PREP ROW (TREE REMOVE) (0"-12" DIA)
|
EA
|
7.000
|
$400.000
|
$725.000
|
$500.000
|
$1,000.000
|
$750.000
|
$725.000
|
$500.000
|
$775.000
|
|
|
PREP ROW (TREE REMOVE) (12"-24" DIA)
|
EA
|
3.000
|
$800.000
|
$1,850.000
|
$850.000
|
$3,000.000
|
$1,500.000
|
$1,820.000
|
$1,500.000
|
$2,000.000
|
|
|
PREP ROW (TREE PRUNE AND TRIM)
|
STA
|
128.000
|
$2,500.000
|
$417.000
|
$300.000
|
$420.000
|
$250.000
|
$417.000
|
$2,000.000
|
$475.000
|
|
|
REMOV CONC (RIPRAP)
|
SY
|
21.000
|
$25.000
|
$23.750
|
$71.000
|
$50.000
|
$20.000
|
$23.750
|
$40.000
|
$23.500
|
|
|
REMOV CONC (DRIVEWAYS)
|
SY
|
70.000
|
$25.000
|
$31.300
|
$34.000
|
$32.000
|
$25.000
|
$31.300
|
$40.000
|
$31.000
|
|
|
REMOV CONC (CURB)
|
LF
|
820.000
|
$5.000
|
$16.200
|
$18.000
|
$5.000
|
$8.000
|
$15.000
|
$20.000
|
$16.000
|
|
|
EXCAV (ROADWAY)
|
CY
|
1,925.000
|
$20.000
|
$37.000
|
$43.000
|
$75.000
|
$6.000
|
$40.000
|
$30.000
|
$32.000
|
|
|
EXCAV (CHANNEL)
|
CY
|
18.000
|
$35.000
|
$17.000
|
$150.000
|
$100.000
|
$40.000
|
$128.110
|
$40.000
|
$105.000
|
|
|
EMBANK (FNL)(OC)(TY B)
|
CY
|
9,166.000
|
$25.000
|
$25.000
|
$45.000
|
$55.000
|
$13.000
|
$50.000
|
$50.000
|
$50.000
|
|
|
BACKFILL (TY B)
|
STA
|
78.000
|
$150.000
|
$159.000
|
$350.000
|
$220.000
|
$200.000
|
$229.760
|
$150.000
|
$605.000
|
|
|
BROADCAST SEED (TEMP_WARM)
|
SY
|
31,711.000
|
$0.200
|
$0.150
|
$0.110
|
$0.050
|
$0.100
|
$0.110
|
$0.100
|
$0.140
|
|
|
BROADCAST SEED (TEMP_COOL)
|
SY
|
31,711.000
|
$0.200
|
$0.150
|
$0.160
|
$0.050
|
$0.010
|
$0.110
|
$0.100
|
$0.140
|
|
|
DRILL SEED (PERM_RURAL_SAND)
|
SY
|
63,409.000
|
$0.150
|
$0.230
|
$0.160
|
$0.200
|
$0.150
|
$0.180
|
$0.100
|
$0.170
|
|
|
VEGETATIVE WATERING
|
TGL
|
544.500
|
$25.000
|
$25.000
|
$55.000
|
$100.000
|
$40.000
|
$52.000
|
$10.000
|
$95.000
|
|
|
CEMENT
|
TON
|
411.000
|
$270.000
|
$245.000
|
$225.000
|
$250.000
|
$225.000
|
$350.150
|
$250.000
|
$280.000
|
|
|
CEMENT TRT (EXIST MATL)(8")
|
SY
|
28,335.000
|
$4.000
|
$2.500
|
$4.500
|
$7.000
|
$5.000
|
$5.590
|
$8.000
|
$11.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
7,084.000
|
$5.250
|
$3.650
|
$7.650
|
$1.500
|
$0.100
|
$4.090
|
$6.200
|
$8.000
|
|
|
EMULS ASPH (EROSN CONT)(MS-2)
|
GAL
|
6,294.000
|
$3.500
|
$2.000
|
$3.500
|
$1.500
|
$0.100
|
$1.800
|
$6.500
|
$6.000
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
5,194.000
|
$98.000
|
$88.000
|
$105.000
|
$90.000
|
$150.000
|
$130.000
|
$170.000
|
$165.000
|
|
|
D-GR HMA TY-C PG64-22 (LEVEL-UP)
|
TON
|
1,668.000
|
$125.000
|
$105.000
|
$150.000
|
$100.000
|
$155.000
|
$140.000
|
$200.000
|
$214.000
|
|
|
D-GR HMA TY-C SAC-B PG70-28
|
TON
|
13,310.000
|
$105.000
|
$101.500
|
$126.000
|
$110.000
|
$148.000
|
$153.000
|
$160.000
|
$136.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
|
SY
|
13,524.000
|
$25.000
|
$35.000
|
$40.500
|
$35.000
|
$45.000
|
$45.000
|
$20.000
|
$57.000
|
|
|
PLANE & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
3,006.000
|
$2.500
|
$5.000
|
$7.500
|
$7.000
|
$3.000
|
$2.360
|
$8.200
|
$6.500
|
|
|
CUT & RESTORING PAV
