PREPARING ROW
|
STA
|
3.000
|
$3,000.000
|
$4,070.670
|
$5,310.000
|
$7,500.000
|
$8,000.000
|
$20,000.000
|
$8,900.000
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
510.000
|
$15.000
|
$15.350
|
$9.500
|
$25.000
|
$30.000
|
$12.000
|
$4.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,933.000
|
$10.000
|
$27.000
|
$8.250
|
$28.000
|
$50.000
|
$45.000
|
$19.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
4,473.000
|
$15.000
|
$28.500
|
$17.700
|
$31.000
|
$50.000
|
$35.000
|
$29.000
|
|
|
BLOCK SODDING
|
SY
|
714.000
|
$5.000
|
$6.320
|
$7.100
|
$6.000
|
$6.400
|
$7.500
|
$6.500
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
61,143.000
|
$0.100
|
$0.110
|
$0.100
|
$0.100
|
$0.080
|
$0.100
|
$0.100
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
61,143.000
|
$0.100
|
$0.110
|
$0.100
|
$0.100
|
$0.090
|
$0.110
|
$0.100
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
122,272.000
|
$0.150
|
$0.150
|
$0.110
|
$0.140
|
$0.090
|
$0.110
|
$0.150
|
|
|
VEGETATIVE WATERING
|
MG
|
2,054.000
|
$35.000
|
$38.900
|
$20.000
|
$32.140
|
$10.000
|
$34.000
|
$25.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
7,138.000
|
$1.050
|
$1.470
|
$1.180
|
$1.400
|
$1.100
|
$1.300
|
$1.500
|
|
|
CEMENT
|
TON
|
450.000
|
$175.000
|
$165.000
|
$183.000
|
$170.000
|
$165.000
|
$185.000
|
$190.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
40,696.000
|
$8.500
|
$4.760
|
$13.000
|
$6.750
|
$7.000
|
$4.000
|
$4.900
|
|
|
PRIME COAT (MC-30)
|
GAL
|
10,171.000
|
$3.250
|
$4.050
|
$4.450
|
$5.000
|
$4.300
|
$4.300
|
$4.500
|
|
|
EMULS ASPH (PRIME)(MS-2 OR SS-1)
|
GAL
|
32,603.000
|
$3.250
|
$4.030
|
$3.550
|
$4.500
|
$3.000
|
$4.000
|
$4.400
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
|
SY
|
4,472.000
|
$75.000
|
$46.380
|
$56.000
|
$51.000
|
$73.000
|
$62.000
|
$49.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
1,066.000
|
$10.000
|
$9.470
|
$5.300
|
$5.500
|
$10.000
|
$11.000
|
$6.500
|
|
|
CEM STABIL BKFL
|
CY
|
18.000
|
$80.000
|
$157.900
|
$177.000
|
$215.000
|
$160.000
|
$240.000
|
$210.000
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
26.000
|
$90.000
|
$70.780
|
$53.100
|
$137.000
|
$48.000
|
$245.000
|
$190.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
240.000
|
$50.000
|
$84.210
|
$94.400
|
$65.000
|
$85.000
|
$75.000
|
$165.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
99.400
|
$600.000
|
$473.700
|
$531.000
|
$620.000
|
$480.000
|
$750.000
|
$590.000
|
|
|
CMP (GAL STL 18 IN)
|
LF
|
241.000
|
$60.000
|
$36.840
|
$41.300
|
$50.000
|
$37.000
|
$55.000
|
$45.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
94.000
|
$75.000
|
$52.630
|
$59.000
|
$53.000
|
$53.000
|
$60.000
|
$60.000
|
|
|
CMP (GAL STL 36 IN)
|
LF
|
25.000
|
$125.000
|
$73.690
|
$82.600
|
$80.000
|
$74.000
|
$92.000
|
$80.000
|
|
|
CONC BOX CULV (5 FT X 2 FT)(EXTEND)
|
LF
|
33.000
|
$800.000
|
$442.120
|
$495.600
|
$500.000
|
$440.000
|
$575.000
|
$550.000
|
|
|
CONC BOX CULV (5 FT X 3 FT)(EXTEND)
|
LF
|
31.000
|
$850.000
|
$442.120
|
$495.600
|
$525.000
|
$440.000
|
$600.000
|
$570.000
|
|
|
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
|
LF
|
71.000
|
$900.000
|
$547.390
|
$613.600
|
$575.000
|
$550.000
|
$675.000
|
$680.000
|
|
|
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
|
LF
|
16.500
|
$1,000.000
|
$715.810
|
$802.400
|
$825.000
|
$720.000
|
$1,000.000
|
$810.000
|
|
|
CONC BOX CULV (10 FT X 8 FT)(EXTEND)
|
LF
|
6.250
|
$1,500.000
|
