSTR)
LF 828.000 $120.000 $110.000 $103.550 $188.000 $104.000 $135.000 $109.000 $175.000
RAIL (TY T80PP-TS)
LF 140.000 $300.000 $365.000 $833.550 $350.000 $430.000 $710.000 $477.000 $300.000
HEADER TYPE EXPANSION JOINT
CF 6.000 $4,000.000 $1,500.000 $742.100 $2,995.000 $600.000 $3,765.000 $480.000 $1,000.000
CONC BOX CULV (6 FT X 2 FT)
LF 370.000 $500.000 $600.000 $592.000 $650.000 $700.000 $600.000 $512.000 $600.000
CONC BOX CULV (6 FT X 2 FT)(EXTEND)
LF 3.000 $1,500.000 $4,000.000 $5,408.450 $4,960.000 $1,500.000 $3,300.000 $5,200.000 $2,000.000
RC PIPE (CL III)(18 IN)
LF 263.000 $120.000 $125.000 $137.100 $135.000 $125.000 $190.000 $100.000 $150.000
SET (TY I)(S= 6 FT)(HW= 3 FT)(6:1)(C)
EA 6.000 $16,200.000 $8,100.000 $24,605.550 $12,605.000 $17,000.000 $21,000.000 $25,000.000 $2,500.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 7.000 $1,630.000 $6,675.000 $3,000.600 $2,400.000 $3,200.000 $3,600.000 $2,700.000 $1,800.000
CLEAN EXIST CULVERTS
EA 1.000 $2,500.000 $5,175.000 $4,703.650 $2,655.000 $11,000.000 $13,000.000 $5,000.000 $7,500.000
REMOV STR (INLET)
EA 1.000 $1,000.000 $2,070.000 $1,901.100 $2,175.000 $3,500.000 $2,500.000 $1,000.000 $1,000.000
REMOV STR (WINGWALL)
EA 4.000 $1,440.000 $2,070.000 $2,557.500 $2,375.000 $3,000.000 $2,500.000 $10,000.000 $1,000.000
REMOV STR (PIPE)
LF 110.000 $50.000 $30.000 $64.450 $46.000 $30.000 $65.000 $19.000 $75.000
REMOV STR (BOX CULVERT)
LF 36.000 $160.000 $30.000 $71.050 $101.000 $500.000 $355.000 $108.000 $150.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $205,000.000 $175,000.000 $230,000.000 $139,280.430 $250,000.000 $320,000.000 $1,100,000.000 $500,000.000
REMOVE STR (RAIL)
LF 36.000 $60.000 $30.000 $133.850 $102.000 $200.000 $83.500 $42.000 $300.000
MOBILIZATION
LS 1.000 $840,000.000 $900,000.000 $1,100,000.000 $1,132,050.000 $1,293,000.000 $1,429,000.000 $1,300,000.000 $1,400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $17,500.000 $10,000.000 $3,367.000 $66,615.000 $20,650.000 $45,000.000 $51,500.000 $8,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $12,000.000 $18,500.000 $20,750.000 $16,900.000 $30,000.000 $22,000.000 $15,000.000 $15,000.000
TMA (STATIONARY)
DAY 300.000 $200.000 $367.000 $634.200 $270.000 $300.000 $425.000 $400.000 $100.000
TMA (MOBILE OPERATION)
HR 40.000 $150.000 $95.000 $94.500 $86.000 $200.000 $100.000 $63.000 $200.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 257.000 $70.000 $37.000 $86.250 $160.000 $156.000 $135.000 $190.520 $200.000
ROCK FILTER DAMS (REMOVE)
LF 257.000 $30.000 $13.000 $20.700 $20.000 $19.500 $50.000 $32.860 $25.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 156.000 $40.000 $39.000 $36.250 $38.000 $36.000 $315.000 $69.620 $50.000
CONSTRUCTION EXITS (REMOVE)
SY 156.000 $15.000 $13.000 $17.500 $14.000 $13.000 $20.000 $16.890 $20.000
CONSTRUCTION PERIMETER FENCE
LF 420.000 $5.000 $25.000 $8.050 $7.150 $10.000 $15.000 $30.000 $20.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 5,391.000 $7.000 $3.750 $6.900 $5.600 $3.750 $6.500 $8.940 $7.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 5,391.000 $3.000 $1.000 $1.150 $1.050 $1.000 $3.700 $1.720 $3.000
CONSTRUCTING DETOURS (TY1)
SY 17,014.000 $53.000 $19.020 $45.500 $28.000 $100.000 $22.000 $30.000 $60.000
CONSTRUCTING DETOURS (TY2)
SY 2,772.000 $70.000 $64.980 $89.700 $97.000 $60.000 $110.000 $98.000 $100.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 2,370.000 $25.000 $7.550 $12.500 $15.000 $20.000 $9.600 $9.000 $40.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 660.000 $10.000 $14.760 $10.600 $7.250 $20.000 $9.900 $9.400 $20.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 2,370.000 $18.000 $7.550 $11.100 $11.250 $20.000 $9.600 $8.400 $30.000
