REMOVING CONC (CURB)
|
LF
|
20.000
|
$10.000
|
$35.000
|
$150.000
|
$15.000
|
$20.000
|
$100.000
|
$40.390
|
$50.000
|
$20.000
|
|
|
REMOVING STAB BASE & ASPH PAV (18")
|
SY
|
5,287.000
|
$15.000
|
$12.000
|
$8.000
|
$15.000
|
$10.500
|
$10.000
|
$8.330
|
$15.000
|
$15.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
159.000
|
$5.000
|
$66.000
|
$75.000
|
$25.000
|
$10.000
|
$50.000
|
$3.950
|
$20.000
|
$70.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
1,466.000
|
$25.000
|
$26.470
|
$75.000
|
$25.000
|
$28.000
|
$50.000
|
$7.260
|
$30.000
|
$70.000
|
|
|
BACKFILL (TY B)
|
STA
|
3.000
|
$155.000
|
$9,830.070
|
$1,000.000
|
$500.000
|
$750.000
|
$500.000
|
$386.400
|
$1,000.000
|
$3,000.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
8,775.000
|
$1.750
|
$1.630
|
$1.500
|
$1.500
|
$2.400
|
$1.250
|
$0.910
|
$5.000
|
$2.500
|
|
|
BLOCK SODDING
|
SY
|
8,775.000
|
$2.710
|
$3.260
|
$3.250
|
$3.250
|
$3.300
|
$4.000
|
$2.990
|
$6.000
|
$3.000
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
8,775.000
|
$0.250
|
$0.220
|
$0.500
|
$0.250
|
$0.200
|
$0.180
|
$0.180
|
$1.000
|
$0.180
|
|
|
VEGETATIVE WATERING
|
MG
|
147.000
|
$25.000
|
$95.000
|
$50.000
|
$100.000
|
$50.000
|
$115.000
|
$127.850
|
$1.000
|
$30.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY C)
|
SY
|
932.000
|
$3.500
|
$3.150
|
$3.500
|
$3.000
|
$3.200
|
$3.150
|
$2.890
|
$4.000
|
$2.500
|
|
|
FL BS (CMP IN PLC)(TY A OR B GR 4)(8")
|
SY
|
2,282.000
|
$20.000
|
$18.990
|
$30.000
|
$60.000
|
$15.500
|
$35.000
|
$19.810
|
$35.000
|
$30.000
|
|
|
LIME (HYDRATED LIME (SLURRY))
|
TON
|
107.000
|
$250.000
|
$251.910
|
$220.000
|
$250.000
|
$200.000
|
$250.000
|
$218.110
|
$250.000
|
$250.000
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
5,352.000
|
$3.000
|
$9.830
|
$6.000
|
$8.000
|
$5.000
|
$12.000
|
$9.350
|
$10.000
|
$20.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
1,239.000
|
$6.000
|
$3.900
|
$4.000
|
$5.000
|
$3.900
|
$3.760
|
$3.500
|
$10.000
|
$5.000
|
|
|
CONC PVMT (CONT REINF - CRCP) (8")
|
SY
|
2,554.000
|
$90.000
|
$95.000
|
$103.000
|
$80.000
|
$95.000
|
$125.000
|
$90.000
|
$75.000
|
$123.000
|
|
|
CEM STABIL BKFL
|
CY
|
450.000
|
$87.000
|
$106.070
|
$220.000
|
$200.000
|
$124.000
|
$250.000
|
$153.780
|
$200.000
|
$200.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,120.000
|
$25.000
|
$30.350
|
$61.000
|
$40.000
|
$65.000
|
$55.000
|
$24.070
|
$50.000
|
$40.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
156.000
|
$106.000
|
$125.000
|
$175.000
|
$125.000
|
$110.000
|
$100.000
|
$98.710
|
$100.000
|
$200.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
1,164.000
|
$195.000
|
$232.000
|
$250.000
|
$300.000
|
$225.000
|
$200.000
|
$211.530
|
$195.000
|
$300.000
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
24.000
|
$250.000
|
$360.000
|
$255.000
|
$400.000
|
$365.000
|
$425.000
|
$298.000
|
$350.000
|
$270.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
103.000
|
$1,200.000
|
$925.000
|
$1,500.000
|
$1,500.000
|
$1,100.000
|
$1,300.000
|
$1,761.960
|
$1,600.000
|
$2,500.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
65.800
|
$1,300.000
|
$1,600.000
|
$1,500.000
|
$1,500.000
|
$1,400.000
|
$2,000.000
|
$2,064.710
|
$1,600.000
|
$2,500.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
69.200
|
$1,050.000
|
$1,100.000
|
$1,200.000
|
$1,500.000
|
$1,200.000
|
$1,500.000
|
$1,537.920
|
$1,600.000
|
$2,500.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
25,200.000
|
$26.000
|
$16.000
|
$21.000
|
$25.000
|
$21.000
|