$1,042.140
|
$1,168.200
|
$1,450.000
|
$1,100.000
|
$1,700.000
|
$950.000
|
|
|
CONC BOX CULV (5 FT X 6 FT) (EXTEND)
|
LF
|
32.000
|
$1,000.000
|
$1,026.350
|
$1,150.500
|
$675.000
|
$1,100.000
|
$765.000
|
$1,350.000
|
|
|
CONC BOX CULV (6 FT X 2 FT) (EXTEND)
|
LF
|
46.500
|
$900.000
|
$552.650
|
$619.500
|
$510.000
|
$560.000
|
$600.000
|
$650.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
50.000
|
$130.000
|
$136.850
|
$153.400
|
$75.000
|
$136.000
|
$86.000
|
$150.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
133.000
|
$160.000
|
$178.950
|
$200.600
|
$105.000
|
$180.000
|
$117.000
|
$160.000
|
|
|
WINGWALL (FW - 0) (HW=10 FT)
|
EA
|
2.000
|
$15,000.000
|
$24,211.390
|
$27,140.000
|
$21,550.000
|
$24,000.000
|
$25,000.000
|
$30,000.000
|
|
|
WINGWALL (FW - 0) (HW=3 FT)
|
EA
|
6.000
|
$6,000.000
|
$4,737.010
|
$5,310.000
|
$3,230.000
|
$4,800.000
|
$3,700.000
|
$5,500.000
|
|
|
WINGWALL (FW - 0) (HW=4 FT)
|
EA
|
8.000
|
$6,500.000
|
$5,526.510
|
$6,195.000
|
$4,850.000
|
$5,600.000
|
$5,500.000
|
$7,000.000
|
|
|
WINGWALL (FW - 0) (HW=5 FT)
|
EA
|
2.000
|
$6,750.000
|
$8,947.690
|
$10,030.000
|
$7,525.000
|
$9,000.000
|
$8,500.000
|
$9,000.000
|
|
|
WINGWALL (FW - 0) (HW=7 FT)
|
EA
|
4.000
|
$7,500.000
|
$11,053.020
|
$12,390.000
|
$9,700.000
|
$11,000.000
|
$11,000.000
|
$12,500.000
|
|
|
WINGWALL (FW - 0) (HW=8 FT)
|
EA
|
2.000
|
$10,000.000
|
$15,790.040
|
$17,700.000
|
$14,000.000
|
$16,000.000
|
$16,000.000
|
$19,000.000
|
|
|
SET (TY II) (18 IN) (CMP) (6: 1) (P)
|
EA
|
10.000
|
$1,025.000
|
$1,000.040
|
$1,121.000
|
$1,050.000
|
$1,000.000
|
$1,200.000
|
$1,400.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
8.000
|
$1,000.000
|
$947.400
|
$1,062.000
|
$970.000
|
$1,000.000
|
$1,100.000
|
$1,100.000
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
6.000
|
$1,155.000
|
$1,368.470
|
$1,534.000
|
$1,225.000
|
$1,400.000
|
$1,400.000
|
$1,800.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$2,100.000
|
$1,263.200
|
$1,416.000
|
$1,130.000
|
$1,400.000
|
$1,300.000
|
$1,800.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
6.000
|
$2,655.000
|
$2,631.670
|
$2,950.000
|
$2,500.000
|
$2,600.000
|
$3,000.000
|
$3,500.000
|
|
|
SET (TY II) (36 IN) (CMP) (6: 1) (P)
|
EA
|
2.000
|
$4,000.000
|
$3,684.340
|
$4,130.000
|
$4,850.000
|
$3,700.000
|
$5,500.000
|
$3,900.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
24.000
|
$1,000.000
|
$526.330
|
$590.000
|
$750.000
|
$550.000
|
$865.000
|
$900.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
8.000
|
$750.000
|
$675.430
|
$590.000
|
$750.000
|
$550.000
|
$865.000
|
$700.000
|
|
|
REMOV STR (PIPE)
|
LF
|
532.000
|
$13.000
|
$10.530
|
$11.800
|
$11.000
|
$11.000
|
$13.000
|
$19.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$441,000.000
|
$400,000.000
|
$400,000.000
|
$270,000.000
|
$410,000.000
|
$491,357.000
|
$490,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$10,000.000
|
$5,000.000
|
$8,800.000
|
$25,000.000
|
$9,500.000
|
$10,000.000
|
$23,000.000
|
|
|
TEMP PAVED FLUME (INSTALL)
|
SY
|
450.000
|
$30.000
|
$17.900
|
$20.000
|
$31.000
|
$58.000
|
$28.000
|
$70.000
|
|
|
TEMP PAVED FLUME (REMOVE)
|
SY
|
450.000
|
$10.000
|
$10.530
|
$15.000
|
$10.000
|
$12.000
|
$11.000
|
$15.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,915.000
|
$2.900
|
$3.160
|
$2.450
|
$3.000
|
$2.500
|
$2.650
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,915.000
|
$0.600
|
$1.050
|
$1.100
|
$1.000
|
