COMAL SL 337 (0216-01-062)
Items: 15
County: COMAL
Length: 6.2420 MILES (5.5567 MILES)
Highway: SL 337
District: SAN ANTONIO
Control Number: 0216-01-062
DBE Goal: 0.0%
Project: STP 2026(536)HES
Guaranty: $21,000.00
Time: 104 WORKING DAYS
Engineer's Estimate: $1,034,120.20
Date: 04/08/2026 1:00 PM CDT (5 months ago)
Contract Number: 4263224
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193396
Contract Type: FEDERAL
Project Description: INSTALL SAFETY LIGHTING AT RAMPS AND INTERSECTIONS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ELVIA VALDEZ
JEB SMITH
MICHAEL DONOVAN
LUKE STORY
COMAL SL 337 (0216-01-062)
Project Name: N/A
Project: STP 2026(536)HES
Engineer's Estimate: $589,966.45
Length: 2.6230 MILES (2.4005 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: W SAN ANTONIO ST
Limits To: SH 46
Project Description: INSTALL SAFETY LIGHTING AT RAMPS AND INTERSECTIONS
COMAL SH 46 (0216-01-063)
Project Name: SAT_SH0046_5
Project: STP 2026(536)HES
Engineer's Estimate: $444,153.75
Length: 3.6190 MILES (3.1562 MILES)
Project Class: SAFETY IMPROVEMENT PROJECTS
Limits From: SL 337
Limits To: RIVERCREST DR.
Project Description: INSTALL SAFETY LIGHTING AT RAMPS AND INTERSECTIONS
Pay Estimates:
Documents
2 files available
Bidders (10)
E
Engineer's Estimate
$1,034,120.20
1
Awarded
$816,253.50
Over/Under Est:
-21.07%
-$217,866.70
$876,966.55
Over/Under Est:
-15.2%
-$157,153.65
Amt Left:
7.44%
$60,713.05
$908,256.70
Over/Under Est:
-12.17%
-$125,863.50
Amt Left:
11.27%
$92,003.20
Delta:
-3.57%
-$31,290.15
$909,540.49
Over/Under Est:
-12.05%
-$124,579.71
Amt Left:
11.43%
$93,286.99
Delta:
-0.14%
-$1,283.79
$965,680.12
Over/Under Est:
-6.62%
-$68,440.08
Amt Left:
18.31%
$149,426.62
Delta:
-6.17%
-$56,139.63
6
$1,067,198.10
Over/Under Est:
3.2%
$33,077.90
Amt Left:
30.74%
$250,944.60
Delta:
-10.51%
-$101,517.98
$1,151,851.50
Over/Under Est:
11.38%
$117,731.30
Amt Left:
41.11%
$335,598.00
Delta:
-7.93%
-$84,653.40
$1,183,605.50
Over/Under Est:
14.46%
$149,485.30
Amt Left:
45%
$367,352.00
Delta:
-2.76%
-$31,754.00
$1,267,888.00
Over/Under Est:
22.61%
$233,767.80
Amt Left:
55.33%
$451,634.50
Delta:
-7.12%
-$84,282.50
$1,313,299.30
Over/Under Est:
27%
$279,179.10
Amt Left:
60.89%
$497,045.80
Delta:
-3.58%
-$45,411.30
Bid Items & Bid Tabulations
15
Total
0 of 15
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $500.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $500.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $2,000.00 |
