PREPARING ROW
|
AC
|
15.370
|
$250.000
|
$320.570
|
$900.000
|
$670.000
|
$78,074.180
|
$178.170
|
|
|
REMOVING CONC (CURB AND GUTTER)
|
LF
|
112.000
|
$20.000
|
$35.300
|
$50.000
|
$13.000
|
$13.920
|
$11.880
|
|
|
REMOVING STAB BASE AND ASPH PAV (3")
|
SY
|
2,857.000
|
$6.000
|
$8.580
|
$11.000
|
$8.650
|
$4.380
|
$10.110
|
|
|
REMOVING STAB BASE & ASPH PAV (9")
|
SY
|
48.000
|
$6.000
|
$61.310
|
$60.000
|
$56.450
|
$5.100
|
$38.280
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
6,988.000
|
$15.000
|
$14.350
|
$17.000
|
$30.000
|
$8.700
|
$11.420
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
3,235.000
|
$15.000
|
$12.590
|
$25.000
|
$40.000
|
$24.000
|
$10.850
|
|
|
BACKFILL (TY A OR B)
|
STA
|
696.000
|
$160.000
|
$211.470
|
$100.000
|
$212.500
|
$204.000
|
$90.970
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
AC
|
9.700
|
$820.000
|
$483.000
|
$420.000
|
$445.000
|
$858.000
|
$498.880
|
|
|
DRILL SEEDING (TEMP)(WARM OR COOL)
|
AC
|
24.390
|
$460.000
|
$293.250
|
$255.000
|
$270.000
|
$800.000
|
$302.890
|
|
|
FL BS (CMP IN PLC)(TY A OR B GR4)(10")
|
SY
|
33,913.000
|
$17.000
|
$23.180
|
$15.000
|
$28.000
|
$26.400
|
$30.950
|
|
|
FL BS (CMP IN PLC)(TY A OR B GR 4)(16")
|
SY
|
294.000
|
$64.000
|
$58.010
|
$100.000
|
$39.000
|
$36.000
|
$66.560
|
|
|
REWORK BS MTL (TY B)(12")(DENS CONT)
|
SY
|
16,187.000
|
$7.000
|
$16.850
|
$6.000
|
$9.000
|
$5.100
|
$9.870
|
|
|
CEMENT
|
TON
|
200.000
|
$200.000
|
$195.260
|
$170.000
|
$184.500
|
$192.000
|
$192.430
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
33,327.000
|
$3.500
|
$3.130
|
$4.000
|
$3.500
|
$4.800
|
$1.820
|
|
|
PRIME COAT (AE-P)
|
GAL
|
74.000
|
$5.000
|
$4.330
|
$6.000
|
$24.500
|
$4.800
|
$5.590
|
|
|
PRIME COAT (MC-30)
|
GAL
|
8,479.000
|
$3.750
|
$4.320
|
$5.000
|
$4.250
|
$5.820
|
$5.300
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
12,301.000
|
$4.000
|
$4.190
|
$5.000
|
$4.200
|
$4.740
|
$4.400
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
9,505.000
|
$90.000
|
$119.560
|
$117.000
|
$117.650
|
$96.000
|
$119.830
|
|
|
TACK COAT
|
GAL
|
4,479.000
|
$4.000
|
$5.920
|
$6.000
|
$3.450
|
$7.200
|
$6.520
|
|
|
SUPERPAVE MIXTURES SP-C SAC-A PG70-28
|
TON
|
46,924.000
|
$105.000
|
$124.450
|
$130.000
|
$111.500
|
$132.000
|
$130.460
|
|
|
TACK COAT
|
GAL
|
55,176.000
|
$4.000
|
$5.960
|
$6.000
|
$3.450
|
$3.960
|
$6.520
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(2")
|
SY
|
20,689.000
|
$15.000
|
$17.350
|
$19.000
|
$21.250
|
$19.800
|
$22.580
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
|
SY
|
21,934.000
|
$19.750
|
$25.140
|
$20.000
|
$29.650
|
$24.000
|
$32.800
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
4,223.000
|
$5.000
|
$5.820
|
$8.000
|
$5.800
|
$2.220
|
$4.760
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
21,749.000
|
$2.000
|
$2.450
|
$7.000
|
$3.100
|
$1.920
|
$2.480
|
|
|
PLANE ASPH CONC PAV (3"- 5")
|
SY
|
2,333.000
|
$5.000
|
$7.790
|
$7.000
|
$8.650
|
$2.190
|
$5.320
|
|
|
CUT & RESTORE ASPH PAVING
|
SY
|
18.000
|
$300.000
|
$206.180
|
$300.000
|
$220.000
|
$150.000
|
$90.750
|
|
|
FLOWABLE BACKFILL
|
CY
|
6.000
|
$465.000
|
$299.660
|
$800.000
|
$1,105.000
|
$183.600
|
$236.540
|
|
|
DRILL SHAFT (SIGN MTS) (24 IN)
|
LF
|
22.000
|
$300.000
|
$350.750
|
$605.000
|
$184.450
|
$198.000
|
$207.870
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
9.000
|
$500.000
|
$623.300
|
$545.000
|
$571.200
|
$480.000
|
$643.790