|
SY
|
48.000
|
$75.000
|
$152.000
|
$255.000
|
$210.000
|
$55.000
|
$108.000
|
$350.000
|
$850.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
57.000
|
$175.000
|
$302.400
|
$280.000
|
$500.000
|
$250.000
|
$302.400
|
$200.000
|
$300.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
91.000
|
$10.000
|
$1.080
|
$1.000
|
$5.000
|
$25.000
|
$1.080
|
$1.000
|
$1.050
|
|
|
TEMPORARY SPL SHORING
|
SF
|
2,551.000
|
$35.000
|
$32.400
|
$44.000
|
$25.000
|
$65.000
|
$32.400
|
$50.000
|
$32.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
4.000
|
$1,500.000
|
$1,944.000
|
$1,800.000
|
$800.000
|
$2,000.000
|
$1,944.000
|
$1,000.000
|
$1,900.000
|
|
|
CONC STR REPAIR (STANDARD)
|
SF
|
7.000
|
$250.000
|
$432.000
|
$400.000
|
$220.000
|
$250.000
|
$432.000
|
$150.000
|
$430.000
|
|
|
RIPRAP (MOW STRIP)(5 IN)
|
CY
|
48.000
|
$550.000
|
$739.800
|
$769.000
|
$1,000.000
|
$650.000
|
$848.850
|
$600.000
|
$735.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(24 IN)
|
CY
|
255.000
|
$225.000
|
$253.800
|
$329.000
|
$190.000
|
$383.000
|
$253.800
|
$200.000
|
$250.000
|
|
|
CMP (GAL STL 18 IN)
|
LF
|
560.000
|
$95.000
|
$59.400
|
$55.000
|
$70.000
|
$75.000
|
$59.400
|
$80.000
|
$59.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
216.000
|
$115.000
|
$75.600
|
$70.000
|
$90.000
|
$85.000
|
$75.600
|
$120.000
|
$75.000
|
|
|
CONC BOX CULV (4 FT X 3 FT)
|
LF
|
127.000
|
$300.000
|
$405.000
|
$375.000
|
$370.000
|
$500.000
|
$405.000
|
$500.000
|
$400.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
|
LF
|
7.000
|
$850.000
|
$1,404.000
|
$1,300.000
|
$500.000
|
$730.000
|
$1,404.000
|
$500.000
|
$1,400.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
80.000
|
$85.000
|
$91.800
|
$85.000
|
$80.000
|
$90.000
|
$91.800
|
$80.000
|
$90.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
90.000
|
$125.000
|
$104.760
|
$97.000
|
$100.000
|
$105.000
|
$104.760
|
$120.000
|
$104.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 18 IN)
|
EA
|
1.000
|
$12,500.000
|
$5,540.400
|
$5,130.000
|
$8,000.000
|
$7,250.000
|
$6,073.900
|
$2,000.000
|
$5,500.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
3.000
|
$15,000.000
|
$7,182.000
|
$6,650.000
|
$6,000.000
|
$9,750.000
|
$7,715.490
|
$3,000.000
|
$7,100.000
|
|
|
WINGWALL (PW - 2) (HW=4 FT)
|
EA
|
1.000
|
$15,000.000
|
$13,608.000
|
$12,600.000
|
$20,000.000
|
$16,500.000
|
$18,000.000
|
$8,000.000
|
$13,500.000
|
|
|
WINGWALL (PW - 2) (HW=6 FT)
|
EA
|
1.000
|
$20,000.000
|
$15,660.000
|
$14,500.000
|
$24,000.000
|
$18,500.000
|
$22,000.000
|
$10,000.000
|
$15,250.000
|
|
|
WINGWALL (PW - 2) (HW=9 FT)
|
EA
|
1.000
|
$70,000.000
|
$38,880.000
|
$36,000.000
|
$50,000.000
|
$45,000.000
|
$50,000.000
|
$20,000.000
|
$38,500.000
|
|
|
WINGWALL (PW - 2) (HW=10 FT)
|
EA
|
2.000
|
$78,000.000
|
$63,720.000
|
$59,000.000
|
$60,000.000
|
$65,000.000
|
$80,000.000
|
$30,000.000
|
$63,000.000
|
|
|
WINGWALL (PW - 2) (HW=11 FT)
|
EA
|
1.000
|
$80,000.000
|
$62,640.000
|
$58,000.000
|
$62,000.000
|
$68,500.000
|
$80,000.000
|
$30,000.000
