EXCAVATION (ROADWAY)
|
CY
|
4,933.000
|
$25.000
|
$12.000
|
$6.400
|
$15.130
|
$15.000
|
$11.000
|
|
|
|
BLADING
|
STA
|
193.000
|
$400.000
|
$120.000
|
$44.300
|
$148.400
|
$175.000
|
$110.000
|
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
SY
|
43,318.000
|
$0.700
|
$0.110
|
$0.100
|
$0.090
|
$0.100
|
$0.090
|
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
21,659.000
|
$0.700
|
$0.110
|
$0.070
|
$0.070
|
$0.100
|
$0.070
|
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
21,659.000
|
$0.700
|
$0.110
|
$0.080
|
$0.080
|
$0.100
|
$0.080
|
|
|
|
VEGETATIVE WATERING
|
MG
|
1,924.000
|
$30.000
|
$13.750
|
$10.000
|
$12.480
|
$12.000
|
$0.010
|
|
|
|
PROOF ROLLING
|
HR
|
65.000
|
$100.000
|
$95.000
|
$65.000
|
$84.800
|
$125.000
|
$95.000
|
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
32,073.000
|
$36.000
|
$34.850
|
$48.900
|
$48.590
|
$38.000
|
$54.000
|
|
|
|
REWORK BS MTL (TY C)(10")(DENS CONT)
|
SY
|
83,797.000
|
$2.500
|
$1.900
|
$1.050
|
$2.330
|
$2.000
|
$2.300
|
|
|
|
PRIME COAT (RC-250)
|
GAL
|
20,034.000
|
$4.500
|
$3.750
|
$3.800
|
$3.590
|
$3.700
|
$3.500
|
|
|
|
AGGR(TY-PB GR-3 SAC-B)
|
CY
|
813.000
|
$110.000
|
$73.500
|
$109.000
|
$85.400
|
$110.000
|
$90.000
|
|
|
|
AGGR(TY-PB GR-5 SAC-B)
|
CY
|
729.000
|
$105.000
|
$69.500
|
$113.650
|
$91.760
|
$110.000
|
$90.000
|
|
|
|
ASPH (AC 20-5TR OR CRS-1P)
|
GAL
|
33,146.000
|
$3.250
|
$3.550
|
$3.000
|
$2.920
|
$3.250
|
$3.300
|
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
4,177.000
|
$100.000
|
$100.000
|
$89.150
|
$89.330
|
$85.000
|
$100.000
|
|
|
|
TOM (ASPHALT) PG 76-22
|
TON
|
1,081.000
|
$95.000
|
$118.750
|
$108.600
|
$109.920
|
$127.000
|
$110.000
|
|
|
|
TOM - C (AGGREGATE) SAC - B
|
TON
|
15,545.000
|
$95.000
|
$118.750
|
$108.600
|
$109.920
|
$127.000
|
$110.000
|
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 4")
|
SY
|
1,027.000
|
$9.000
|
$4.000
|
$6.600
|
$9.540
|
$7.000
|
$6.000
|
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
38.350
|
$1,200.000
|
$655.000
|
$337.250
|
$500.000
|
$1,850.000
|
$600.000
|
|
|
|
CONC STR REPAIR(DECK REP(PART DEPTH))
|
SF
|
50.000
|
$200.000
|
$306.000
|
$140.000
|
$95.000
|
$150.000
|
$125.000
|
|
|
|
CONC STR REPAIR (STANDARD)
|
SF
|
33.330
|
$300.000
|
$306.000
|
$175.000
|
$200.000
|
$160.000
|
$155.000
|
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
20.000
|
$700.000
|
$695.000
|
$325.000
|
$600.000
|
$550.000
|
$500.000
|
|
|
|
CLEANING AND SEALING EXIST JOINTS(CL7)
|
LF
|
370.000
|
$30.000
|
$25.000
|
$47.000
|
$36.000
|
$45.000
|
$34.000
|
|
|
|
RETROFIT RAIL (TY SSTR)
|
LF
|
251.000
|
$200.000
|
$205.000
|
$250.000
|
$250.000
|
$175.000
|
$191.000
|
|
|
|
CMP AR (GAL STL DES 3)
|
LF
|
42.000
|
$100.000
|
$44.000
|
$100.000
|
$90.000
|
$80.000
|
$70.000
|
|
|
|
SET (TY I) (DES 3) (CMP) (6: 1) (C)
|
EA
|
2.000
|
$2,500.000
|
$1,450.000
|
$1,200.000
|
$1,600.000
|
$2,500.000
|
$2,500.000
|
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$467,733.000
|
$350,000.000
|
$443,145.000
|
$502,876.730
|
$550,000.000
|
$658,500.000
|
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
14.000
|
$5,000.000
|
$5,225.000
|