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
31.000
|
$560.000
|
$611.970
|
$535.000
|
$560.000
|
$600.000
|
$632.090
|
|
|
CONC BOX CULV (4 FT X 2 FT)(EXTEND)
|
LF
|
25.000
|
$750.000
|
$546.250
|
$475.000
|
$500.000
|
$948.000
|
$564.210
|
|
|
CONC BOX CULV (6 FT X 3 FT)(EXTEND)
|
LF
|
25.000
|
$800.000
|
$546.250
|
$475.000
|
$500.000
|
$990.000
|
$564.210
|
|
|
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
|
LF
|
59.000
|
$850.000
|
$546.250
|
$475.000
|
$500.000
|
$612.000
|
$564.210
|
|
|
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
|
LF
|
84.000
|
$900.000
|
$546.250
|
$775.000
|
$500.000
|
$888.000
|
$564.210
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
110.000
|
$150.000
|
$132.220
|
$180.000
|
$134.500
|
$87.000
|
$93.710
|
|
|
WINGWALL (PW - 1) (HW=5 FT)
|
EA
|
2.000
|
$15,000.000
|
$13,800.000
|
$12,000.000
|
$12,645.000
|
$13,800.000
|
$14,253.740
|
|
|
WINGWALL (PW - 1) (HW=6 FT)
|
EA
|
1.000
|
$15,000.000
|
$22,356.000
|
$19,500.000
|
$20,500.000
|
$19,200.000
|
$23,091.060
|
|
|
WINGWALL (PW - 1) (HW=7 FT)
|
EA
|
1.000
|
$27,000.000
|
$28,543.000
|
$25,000.000
|
$26,000.000
|
$25,200.000
|
$29,481.480
|
|
|
WINGWALL (PW - 1) (HW=8 FT)
|
EA
|
1.000
|
$27,000.000
|
$29,617.100
|
$26,000.000
|
$63,500.000
|
$30,000.000
|
$30,590.900
|
|
|
SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C)
|
EA
|
1.000
|
$1,400.000
|
$11,820.520
|
$11,100.000
|
$11,800.000
|
$10,800.000
|
$12,858.060
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,450.000
|
$3,980.990
|
$10,000.000
|
$5,460.000
|
$1,800.000
|
$2,245.450
|
|
|
REMOV STR (SET)
|
EA
|
4.000
|
$1,400.000
|
$1,200.000
|
$1,000.000
|
$1,780.000
|
$1,200.000
|
$1,235.980
|
|
|
REMOV STR (WINGWALL)
|
EA
|
4.000
|
$1,400.000
|
$1,750.000
|
$1,500.000
|
$2,375.000
|
$2,040.000
|
$1,396.900
|
|
|
REMOV STR (PIPE)
|
LF
|
40.000
|
$150.000
|
$50.000
|
$30.000
|
$47.500
|
$18.000
|
$32.060
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
106.000
|
$152.000
|
$300.000
|
$30.000
|
$405.000
|
$78.000
|
$255.740
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$750,000.000
|
$900,000.000
|
$1,200,000.000
|
$1,200,000.000
|
$1,200,000.000
|
$1,368,464.840
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
11.000
|
$20,000.000
|
$15,000.000
|
$20,000.000
|
$36,150.000
|
$9,300.000
|
$40,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
825.000
|
$4.000
|
$3.570
|
$5.230
|
$8.000
|
$5.400
|
$3.680
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
825.000
|
$1.000
|
$1.150
|
$0.450
|
$3.200
|
$1.200
|
$1.190
|
|
|
PERM CTB (SGL SLOPE) (TY 1) (42 )
|
LF
|
500.000
|
$125.000
|
$114.090
|
$100.000
|
$104.600
|
$102.000
|
$117.840
|
|
|
CONC CURB & GUTTER (TY II)
|
LF
|
327.000
|
$20.000
|
$40.370
|
$36.000
|
$37.000
|
$28.800
|
$41.690
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
155,540.000
|
$0.110
|
$0.140
|
$0.210
|
$0.110
|
$0.240
|
$0.170
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
68,890.000
|
$0.200
|
$0.140
|
$0.170
|
$0.250
|
$0.240
|
$0.170
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,625.000
|
$26.000
|
$28.750
|
$30.000
|
$26.350
|
$31.800
|
$35.630
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
16.000
|
$2,200.000
|
$2,300.000
|
$560.000
|
$2,110.000
|
$2,220.000
|
$665.170
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
2,200.000
|
$3.000
|
$3.450
|
$3.000
|
$3.150
|
$3.360
|
$3.560
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
16.000
|
$2,900.000