PORT CTB (CONNECTION HARDWARE)
EA 80.000 $1.000 $50.000 $63.600 $139.000 $50.000 $75.000 $100.000 $150.000
DRIVEWAYS (CONC)
SY 500.000 $150.000 $139.500 $210.000 $190.000 $140.000 $190.000 $124.000 $200.000
DRIVEWAYS (ACP)
SY 201.000 $85.000 $71.670 $118.700 $92.500 $100.000 $170.000 $142.000 $150.000
MTL W-BEAM GD FEN (STEEL POST)
LF 100.000 $40.000 $47.000 $54.050 $48.000 $40.000 $41.000 $47.000 $50.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $2,675.000 $3,231.500 $2,725.000 $3,000.000 $3,765.000 $2,675.000 $3,500.000
REMOVE METAL BEAM GUARD FENCE
LF 1,775.000 $4.000 $3.000 $4.130 $3.350 $5.000 $5.400 $3.000 $10.000
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $175.000 $300.000 $345.000 $306.000 $500.000 $540.000 $300.000 $1,000.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 3.000 $200.000 $300.000 $345.000 $306.000 $500.000 $540.000 $300.000 $1,000.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,800.000 $3,400.000 $3,910.000 $3,475.000 $3,500.000 $4,850.000 $3,400.000 $4,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $255.000 $300.000 $345.000 $325.000 $500.000 $540.000 $300.000 $1,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $3,000.000 $3,750.000 $4,312.000 $3,825.000 $2,000.000 $2,700.000 $1,150.000 $4,000.000
CRASH CUSH ATTEN (REMOVE)
EA 8.000 $1,500.000 $2,500.000 $2,875.000 $2,550.000 $1,600.000 $2,150.000 $920.000 $3,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $20,000.000 $33,500.000 $38,525.000 $34,125.000 $40,000.000 $37,650.000 $33,000.000 $36,000.000
CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)
EA 1.000 $29,000.000 $52,500.000 $60,375.000 $53,500.000 $40,000.000 $60,250.000 $55,000.000 $60,000.000
CCA (INSTL)(N)(TL3)(WORK ZONE)
EA 6.000 $10,000.000 $6,750.000 $12,075.000 $10,695.000 $10,000.000 $9,700.000 $10,000.000 $13,000.000
WIRE FENCE (TY C)
LF 492.000 $15.000 $35.000 $17.250 $9.000 $25.000 $35.000 $40.000 $30.000
GATE (TY 1)
EA 1.000 $1,000.000 $500.000 $2,587.500 $1,959.000 $1,500.000 $9,800.000 $3,500.000 $1,000.000
WIRE FENCE (WATER GAP)
LF 33.000 $150.000 $150.000 $97.750 $66.000 $75.000 $65.000 $60.000 $75.000
PIPE UNDERDRAINS (TY 6) (6")
LF 485.000 $25.000 $10.000 $28.000 $26.000 $50.000 $50.000 $41.000 $30.000
RELOCATE EXISTING MAILBOX
EA 1.000 $300.000 $550.000 $621.000 $491.000 $550.000 $945.000 $540.000 $1,000.000
REMOVE RD IL ASM (TRANS-BASE)
EA 2.000 $950.000 $900.000 $1,150.000 $925.000 $500.000 $975.000 $1,000.000 $1,500.000
IN RD IL (TY ST) 50T-8 (400W EQ) LED
EA 4.000 $7,000.000 $7,125.000 $9,200.000 $7,250.000 $3,500.000 $7,700.000 $8,000.000 $13,000.000
CONDT (PVC) (SCH 40) (2")
LF 250.000 $16.000 $15.000 $17.250 $15.500 $20.000 $16.150 $15.000 $20.000
CONDT (PVC) (SCH 80) (2")
LF 475.000 $18.000 $18.000 $28.750 $25.500 $20.000 $19.500 $25.000 $30.000
ELEC CONDR (NO.8) BARE
LF 725.000 $2.000 $2.500 $2.880 $2.600 $5.000 $2.700 $2.500 $3.000
ELEC CONDR (NO.8) INSULATED
LF 1,450.000 $2.500 $3.000 $3.160 $3.050 $5.000 $3.250 $2.750 $4.000
GROUND BOX TY A (122311)W/APRON
EA 5.000 $2,400.000 $1,250.000 $1,840.000 $1,275.000 $1,500.000 $1,345.000 $1,600.000 $2,000.000
REMOVE GROUND BOX
EA 1.000 $350.000 $200.000 $690.000 $205.000 $500.000 $215.000 $600.000 $100.000
REMOVE ELECTRICAL SERVICES