$22.000
|
$22.810
|
$22.000
|
$40.000
|
|
|
BRIDGE SIDEWALK (HPC)
|
SF
|
7,000.000
|
$13.000
|
$11.700
|
$12.000
|
$15.000
|
$8.400
|
$13.000
|
$17.890
|
$25.000
|
$15.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
115.600
|
$695.000
|
$650.000
|
$900.000
|
$750.000
|
$620.000
|
$750.000
|
$772.920
|
$850.000
|
$775.000
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
4,101.000
|
$175.000
|
$200.000
|
$190.000
|
$225.000
|
$225.000
|
$300.000
|
$239.740
|
$315.000
|
$215.000
|
|
|
RIPRAP (STONE PROTECTION)(30 IN)
|
CY
|
1,533.400
|
$271.490
|
$94.000
|
$155.000
|
$100.000
|
$100.000
|
$105.000
|
$180.090
|
$150.000
|
$200.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
20.000
|
$600.000
|
$450.000
|
$700.000
|
$500.000
|
$950.000
|
$800.000
|
$643.100
|
$550.000
|
$875.000
|
|
|
STR STEEL (MISC NON - BRIDGE)
|
LB
|
504.000
|
$18.000
|
$21.000
|
$30.000
|
$20.000
|
$17.500
|
$20.000
|
$27.340
|
$30.000
|
$20.000
|
|
|
RAIL (TY C402)(HPC)
|
LF
|
772.000
|
$141.920
|
$165.000
|
$275.000
|
$180.000
|
$185.000
|
$210.000
|
$177.660
|
$200.000
|
$235.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
143.000
|
$130.500
|
$148.000
|
$175.000
|
$150.000
|
$150.000
|
$125.000
|
$191.880
|
$150.000
|
$190.000
|
|
|
RAISING EXIST STRUCT
|
LS
|
1.000
|
$120,000.000
|
$100,000.000
|
$20,000.000
|
$40,000.000
|
$702,850.000
|
$95,000.000
|
$480,000.000
|
$150,000.000
|
$500,000.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$100,000.000
|
$192,578.590
|
$150,000.000
|
$250,000.000
|
$250,000.000
|
$210,000.000
|
$478,400.000
|
$200,000.000
|
$300,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$440,000.000
|
$472,915.620
|
$500,000.000
|
$550,000.000
|
$560,450.000
|
$592,000.000
|
$575,000.000
|
$550,000.000
|
$700,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
16.000
|
$14,000.000
|
$7,000.000
|
$5,500.000
|
$4,000.000
|
$6,000.000
|
$14,700.000
|
$5,300.250
|
$10,000.000
|
$25,000.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$25.000
|
$29.000
|
$28.000
|
$30.000
|
$28.000
|
$28.280
|
$22.500
|
$5.000
|
$25.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$10.000
|
$9.000
|
$9.000
|
$10.000
|
$7.800
|
$8.250
|
$12.000
|
$1.000
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,358.000
|
$3.000
|
$3.000
|
$5.000
|
$3.000
|
$2.700
|
$3.050
|
$1.700
|
$1.000
|
$2.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,358.000
|
$1.100
|
$0.700
|
$2.000
|
$1.000
|
$0.550
|
$0.600
|
$0.250
|
$1.000
|
$0.250
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
12.000
|
$5.000
|
$12.000
|
$10.000
|
$20.000
|
$9.000
|
$21.000
|
$5.000
|
$10.000
|
$7.500
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
12.000
|
$1.000
|
$1.800
|
$5.000
|
$2.000
|
$1.900
|
$10.500
|
$1.000
|
$10.000
|
$1.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
156.000
|
$55.000
|
$363.050
|
$300.000
|
$225.000
|
$310.000
|
$300.000
|
$181.550
|
$600.000
|
$90.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
1,800.000
|
$50.000
|
$30.000
|
$55.000
|
$85.000
|
$32.000
|
$30.000
|
$44.020
|
$95.000
|
$80.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
1,260.000
|
$20.000
|
$3.600
|
$15.000
|
$10.000
|
$6.000
|
$10.000
|
$8.230
|
$12.000
|
$5.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
1,800.000
|
$20.000
|
$14.500
|
$20.000
|
$15.000
|
$9.000
|
$15.000
|
$7.590
|
$14.000
|
$5.000
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
491.000
|
$20.000
|
$25.000
|
$55.000
|
$40.000
|
$30.000
|
$35.000
|
$28.240
|
$30.000
|