|
$62,000.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1)(C)
|
EA
|
2.000
|
$15,000.000
|
$11,880.000
|
$11,000.000
|
$26,000.000
|
$10,500.000
|
$15,000.000
|
$10,000.000
|
$11,750.000
|
|
|
SET (TY II) (18 IN) (CMP) (6: 1) (P)
|
EA
|
49.000
|
$1,500.000
|
$1,296.000
|
$1,200.000
|
$2,600.000
|
$1,250.000
|
$1,296.000
|
$1,000.000
|
$1,250.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$1,800.000
|
$1,166.400
|
$1,080.000
|
$2,300.000
|
$1,400.000
|
$1,166.400
|
$1,500.000
|
$1,150.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
5.000
|
$1,700.000
|
$1,528.200
|
$1,415.000
|
$2,800.000
|
$1,500.000
|
$1,528.200
|
$1,500.000
|
$1,530.000
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
8.000
|
$1,800.000
|
$1,771.200
|
$1,640.000
|
$3,100.000
|
$1,650.000
|
$1,771.200
|
$1,500.000
|
$1,700.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$2,000.000
|
$1,598.400
|
$1,480.000
|
$2,800.000
|
$1,650.000
|
$1,598.400
|
$1,500.000
|
$1,550.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$2,200.000
|
$1,846.800
|
$1,710.000
|
$3,200.000
|
$1,650.000
|
$1,846.800
|
$1,500.000
|
$1,750.000
|
|
|
SET (TY II) (36 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$3,000.000
|
$5,400.000
|
$5,000.000
|
$9,000.000
|
$3,500.000
|
$5,400.000
|
$2,000.000
|
$5,300.000
|
|
|
SET (REMOV & REINSTALL)
|
EA
|
3.000
|
$500.000
|
$540.000
|
$500.000
|
$900.000
|
$700.000
|
$840.000
|
$500.000
|
$540.000
|
|
|
REMOV & RE - LAY PIPE (18 IN)
|
LF
|
57.000
|
$50.000
|
$64.800
|
$60.000
|
$90.000
|
$80.000
|
$64.800
|
$100.000
|
$63.000
|
|
|
REMOV & RE - LAY PIPE (24 IN)
|
LF
|
12.000
|
$75.000
|
$97.200
|
$90.000
|
$100.000
|
$90.000
|
$97.200
|
$120.000
|
$95.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
7.000
|
$2,500.000
|
$3,340.000
|
$3,100.000
|
$2,000.000
|
$3,500.000
|
$3,340.000
|
$2,000.000
|
$3,350.000
|
|
|
REMOV STR (SET)
|
EA
|
54.000
|
$750.000
|
$216.000
|
$200.000
|
$1,000.000
|
$400.000
|
$216.000
|
$500.000
|
$215.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
4.000
|
$1,000.000
|
$972.000
|
$900.000
|
$8,000.000
|
$1,000.000
|
$972.000
|
$2,000.000
|
$970.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
6.000
|
$1,500.000
|
$972.000
|
$900.000
|
$10,000.000
|
$1,000.000
|
$972.000
|
$2,000.000
|
$970.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,009.000
|
$25.000
|
$10.800
|
$10.000
|
$50.000
|
$12.000
|
$10.800
|
$10.000
|
$10.500
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
8.000
|
$50.000
|
$864.000
|
$800.000
|
$1,000.000
|
$100.000
|
$864.000
|
$500.000
|
$855.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$529,366.100
|
$582,000.000
|
$420,000.000
|
$741,000.000
|
$650,000.000
|
$860,000.000
|
$600,000.000
|
$650,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
19.000
|
$8,000.000
|
$2,000.000
|
$20,500.000
|
$20,000.000
|
$20,000.000
|
$30,000.000
|
$5,000.000
|
$25,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
353.000
|
$250.000
|
$183.330
|
$350.000
|
$50.000
|
$1.000
|
$1.000
|
$300.000
|