EA 1.000 $750.000 $200.000 $747.500 $205.000 $12,500.000 $215.000 $650.000 $1,000.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 2.000 $12,000.000 $7,725.000 $8,625.000 $7,865.000 $8,000.000 $8,300.000 $7,500.000 $12,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 5.000 $850.000 $990.000 $862.500 $705.000 $990.000 $940.000 $750.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 16.000 $1,100.000 $990.000 $1,035.000 $705.000 $990.000 $1,155.000 $900.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 1.000 $1,500.000 $990.000 $1,380.000 $705.000 $990.000 $1,325.000 $1,200.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $1,400.000 $990.000 $1,380.000 $1,075.000 $990.000 $1,375.000 $1,200.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,400.000 $1,500.000 $1,495.000 $615.000 $1,500.000 $1,490.000 $1,300.000 $2,000.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 2.000 $1,400.000 $1,500.000 $1,667.500 $998.000 $1,500.000 $1,695.000 $1,450.000 $2,000.000
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
EA 2.000 $1,600.000 $1,500.000 $1,840.000 $998.000 $1,500.000 $1,885.000 $1,600.000 $2,000.000
REMOVE SM RD SN SUP&AM
EA 17.000 $115.000 $100.000 $115.000 $225.000 $100.000 $165.000 $200.000 $150.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 16.000 $40.000 $45.000 $55.200 $102.000 $50.000 $54.000 $45.000 $150.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 12.000 $45.000 $45.000 $55.200 $102.000 $50.000 $54.000 $45.000 $150.000
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB
EA 4.000 $40.000 $45.000 $55.200 $102.000 $100.000 $54.000 $45.000 $150.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 8.000 $100.000 $80.000 $138.000 $102.000 $80.000 $130.000 $120.000 $100.000
INSTL OM SM RD SIGN (1-OM-PW)R
EA 4.000 $1.000 $15.000 $14.950 $102.000 $15.000 $43.000 $13.000 $25.000
INSTL OM SM RD SIGN (2-OM-PW)Y
EA 27.000 $1.000 $15.000 $20.700 $102.000 $15.000 $48.500 $18.000 $25.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 10,517.000 $0.500 $1.250 $1.440 $1.300 $1.000 $1.350 $1.250 $1.500
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 9,813.000 $0.500 $1.250 $1.440 $1.300 $1.000 $1.350 $1.250 $1.500
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 113.000 $1.500 $1.500 $1.730 $1.600 $2.000 $1.600 $1.500 $1.750
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,428.000 $1.500 $1.250 $1.440 $1.300 $2.000 $1.350 $1.250 $1.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 138.000 $10.000 $17.500 $20.130 $17.850 $20.000 $18.850 $17.500 $25.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 17,705.000 $0.700 $0.850 $0.980 $0.950 $1.000 $0.900 $0.850 $1.000
TY I HIGH PERF PM (Y)6"(BRK)(100MIL)
LF 330.000 $0.700 $1.000 $1.150 $1.050 $2.000 $1.100 $1.000 $1.250
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 17,587.000 $0.700 $0.850 $0.980 $0.900 $1.000 $0.900 $0.850 $1.000
PREFAB PM TY C (W)(ARROW)
EA 6.000 $250.000 $275.000 $316.250 $280.000 $320.000 $295.000 $275.000 $350.000
PREFAB PM TY C (W)(WORD)
EA 6.000 $250.000 $375.000 $431.250 $382.000 $420.000 $400.000 $375.000 $450.000
REFL PAV MRKR TY I-C
EA 70.000 $9.000 $7.000 $8.050 $7.150 $15.000 $7.550 $7.000 $10.000
REFL PAV MRKR TY II-A-A
EA 470.000 $9.000 $7.000 $8.050 $7.150 $15.000 $7.550 $7.000 $10.000
ELIM EXT PM & MRKS (4")
LF 2,220.000 $1.000 $6.000 $6.900 $6.150 $3.000 $6.450 $6.000 $10.000
ANTI-GRAFFITI COATNG (PERMNENT-TY III)
SF 6,260.000 $2.500 $1.790 $2.060 $1.850 $1.790 $2.150 $2.500 $2.000
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $500.000 $500.000 $575.000 $510.000 $900.000 $540.000 $750.000 $750.000
Totals: $10,704,179.350 $9,899,342.510 $11,103,635.041 $11,346,486.000 $12,935,696.200 $12,984,816.070 $13,026,103.726 $13,990,306.250
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $3,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $10,000.00
Total: $13,000.00