PREPARING ROW
|
STA
|
362.000
|
$400.000
|
$600.000
|
$1,750.000
|
$1,200.000
|
$1,500.000
|
|
|
REMOVING STAB BASE & ASPH PAV (4"-22")
|
SY
|
176,596.000
|
$2.000
|
$8.000
|
$0.600
|
$2.000
|
$11.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
52,234.000
|
$18.500
|
$28.000
|
$19.000
|
$17.000
|
$29.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
54,613.000
|
$26.250
|
$28.000
|
$65.000
|
$100.000
|
$68.000
|
|
|
BACKFILL TY A
|
CY
|
55,260.000
|
$45.750
|
$24.000
|
$72.000
|
$72.000
|
$62.000
|
|
|
BLADING
|
HR
|
62.000
|
$285.000
|
$137.110
|
$112.000
|
$215.000
|
$400.000
|
|
|
FL BS (RDWY DEL)(TY A GR 5)
|
TON
|
94,863.000
|
$49.250
|
$48.000
|
$34.500
|
$33.000
|
$47.000
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
6,505.000
|
$4.500
|
$3.000
|
$4.900
|
$7.700
|
$4.500
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
123,685.000
|
$3.250
|
$4.000
|
$1.000
|
$4.000
|
$4.600
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
1,476.000
|
$75.000
|
$125.000
|
$148.000
|
$200.000
|
$300.000
|
|
|
TOM (ASPHALT) PG 76-22
|
TON
|
574.000
|
$575.000
|
$700.000
|
$1,200.000
|
$700.000
|
$1,000.000
|
|
|
TOM-C (AGGREGATE) SAC-A
|
TON
|
9,147.000
|
$62.000
|
$103.000
|
$82.500
|
$80.000
|
$120.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
2,390.000
|
$265.500
|
$173.000
|
$202.000
|
$175.000
|
$300.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
1,056.000
|
$6.100
|
$9.000
|
$25.000
|
$1.000
|
$28.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
4,851.000
|
$13.000
|
$33.000
|
$50.000
|
$60.150
|
$50.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
1,540.000
|
$125.000
|
$135.000
|
$170.000
|
$300.000
|
$230.000
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
646.000
|
$150.000
|
$140.000
|
$180.000
|
$290.000
|
$330.000
|
|
|
CONC BOX CULV (8 FT X 8 FT)
|
LF
|
53.000
|
$900.000
|
$700.000
|
$1,200.000
|
$1,612.000
|
$1,000.000
|
|
|
CONC BOX CULV (10 FT X 7 FT)
|
LF
|
55.000
|
$800.000
|
$915.000
|
$1,350.000
|
$1,932.000
|
$1,400.000
|
|
|
CONC BOX CULV (10 FT X 8 FT)
|
LF
|
271.000
|
$500.000
|
$940.000
|
$1,380.000
|
$1,677.000
|
$1,500.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
2,381.000
|
$61.000
|
$65.000
|
$120.000
|
$107.000
|
$110.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
2,122.000
|
$105.000
|
$85.000
|
$136.000
|
$128.000
|
$130.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
404.000
|
$145.000
|
$120.000
|
$156.000
|
$188.000
|
$190.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
633.000
|
$215.000
|
$180.000
|
$235.000
|
$270.000
|
$290.000
|
|
|
WINGWALL (PW - 2) (HW=10 FT)
|
EA
|
2.000
|
$26,000.000
|
$10,000.000
|
$70,000.000
|
$29,000.000
|
$70,000.000
|
|
|
WINGWALL (PW - 2) (HW=11 FT)
|
EA
|
4.000
|
$31,500.000
|
$12,000.000
|
$58,000.000
|
$38,000.000
|
$99,000.000
|
|
|
WINGWALL (PW - 2) (HW=9 FT)
|
EA
|
2.000
|
$28,000.000
|
$8,000.000
|
$58,000.000
|
$23,000.000
|
$53,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
54.000
|
$1,050.000
|
$1,200.000
|
$2,100.000
|
$2,712.000
|
$2,300.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
16.000
|
$4,410.000
|
$1,500.000
|
$1,750.000
|
$2,964.000
|
$2,800.000
|
|
|
SET (TY II) (30 IN) (RCP) (3: 1) (C)
|
EA
|
60.000
|
$1,400.000
|
$1,550.000
|
$2,300.000
|
$3,144.000
|
$4,500.000
|
|
|
SET (TY II) (36 IN) (RCP) (3: 1) (C)
|
EA
|
10.000
|
$2,000.000
|
$2,000.000
|
$2,750.000
|
$4,075.000
|
$5,600.000
|
|
|
SET (TY II) (48 IN) (RCP) (3: 1) (C)
|
EA
|
18.000
|
$3,600.000
|
$3,000.000
|
$7,700.000
|
$5,775.000
|
$7,200.000
|
|
|
REMOV STR (BOX CULVERT)
|
EA
|
4.000
|
$17,025.000
|
$8,500.000
|
$11,000.000
|
$12,704.000
|
$9,000.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
116.000
|
$7,750.760
|
$1,500.000
|
$1,300.000
|
$772.000
|
$3,000.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
58.000
|
$1,200.000
|
$1,900.000
|
$1,300.000
|
$797.000
|
$3,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
3,096.000
|
$23.970
|
$12.000
|
$35.000
|
$18.000
|
$50.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$2,200,000.000
|
$2,035,345.930
|
$2,800,000.000
|
$2,940,000.000
|
$3,400,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
18.000
|
$9,286.980
|
$9,000.000
|
$6,300.000