|
$3,450.000
|
$2,925.000
|
$3,160.000
|
$3,300.000
|
$3,474.350
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
16.000
|
$305.000
|
$345.000
|
$480.000
|
$315.000
|
$360.000
|
$570.150
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
156.000
|
$27.000
|
$46.000
|
$40.000
|
$37.000
|
$30.000
|
$41.570
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
29.000
|
$1,500.000
|
$832.600
|
$724.000
|
$815.000
|
$582.000
|
$920.550
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$894.000
|
$847.550
|
$737.000
|
$845.000
|
$708.000
|
$950.250
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
1.000
|
$1,500.000
|
$1,138.500
|
$990.000
|
$1,100.000
|
$810.000
|
$1,247.200
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
32.000
|
$105.000
|
$143.750
|
$105.000
|
$130.000
|
$120.000
|
$148.480
|
|
|
INSTALL LRSS (STRUCT STEEL)
|
LB
|
900.000
|
$6.200
|
$11.500
|
$10.000
|
$5.250
|
$12.000
|
$5.940
|
|
|
REMOVE LRSA
|
EA
|
2.000
|
$1,265.000
|
$1,725.000
|
$1,500.000
|
$1,055.000
|
$1,140.000
|
$1,187.810
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND
|
EA
|
51.000
|
$135.000
|
$136.850
|
$119.000
|
$140.000
|
$108.000
|
$160.350
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND(BI)
|
EA
|
12.000
|
$135.000
|
$136.850
|
$119.000
|
$140.000
|
$90.000
|
$160.350
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
|
EA
|
24.000
|
$30.000
|
$40.250
|
$44.000
|
$37.000
|
$30.000
|
$41.570
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
3,140.000
|
$0.300
|
$0.400
|
$0.350
|
$0.370
|
$0.360
|
$0.420
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
37,175.000
|
$0.300
|
$0.400
|
$0.350
|
$0.370
|
$0.300
|
$0.420
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
4,180.000
|
$1.050
|
$1.470
|
$1.000
|
$1.200
|
$1.200
|
$2.380
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
12,120.000
|
$1.100
|
$1.470
|
$1.000
|
$1.250
|
$1.800
|
$2.380
|
|
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
|
LF
|
150.000
|
$12.000
|
$23.000
|
$20.000
|
$21.100
|
$12.000
|
$23.760
|
|
REFL PAV MRK TY I (W)(RR XING)(090MIL)
|
EA
|
1.000
|
$700.000
|
$1,150.000
|
$1,000.000
|
$1,055.000
|
$648.000
|
$1,187.810
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(090MIL)
|
LF
|
13,910.000
|
$0.350
|
$0.410
|
$0.360
|
$0.380
|
$0.420
|
$0.430
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
147,670.000
|
$0.350
|
$0.410
|
$0.360
|
$0.380
|
$0.360
|
$0.430
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
2,340.000
|
$0.350
|
$0.410
|
$0.360
|
$0.380
|
$0.360
|
$0.430
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
148,290.000
|
$0.350
|
$0.410
|
$0.360
|
$0.380
|
$0.360
|
$0.430
|
|
REFL PAV MRKR TY I-A
|
EA
|
1,974.000
|
$3.500
|
$3.740
|
$3.250
|
$3.450
|
$4.800
|
$3.860
|
|
REFL PAV MRKR TY I-C
|
EA
|
696.000
|
$3.500
|
$3.740
|
$3.250
|
$3.450
|
$3.900
|
$3.860
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
870.000
|
$0.750
|
$2.300
|
$2.000
|
$2.100
|
$0.480
|
$2.380
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$15,000.000
|
$10,338.090
|
$12,500.000
|
$21,500.000
|
$10,200.000
|
$25,862.650
|
|
|
TMA (STATIONARY)
|
DAY
|
104.000
|
$460.000
|
$410.220
|
$950.000
|
$675.000
|
$252.000
|
$428.570
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
160.000
|
$65.000
|
$71.950
|
$10.000
|
$67.500
|
$60.000
|
$90.600
|
|
Totals: |
$10,000,117.050
|
$11,978,029.648
|
$12,176,951.500
|
$12,246,482.100
|
$13,372,225.137
|
$13,389,433.756
|