COLLIN US 75 (0047-06-159)
Items: 15
County: COLLIN
Length: N/A
Highway: US 75
District: DALLAS
Control Number: 0047-06-159
DBE Goal: N/A
Project: NH 2017(885)
Guaranty: N/A
Time: 74 WORKING DAYS
Engineer's Estimate: $723,127.00
Date: 03/07/2017 (9 years ago)
Contract Number: N/A
Type: FULL DEPTH CONCRETE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
E
Engineer's Estimate
$723,127.00
1
Awarded
$657,809.00
Over/Under Est:
-9.03%
-$65,318.00
$661,676.50
Over/Under Est:
-8.5%
-$61,450.50
Amt Left:
0.59%
$3,867.50
$663,040.00
Over/Under Est:
-8.31%
-$60,087.00
Amt Left:
0.8%
$5,231.00
Delta:
-0.21%
-$1,363.50
$805,488.00
Over/Under Est:
11.39%
$82,361.00
Amt Left:
22.45%
$147,679.00
Delta:
-21.48%
-$142,448.00
$989,409.40
Over/Under Est:
36.82%
$266,282.40
Amt Left:
50.41%
$331,600.40
Delta:
-22.83%
-$183,921.40
$1,044,684.50
Over/Under Est:
44.47%
$321,557.50
Amt Left:
58.81%
$386,875.50
Delta:
-5.59%
-$55,275.10
Bid Items & Bid Tabulations
15
Total
0 of 15