|
$15,000.000
|
$26,000.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
3,960.000
|
$6.000
|
$3.000
|
$5.000
|
$8.000
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
3,960.000
|
$2.000
|
$1.100
|
$2.000
|
$2.000
|
$2.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
18.000
|
$2,800.000
|
$3,700.000
|
$5,200.000
|
$5,600.000
|
$6,000.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
8,490.000
|
$35.000
|
$54.000
|
$70.000
|
$96.000
|
$90.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
55,560.000
|
$6.000
|
$6.000
|
$8.000
|
$5.300
|
$12.000
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
8,490.000
|
$10.000
|
$6.000
|
$5.300
|
$8.000
|
$13.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
286.000
|
$91.000
|
$104.000
|
$92.000
|
$130.000
|
$275.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,418.000
|
$90.000
|
$60.000
|
$104.000
|
$60.000
|
$55.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
9,755.000
|
$21.000
|
$22.000
|
$30.000
|
$36.000
|
$23.000
|
|
|
MTL BM GD FEN (LONG SPAN SYSTEM)
|
EA
|
13.000
|
$1,500.000
|
$694.000
|
$1,400.000
|
$2,000.000
|
$750.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
30.000
|
$3,000.000
|
$3,000.000
|
$3,200.000
|
$3,250.000
|
$3,200.000
|
|
|
CRASH CUSH ATTEN (INSTL)
|
EA
|
10.000
|
$8,000.000
|
$11,450.000
|
$8,500.000
|
$7,000.000
|
$10,000.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
44.000
|
$1,900.000
|
$2,000.000
|
$4,000.000
|
$500.000
|
$2,000.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
14.000
|
$850.000
|
$520.000
|
$150.000
|
$250.000
|
$1,000.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
13.000
|
$37.000
|
$29.000
|
$26.500
|
$31.000
|
$30.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
16.000
|
$800.000
|
$510.000
|
$475.000
|
$1,100.000
|
$500.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
10.000
|
$975.000
|
$540.000
|
$500.000
|
$1,300.000
|
$530.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
|
EA
|
1.000
|
$1,050.000
|
$567.000
|
$525.000
|
$1,350.000
|
$560.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
12.000
|
$75.000
|
$110.000
|
$79.000
|
$80.000
|
$90.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI)
|
EA
|
22.000
|
$60.000
|
$58.000
|
$52.500
|
$82.000
|
$60.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
76.000
|
$160.000
|
$46.000
|
$42.000
|
$82.000
|
$50.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
46.000
|
$20.000
|
$12.000
|
$10.500
|
$20.000
|
$12.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
72,280.000
|
$1.000
|
$0.800
|
$1.070
|
$0.800
|
$1.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
54,210.000
|
$1.000
|
$0.900
|
$0.690
|
$2.000
|
$0.600
|
|
REFL PAV MRK TY II (W) 4" (SLD)
|
LF
|
72,276.000
|
$0.250
|
$0.160
|
$0.210
|
$0.200
|
$0.220
|
|
REFL PAV MRK TY II (Y) 4" (BRK)
|
LF
|
7,815.000
|
$0.850
|
$0.160
|
$0.210
|
$0.200
|
$0.220
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
25,218.000
|
$0.300
|
$0.160
|
$0.210
|
$0.200
|
$0.220
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
72,276.000
|
$0.450
|
$0.350
|
$0.480
|
$0.400
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
7,815.000
|
$0.350
|
$0.350
|
$0.480
|
$0.400
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
25,218.000
|
$0.350
|
$0.350
|
$0.480
|
$0.400
|
$0.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
681.000
|
$65.000
|
$3.000
|
$6.300
|
$2.800
|
$7.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
72,280.000
|
$0.500
|
$1.000
|
$0.950
|
$0.500
|
$1.000
|
|
|
FILTER FABRIC (TY 2)
|
SY
|
5,273.000
|
$43.000
|
$8.000
|
$12.600
|
$25.000
|
$2.000
|
|
|
EMULSION
|
GAL
|
978,048.000
|
$2.650
|
$2.700
|
$3.000
|
$2.750
|
$3.000
|
|
|
CEMENT
|
TON
|
966.000
|
$201.500
|
$168.000
|
$185.000
|
$168.000
|
$210.000
|
|
|
EMUL TRTMNT(MX EXST MTRL & NEW BASE)10"
|
SY
|
180,692.000
|
$4.000
|
$3.300
|
$7.850
|
$3.250
|
$8.200
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$14,500.000
|
$18,000.000
|
$6,900.000
|
$25,000.000
|
$25,000.000
|
|
|
TMA (STATIONARY)
|
EA
|
2.000
|
$17,000.000
|
$8,700.000
|
$40,000.000
|
$123,725.000
|
$25,000.000
|
|
Totals: |
$22,909,056.370
|
$22,480,668.540
|
$28,030,780.610
|
$29,436,820.350
|
$34,448,235.380
|