$350.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
20.000
|
$250.000
|
$875.000
|
$715.000
|
$50.000
|
$1.000
|
$300.000
|
$300.000
|
$750.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
150.000
|
$45.000
|
$44.600
|
$42.000
|
$42.000
|
$42.000
|
$42.000
|
$20.000
|
$60.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
150.000
|
$15.000
|
$11.000
|
$15.000
|
$15.000
|
$10.000
|
$15.000
|
$5.000
|
$18.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
11,185.000
|
$3.950
|
$3.390
|
$4.220
|
$4.250
|
$1.000
|
$4.220
|
$5.000
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
11,185.000
|
$1.000
|
$0.840
|
$0.750
|
$0.800
|
$0.500
|
$0.750
|
$1.000
|
$0.950
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
2,670.000
|
$4.750
|
$3.740
|
$5.000
|
$5.000
|
$1.000
|
$5.000
|
$5.000
|
$7.250
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
2,670.000
|
$1.250
|
$0.840
|
$1.200
|
$1.250
|
$0.500
|
$1.200
|
$1.000
|
$0.950
|
|
|
DRIVEWAYS (CONC)
|
SY
|
109.000
|
$125.000
|
$140.400
|
$171.000
|
$180.000
|
$180.000
|
$152.410
|
$120.000
|
$135.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
3,905.000
|
$55.000
|
$39.000
|
$42.000
|
$60.000
|
$50.000
|
$65.000
|
$140.000
|
$58.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
3,304.000
|
$25.000
|
$19.000
|
$23.000
|
$22.000
|
$35.000
|
$45.000
|
$15.000
|
$30.000
|
|
|
TURNOUTS (ACP)
|
SY
|
1,405.000
|
$50.000
|
$36.000
|
$79.000
|
$40.000
|
$70.000
|
$65.000
|
$260.000
|
$58.000
|
|
|
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
|
LF
|
73,931.000
|
$0.250
|
$0.200
|
$0.200
|
$0.150
|
$0.200
|
$0.200
|
$0.200
|
$0.220
|
|
|
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
|
LF
|
36,966.000
|
$0.300
|
$0.200
|
$0.200
|
$0.150
|
$0.200
|
$0.200
|
$0.200
|
$0.220
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,400.000
|
$26.000
|
$20.890
|
$23.000
|
$20.000
|
$23.000
|
$20.250
|
$40.000
|
$24.500
|
|
|
MTL BEAM GD FEN TRANS (T101)
|
EA
|
4.000
|
$1,500.000
|
$1,025.640
|
$780.000
|
$1,000.000
|
$780.000
|
$1,025.000
|
$1,500.000
|
$840.000
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
EA
|
2.000
|
$1,000.000
|
$1,025.000
|
$1,125.000
|
$1,000.000
|
$1,125.000
|
$1,025.000
|
$1,500.000
|
$1,200.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,375.000
|
$3.000
|
$2.000
|
$3.000
|
$2.000
|
$3.000
|
$2.000
|
$5.000
|
$3.250
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
8.000
|
$450.000
|
$200.640
|
$200.000
|
$200.000
|
$200.000
|
$200.000
|
$500.000
|
$215.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$3,500.000
|
$2,850.000
|
$2,950.000
|
$2,900.000
|
$2,950.000
|
$2,850.000
|
$3,500.000
|
$3,150.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$300.000
|
$200.000
|
$250.000
|
$200.000
|
$250.000
|
$200.000
|
$500.000
|
$270.000
|
|
|
WIRE FENCE (TY C)
|
LF
|
100.000
|
$50.000
|
$14.750
|
$60.000
|
$15.000
|
$54.000
|
$30.000
|
$30.000
|
$16.000
|
|
|
WIRE FENCE (REMOVE)
|
LF
|
100.000
|
$20.000
|
$2.400
|
$10.000
|
$2.500
|
$16.000
|
$10.000
|
$1.000
|
$2.500