$1.000
|
$1.100
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
2,180.000
|
$4.500
|
$6.320
|
$3.500
|
$6.000
|
$3.500
|
$3.600
|
$7.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
2,180.000
|
$0.850
|
$1.050
|
$0.900
|
$1.000
|
$1.000
|
$0.950
|
$1.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,943.000
|
$33.000
|
$22.170
|
$27.750
|
$43.000
|
$45.000
|
$27.000
|
$34.000
|
|
|
TURNOUTS (ACP)
|
SY
|
198.000
|
$30.000
|
$40.300
|
$41.500
|
$60.000
|
$38.000
|
$52.000
|
$69.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
2,144.000
|
$23.000
|
$21.980
|
$20.000
|
$32.000
|
$14.000
|
$25.000
|
$15.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
71,750.000
|
$0.150
|
$0.220
|
$0.260
|
$0.230
|
$0.230
|
$0.160
|
$0.120
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
35,875.000
|
$0.150
|
$0.410
|
$0.500
|
$0.230
|
$0.230
|
$0.210
|
$0.180
|
|
|
WIRE FENCE (TY C)
|
LF
|
60.000
|
$10.000
|
$56.130
|
$35.000
|
$100.000
|
$18.000
|
$23.000
|
$19.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
9.000
|
$275.000
|
$315.800
|
$354.000
|
$350.000
|
$350.000
|
$265.000
|
$290.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
12.000
|
$600.000
|
$815.820
|
$914.500
|
$900.000
|
$900.000
|
$500.000
|
$430.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
20.000
|
$650.000
|
$947.400
|
$1,062.000
|
$1,050.000
|
$1,100.000
|
$665.000
|
$570.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
6.000
|
$720.000
|
$1,052.670
|
$1,180.000
|
$1,200.000
|
$1,200.000
|
$833.000
|
$700.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-2EXT)
|
EA
|
1.000
|
$920.000
|
$1,210.570
|
$1,357.000
|
$1,350.000
|
$1,300.000
|
$1,090.000
|
$900.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
39.000
|
$85.000
|
$105.270
|
$118.000
|
$115.000
|
$120.000
|
$95.000
|
$110.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
26.000
|
$85.000
|
$147.370
|
$165.200
|
$165.000
|
$160.000
|
$120.000
|
$100.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
3,816.000
|
$1.000
|
$1.140
|
$1.000
|
$2.250
|
$0.500
|
$1.100
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
73,316.000
|
$0.340
|
$0.440
|
$0.540
|
$0.450
|
$0.440
|
$0.510
|
$0.450
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
8,920.000
|
$0.360
|
$0.440
|
$0.860
|
$0.450
|
$0.440
|
$0.510
|
$0.450
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
21,636.000
|
$0.340
|
$0.440
|
$0.860
|
$0.450
|
$0.440
|
$0.510
|
$0.450
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
98.000
|
$15.000
|
$21.050
|
$23.600
|
$21.000
|
$21.000
|
$25.000
|
$21.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
681.000
|
$3.750
|
$3.680
|
$7.080
|
$3.650
|
$4.000
|
$4.250
|
$3.700
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
8,058.000
|
$115.000
|
$76.000
|
$88.000
|
$79.000
|
$102.000
|
$97.000
|
$99.000
|
|
|
SP MIXES SP-D SAC-B PG70-22
|
TON
|
12,873.000
|
$110.000
|
$95.000
|
$94.000
|
$108.000
|
$100.000
|
$111.000
|
$107.000
|
|
|
TACK COAT
|
GAL
|
4,671.000
|
$3.250
|
$4.030
|
$3.750
|
$4.500
|
$3.500
|
$3.300
|
$5.500
|
|
|
TMA (STATIONARY)
|
DAY
|
170.000
|
$200.000
|
$249.150
|
$300.000
|
$1,100.000
|
$280.000
|
$235.000
|
$60.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
5.000
|
$2,000.000
|
$1,796.290
|
$177.000
|
$1,200.000
|
$650.000
|
$235.000
|
$390.000
|
|
Totals: |
$4,968,612.430
|
$4,202,296.735
|
$4,652,222.340
|
$4,838,380.240
|
$4,866,647.920
|
$4,938,029.520
|
$4,963,254.100
|