$7,000.000
|
$3,392.000
|
$5,000.000
|
$12,500.000
|
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
80.000
|
$28.000
|
$44.000
|
$22.000
|
$36.000
|
$25.000
|
$20.000
|
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
80.000
|
$10.000
|
$12.000
|
$10.000
|
$10.000
|
$5.000
|
$15.000
|
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
420.000
|
$2.500
|
$3.000
|
$3.500
|
$3.100
|
$4.000
|
$3.100
|
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
420.000
|
$1.000
|
$1.500
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
165.000
|
$5.000
|
$6.000
|
$7.000
|
$6.000
|
$5.000
|
$6.000
|
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
165.000
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
$1.000
|
|
|
|
PORT CTB (DES SOURCE)(SAFETY SH)
|
LF
|
350.000
|
$25.000
|
$10.500
|
$29.000
|
$35.000
|
$18.000
|
$15.000
|
|
|
|
PORT CTB (MOVE)(SAFETY SH)
|
LF
|
350.000
|
$17.000
|
$9.500
|
$19.000
|
$12.000
|
$8.000
|
$6.000
|
|
|
|
PORT CTB (STKPL)(SAFETY SH)
|
LF
|
350.000
|
$22.000
|
$10.500
|
$25.000
|
$22.000
|
$18.000
|
$15.000
|
|
|
|
INTERSECTIONS (ACP)
|
SY
|
682.800
|
$40.000
|
$79.250
|
$51.500
|
$32.720
|
$60.000
|
$65.000
|
|
|
|
INTERSECTIONS (SURF TREAT)
|
SY
|
455.200
|
$30.000
|
$19.000
|
$52.000
|
$21.600
|
$40.000
|
$75.000
|
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
1,128.600
|
$35.000
|
$19.000
|
$41.000
|
$21.420
|
$25.000
|
$50.000
|
|
|
|
TURNOUTS (SURF TREAT)
|
SY
|
138.600
|
$30.000
|
$19.000
|
$58.000
|
$21.420
|
$35.000
|
$50.000
|
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
400.000
|
$30.000
|
$21.650
|
$21.000
|
$19.500
|
$20.000
|
$19.500
|
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$2,200.000
|
$1,610.000
|
$1,585.000
|
$1,450.000
|
$1,900.000
|
$1,450.000
|
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
970.000
|
$3.000
|
$2.000
|
$3.000
|
$1.750
|
$3.000
|
$1.750
|
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,800.000
|
$2,225.000
|
$3,140.000
|
$1,990.000
|
$2,825.000
|
$1,990.000
|
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
2.000
|
$12,500.000
|
$12,650.000
|
$10,000.000
|
$9,500.000
|
$9,000.000
|
$9,000.000
|
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$2,000.000
|
$2,100.000
|
$2,500.000
|
$1,500.000
|
$2,500.000
|
$1,250.000
|
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$1,100.000
|
$1,150.000
|
$1,000.000
|
$1,000.000
|
$1,000.000
|
$750.000
|
|
|
|
PIPE UNDERDRAINS (TY 7) (6")
|
LF
|
150.000
|
$50.000
|
$21.000
|
$55.000
|
$25.000
|
$35.000
|
$25.000
|
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 2
|
EA
|
13.000
|
$200.000
|
$240.000
|
$240.000
|
$215.000
|
$200.000
|
$215.000
|
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
1.000
|
$230.000
|
$300.000
|
$300.000
|
$270.000
|
$250.000
|
$270.000
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$550.000
|
$635.000
|
$565.000
|
$570.000
|
$450.000
|
$570.000
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
3.000
|
$750.000
|
$790.000
|
$790.000
|
$710.000
|
$500.000
|
$710.000
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
1.000
|
$549.000
|
$900.000
|
$900.000
|
$810.000
|