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 2
|
EA
|
17.000
|
$350.000
|
$220.000
|
$220.000
|
$220.000
|
$220.000
|
$365.570
|
$300.000
|
$230.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
31.000
|
$300.000
|
$190.000
|
$190.000
|
$190.000
|
$190.000
|
$335.570
|
$300.000
|
$200.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SB(P)
|
EA
|
28.000
|
$825.000
|
$520.000
|
$520.000
|
$500.000
|
$520.000
|
$520.000
|
$800.000
|
$560.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SB(T)
|
EA
|
10.000
|
$800.000
|
$565.000
|
$565.000
|
$600.000
|
$565.000
|
$565.000
|
$800.000
|
$610.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
103.000
|
$650.000
|
$340.000
|
$340.000
|
$340.000
|
$340.000
|
$340.000
|
$500.000
|
$365.000
|
|
|
IN SM RD SN SUP&AM (INST SIGN ONLY)
|
EA
|
14.000
|
$350.000
|
$120.000
|
$120.000
|
$120.000
|
$120.000
|
$120.000
|
$800.000
|
$127.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
74.000
|
$120.000
|
$90.000
|
$90.000
|
$90.000
|
$90.000
|
$90.000
|
$200.000
|
$96.000
|
|
|
REMOVE SM RD SN SUP&AM (SIGN ONLY)
|
EA
|
14.000
|
$50.000
|
$50.000
|
$50.000
|
$50.000
|
$50.000
|
$50.000
|
$100.000
|
$54.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
22.000
|
$50.000
|
$61.000
|
$45.000
|
$31.000
|
$25.000
|
$50.000
|
$12.000
|
$27.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
62.000
|
$125.000
|
$59.000
|
$59.000
|
$60.000
|
$59.000
|
$59.000
|
$35.000
|
$63.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
4,052.000
|
$0.850
|
$1.430
|
$1.250
|
$2.250
|
$1.000
|
$1.000
|
$2.350
|
$3.500
|
|
|
PAVEMENT SLER 6"
|
LF
|
460.000
|
$0.500
|
$0.200
|
$0.170
|
$0.170
|
$0.200
|
$0.200
|
$0.250
|
$0.180
|
|
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
|
LF
|
74,446.000
|
$0.550
|
$0.490
|
$0.500
|
$0.500
|
$0.490
|
$0.490
|
$0.600
|
$0.540
|
|
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
|
LF
|
9,050.000
|
$0.550
|
$0.510
|
$0.500
|
$0.500
|
$0.510
|
$0.510
|
$0.600
|
$0.540
|
|
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
|
LF
|
37,288.000
|
$0.550
|
$0.500
|
$0.500
|
$0.500
|
$0.500
|
$0.500
|
$0.600
|
$0.540
|
|
PREFAB PM TY C (W)(24")(SLD)
|
LF
|
200.000
|
$15.000
|
$11.000
|
$12.750
|
$13.000
|
$11.000
|
$11.000
|
$13.000
|
$13.750
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
752.000
|
$3.500
|
$3.550
|
$5.000
|
$5.000
|
$3.550
|
$3.550
|
$4.200
|
$5.300
|
|
|
ELIM EXT PM & MRKS (4")
|
LF
|
460.000
|
$0.500
|
$1.000
|
$0.340
|
$0.300
|
$1.000
|
$1.000
|
$1.200
|
$0.370
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
460.000
|
$0.500
|
$0.300
|
$0.010
|
$0.010
|
$0.300
|
$0.300
|
$0.350
|
$0.020
|
|
|
DRIFTWOOD REMOVAL
|
CY
|
45.000
|
$150.000
|
$43.000
|
$475.000
|
$43.000
|
$1,000.000
|
$43.000
|
$100.000
|
$46.000
|
|
|
BONDING COURSE
|
GAL
|
7,604.000
|
$5.000
|
$4.200
|
$3.500
|
$1.000
|
$1.000
|
$4.000
|
$5.000
|
$2.250
|
|
Totals: |
$5,976,727.050
|
$5,255,697.320
|
$6,499,041.060
|
$6,674,167.000
|
$6,851,607.900
|
$7,793,458.660
|
$7,857,857.500
|
$7,981,358.660
|