$45.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
714.000
|
$50.000
|
$98.000
|
$53.000
|
$60.000
|
$64.000
|
$55.000
|
$21.780
|
$65.000
|
$60.000
|
|
|
CONC SIDEWALKS (4")
|
SY
|
351.000
|
$50.000
|
$60.000
|
$88.000
|
$80.000
|
$80.000
|
$100.000
|
$55.910
|
$85.000
|
$80.000
|
|
|
CURB RAMPS (TY 10)
|
EA
|
8.000
|
$2,000.000
|
$2,000.000
|
$2,200.000
|
$2,000.000
|
$2,800.000
|
$4,000.000
|
$3,177.030
|
$3,000.000
|
$2,700.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
175.000
|
$35.000
|
$35.000
|
$31.000
|
$30.000
|
$31.000
|
$31.500
|
$33.000
|
$30.000
|
$27.500
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
2.000
|
$2,360.000
|
$3,200.000
|
$2,800.000
|
$2,000.000
|
$2,100.000
|
$3,150.000
|
$2,750.000
|
$2,000.000
|
$1,875.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$3,500.000
|
$4,000.000
|
$3,500.000
|
$3,250.000
|
$3,600.000
|
$3,675.000
|
$3,850.000
|
$3,000.000
|
$3,175.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
3.000
|
$1,000.000
|
$1,172.960
|
$1,500.000
|
$3,000.000
|
$1,000.000
|
$1,470.000
|
$1,050.000
|
$3,000.000
|
$1,800.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
7.000
|
$350.000
|
$832.240
|
$1,000.000
|
$1,500.000
|
$750.000
|
$735.000
|
$745.000
|
$1,000.000
|
$1,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
6.000
|
$9,000.000
|
$9,417.180
|
$9,500.000
|
$10,000.000
|
$9,000.000
|
$9,450.000
|
$8,430.000
|
$10,000.000
|
$10,000.000
|
|
|
CRASH CUSHION ATTEN (INSTALL) (QUAD)(N)
|
EA
|
1.000
|
$30,000.000
|
$32,500.000
|
$33,000.000
|
$32,500.000
|
$27,000.000
|
$31,500.000
|
$28,000.000
|
$35,000.000
|
$30,000.000
|
|
|
REMOVE RD IL ASM (TRANS-BASE)
|
EA
|
3.000
|
$500.000
|
$982.380
|
$1,100.000
|
$800.000
|
$900.000
|
$3,150.000
|
$758.000
|
$800.000
|
$435.000
|
|
|
IN RD IL (TY ST) 40T-10 (250W EQ) LED
|
EA
|
3.000
|
$6,000.000
|
$6,210.000
|
$5,800.000
|
$6,000.000
|
$6,400.000
|
$6,300.000
|
$5,345.000
|
$6,000.000
|
$5,365.000
|
|
|
CONDT (PVC) (SCH 80) (2")
|
LF
|
590.000
|
$15.000
|
$20.000
|
$16.000
|
$20.000
|
$21.000
|
$42.000
|
$17.000
|
$20.000
|
$28.600
|
|
|
ELEC CONDR (NO.6) BARE
|
LF
|
840.000
|
$2.000
|
$3.000
|
$3.000
|
$4.000
|
$3.000
|
$7.880
|
$2.500
|
$3.000
|
$2.650
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
1,680.000
|
$2.500
|
$3.000
|
$3.000
|
$4.000
|
$3.000
|
$8.400
|
$2.500
|
$3.000
|
$2.750
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
2.000
|
$800.000
|
$1,200.000
|
$1,400.000
|
$1,250.000
|
$1,200.000
|
$2,100.000
|
$2,366.240
|
$1,500.000
|
$2,225.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
4.000
|
$820.000
|
$800.000
|
$730.000
|
$1,000.000
|
$900.000
|
$735.000
|
$731.500
|
$1,000.000
|
$750.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
7.000
|
$1,000.000
|
$900.000
|
$890.000
|
$1,250.000
|
$1,200.000
|
$845.000
|
$880.000
|
$1,500.000
|
$900.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
2.000
|
$900.000
|
$1,300.000
|
$1,200.000
|
$1,500.000
|
$1,500.000
|
$1,155.000
|
$1,210.000
|
$1,500.000
|
$1,300.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
11.000
|
$100.000
|
$120.000
|
$145.000
|
$150.000
|
$120.000
|
$31.500
|
$104.500
|
$300.000
|
$100.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
7.000
|
$20.000
|
$42.000
|
$22.000
|
$50.000
|
$23.000
|
$32.550
|
$39.600
|
$100.000
|
$100.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
6.000
|
$27.000
|
$36.000
|
$44.000
|
$50.000
|
$46.000
|
$52.500
|
$35.200
|
$30.000
|
$200.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
4.000
|
$200.000
|
$190.000
|