$550.000
|
$810.000
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
|
EA
|
2.000
|
$1,000.000
|
$1,000.000
|
$955.000
|
$895.000
|
$550.000
|
$895.000
|
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
18.000
|
$550.000
|
$365.000
|
$361.000
|
$325.000
|
$300.000
|
$325.000
|
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
12.000
|
$450.000
|
$440.000
|
$440.000
|
$395.000
|
$375.000
|
$395.000
|
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$250.000
|
$450.000
|
$420.000
|
$375.000
|
$300.000
|
$375.000
|
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
38.000
|
$85.000
|
$78.000
|
$80.000
|
$70.000
|
$75.000
|
$70.000
|
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
12.000
|
$30.000
|
$22.000
|
$27.000
|
$30.000
|
$30.000
|
$27.000
|
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
12.000
|
$400.000
|
$23.000
|
$32.000
|
$40.000
|
$30.000
|
$35.000
|
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
82,100.000
|
$0.400
|
$0.140
|
$0.140
|
$0.130
|
$0.150
|
$0.130
|
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
82,100.000
|
$0.400
|
$0.300
|
$0.300
|
$0.270
|
$0.270
|
$0.270
|
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
4,100.000
|
$0.950
|
$0.830
|
$0.830
|
$0.750
|
$1.000
|
$0.750
|
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
7,200.000
|
$0.750
|
$0.830
|
$0.830
|
$0.750
|
$1.000
|
$0.750
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
421.000
|
$1.200
|
$1.500
|
$1.000
|
$1.040
|
$1.000
|
$1.200
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
3,396.000
|
$1.200
|
$1.250
|
$1.000
|
$1.040
|
$1.000
|
$1.200
|
|
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
47.000
|
$4.800
|
$34.000
|
$33.000
|
$30.000
|
$30.000
|
$30.000
|
|
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
5,381.000
|
$0.550
|
$0.390
|
$0.390
|
$0.350
|
$0.350
|
$0.350
|
|
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
107,526.000
|
$0.500
|
$0.320
|
$0.320
|
$0.290
|
$0.300
|
$0.290
|
|
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
10,300.000
|
$0.500
|
$0.390
|
$0.390
|
$0.350
|
$0.350
|
$0.350
|
|
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
51,242.000
|
$0.500
|
$0.330
|
$0.330
|
$0.300
|
$0.300
|
$0.300
|
|
|
|
REFL PAV MRKR TY I-C
|
EA
|
479.000
|
$6.000
|
$3.880
|
$3.900
|
$3.500
|
$4.000
|
$3.500
|
|
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,161.000
|
$5.000
|
$4.220
|
$4.250
|
$3.800
|
$4.000
|
$3.800
|
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
25,610.000
|
$1.000
|
$0.550
|
$0.650
|
$0.550
|
$1.000
|
$0.500
|
|
|
|
TEMP TRAF SIGNALS
|
EA
|
2.000
|
$500.000
|
$7,500.000
|
$4,800.000
|
$2,000.000
|
$15,000.000
|
$25,000.000
|
|
|
|
TMA (STATIONARY)
|
DAY
|
26.000
|
$400.000
|
$210.000
|
$400.000
|
$300.000
|
$700.000
|
$300.000
|
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
360.000
|
$50.000
|
$35.000
|
$18.000
|
$70.000
|
$75.000
|
$30.000
|
|
1
|
|
TOM-C (AGGREGATE) SAC-A
|
TON
|
15,545.000
|
$95.000
|
$0.000
|
$0.000
|
$0.000
|
$0.000
|
$0.000
|
|
Totals: |
$6,694,572.750
|
$5,024,304.050
|
$5,332,186.608
|
$5,419,222.250
|
$5,567,195.950
|
$5,963,972.450
|