$165.000
|
$200.000
|
$170.000
|
$160.650
|
$187.000
|
$150.000
|
$150.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
7,894.000
|
$0.750
|
$1.150
|
$1.250
|
$1.250
|
$1.100
|
$1.080
|
$1.000
|
$1.000
|
$1.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
7,856.000
|
$0.750
|
$1.150
|
$1.250
|
$1.250
|
$1.100
|
$1.080
|
$1.000
|
$1.000
|
$1.000
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
60.000
|
$3.000
|
$5.740
|
$5.500
|
$4.000
|
$4.000
|
$5.380
|
$5.000
|
$5.000
|
$5.000
|
|
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
|
LF
|
45.000
|
$4.000
|
$5.740
|
$5.500
|
$4.000
|
$4.000
|
$5.380
|
$5.000
|
$5.000
|
$5.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
5,938.000
|
$0.200
|
$0.230
|
$0.250
|
$0.250
|
$0.250
|
$0.220
|
$0.200
|
$0.250
|
$0.200
|
|
|
PAVEMENT SEALER 12"
|
LF
|
45.000
|
$0.500
|
$3.500
|
$3.500
|
$2.000
|
$2.100
|
$3.230
|
$3.000
|
$2.000
|
$3.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
1,230.000
|
$0.450
|
$1.150
|
$1.250
|
$1.000
|
$0.900
|
$1.080
|
$1.000
|
$1.000
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
4,429.000
|
$0.400
|
$1.150
|
$1.250
|
$1.000
|
$0.850
|
$1.080
|
$1.000
|
$1.000
|
$1.000
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
5,550.000
|
$0.400
|
$1.150
|
$1.250
|
$1.000
|
$0.850
|
$1.080
|
$1.000
|
$1.000
|
$1.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
64.000
|
$4.000
|
$8.100
|
$8.000
|
$8.000
|
$5.400
|
$7.530
|
$7.000
|
$5.000
|
$7.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
78.000
|
$5.000
|
$8.100
|
$8.000
|
$8.000
|
$5.400
|
$7.530
|
$7.000
|
$5.000
|
$7.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
16,262.000
|
$0.400
|
$0.400
|
$0.500
|
$0.750
|
$0.650
|
$0.380
|
$0.350
|
$0.700
|
$0.350
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
5,938.000
|
$0.150
|
$0.230
|
$0.500
|
$0.100
|
$0.050
|
$0.220
|
$0.200
|
$0.100
|
$0.200
|
|
|
TREE TRIMMING / BRUSH REMOVAL
|
MI
|
0.214
|
$20,000.000
|
$12,000.000
|
$500,000.000
|
$100,000.000
|
$20,000.000
|
$105,000.000
|
$50,000.000
|
$100,000.000
|
$30,000.000
|
|
|
TREE REMOVAL (36" - 42" DIA)
|
EA
|
5.000
|
$3,500.000
|
$6,000.000
|
$5,000.000
|
$2,000.000
|
$3,600.000
|
$2,100.000
|
$6,000.000
|
$5,000.000
|
$1,000.000
|
|
|
D-GR HMA TY-B PG64-22 (EXEMPT)
|
TON
|
1,111.000
|
$130.000
|
$122.000
|
$121.000
|
$140.000
|
$125.000
|
$130.000
|
$110.000
|
$140.000
|
$110.000
|
|
|
SP MIXES SP-D SAC-A PG70-22
|
TON
|
996.000
|
$170.000
|
$152.000
|
$151.000
|
$150.000
|
$155.000
|
$165.000
|
$138.000
|
$140.000
|
$138.000
|
|
|
TACK COAT
|
GAL
|
544.000
|
$3.250
|
$3.810
|
$4.000
|
$5.000
|
$3.900
|
$3.250
|
$4.290
|
$6.000
|
$3.500
|
|
|
INSTALL FTB
|
LF
|
142.000
|
$45.000
|
$100.000
|
$75.000
|
$80.000
|
$100.000
|
$82.540
|
$49.230
|
$50.000
|
$80.000
|
|
|
REMOVE FTB
|
LF
|
142.000
|
$5.000
|
$16.000
|
$30.000
|
$15.000
|
$11.000
|
$13.950
|
$4.350
|
$10.000
|
$10.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$24,000.000
|
$20,000.000
|
$17,500.000
|
$15,000.000
|
$17,500.000
|
$18,427.150
|
$32,000.000
|
$15,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
222.000
|
$200.000
|
$350.000
|
$100.000
|
$75.000
|
$180.000
|
$157.500
|
$321.300
|
$200.000
|
$100.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
4.000
|
$350.000
|
$475.000
|
$250.000
|
$500.000
|
$750.000
|
$735.000
|
$521.670
|
$250.000
|
$1,200.000
|
|
Totals: |
$4,931,327.756
|
$4,761,917.350
|
$5,261,522.000
|
$5,447,050.300
|
$5,604,599.350
|
$5,919,659.810
|
$5,946,730.290
|
$6,114,341.700
|
$7,282,504.900
|