|
|
REMOVING CONC (PAV)
|
SY
|
8,178.000
|
$10.350
|
$11.000
|
$10.290
|
$17.500
|
$12.000
|
$14.700
|
$10.290
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
802.230
|
$11.450
|
$12.000
|
$11.440
|
$20.000
|
$15.000
|
$14.700
|
$11.440
|
|
|
REMOVING CONC (CURB)
|
LF
|
840.000
|
$5.000
|
$4.000
|
$3.740
|
$20.000
|
$15.000
|
$10.500
|
$3.740
|
|
|
REMOVING STAB BASE & ASPH PAV (7"-12")
|
SY
|
9,214.000
|
$5.250
|
$5.000
|
$7.040
|
$10.000
|
$5.500
|
$10.500
|
$10.780
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,474.000
|
$7.450
|
$22.000
|
$21.340
|
$20.000
|
$33.000
|
$21.000
|
$21.340
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
215.000
|
$11.100
|
$44.000
|
$42.460
|
$30.000
|
$25.000
|
$21.000
|
$42.460
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
3,395.000
|
$1.130
|
$3.000
|
$2.500
|
$6.000
|
$7.000
|
$2.520
|
$3.000
|
|
|
BLOCK SODDING
|
SY
|
3,395.000
|
$3.150
|
$7.000
|
$6.840
|
$6.000
|
$7.000
|
$7.350
|
$7.000
|
|
|
VEGETATIVE WATERING
|
MG
|
505.000
|
$12.000
|
$60.000
|
$57.670
|
$50.000
|
$60.000
|
$3.150
|
$57.670
|
|
|
LIME (HYD, COM, OR QK(SLURRY))
|
TON
|
210.000
|
$172.000
|
$211.000
|
$202.400
|
$185.000
|
$187.000
|
$189.000
|
$180.000
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
12,746.000
|
$4.000
|
$6.000
|
$5.390
|
$6.000
|
$3.500
|
$3.150
|
$4.600
|
|
|
SUPERPAVE MIXTURES SP-B PG64-22
|
TON
|
2,804.000
|
$80.000
|
$46.000
|
$85.090
|
$95.000
|
$110.000
|
$105.000
|
$90.970
|
|
|
CONC PVMT (CONT REINF - CRCP) (12")
|
SY
|
8,039.000
|
$72.000
|
$48.000
|
$91.500
|
$80.000
|
$105.000
|
$84.000
|
$99.250
|
|
|
CONC PVMT (CONT REINF-CRCP) (HES)(12")
|
SY
|
2,608.000
|
$90.000
|
$355.000
|
$102.000
|
$95.000
|
$125.000
|
$126.000
|
$148.250
|
|
|
FULL - DEPTH REPAIR CPCD (9")
|
SY
|
4,511.300
|
$150.000
|
$46.000
|
$210.000
|
$205.000
|
$175.000
|
$235.350
|
$199.950
|
|
|
FULL - DEPTH REPAIR CPJR (9")
|
SY
|
1,588.000
|
$155.000
|
$48.000
|
$305.000
|
$225.000
|
$380.000
|
$337.900
|
$479.850
|
|
|
CLEANING AND SEALING EXISTING JOINTS
|
LF
|
2,600.000
|
$5.000
|
$53.000
|
$17.000
|
$10.000
|
$2.000
|
$18.530
|
$2.700
|
|
|
ADJUSTING INLETS
|
EA
|
2.000
|
$1,580.000
|
$401.000
|
$5,000.000
|
$1,500.000
|
$2,000.000
|
$3,150.000
|
$11,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$273,893.520
|
$180,000.000
|
$186,000.000
|
$300,000.000
|
$252,000.000
|
$482,000.000
|
$250,350.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$15,000.000
|
$1,719.000
|
$6,800.000
|
$8,500.000
|
$13,500.000
|
$21,000.000
|
$17,550.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
24.000
|
$28.750
|
$57.000
|
$80.500
|
$30.000
|
$81.000
|
$31.500
|
$33.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
24.000
|
$9.770
|
$29.000
|
$46.280
|
$15.000
|
$46.000
|
$15.750
|
$16.500
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
155.560
|
$21.000
|
$19.000
|
$30.610
|
$45.000
|
$31.000
|
$21.000
|
$22.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
155.560
|
$8.900
|
$10.000
|
$9.680
|
$20.000
|
$10.000
|
$10.500
|
$11.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,600.000
|
$1.670
|
$2.000
|
$3.750
|
$4.000
|
$4.000
|
$1.520
|
$1.600
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,600.000
|
$0.550
|
$0.500
|
$0.530
|
$2.000
|
$1.000
|
$0.110
|
$0.110
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
430.000
|
$3.930
|
$4.000
|
$5.040
|
$15.000
|
$5.000
|
$3.680
|
$3.850
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
430.000
|
$0.660
|
$1.000
|
$0.430
|
$9.000
|
$1.000
|
$1.050
|
$1.100
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
2,560.000
|
$40.000
|
$70.000
|
$28.600
|
$72.000
|
$52.000
|
$21.000
|
$28.600
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
60.000
|
$60.000
|
$70.000
|
$57.200
|
$72.000
|
$52.000
|
$31.500
|
$57.200
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
1,680.000
|
$6.000
|
$57.000
|
$5.500
|
$20.000
|
$10.000
|
$3.150
|
$5.500
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
20.000
|
$8.500
|
$57.000
|
$11.000
|
$20.000
|
$10.000
|
$21.000
|
$11.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
2,560.000
|
$10.000
|
$57.000
|
$7.700
|
$20.000
|
$9.000
|
$5.250
|
$7.700
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
60.000
|
$10.000
|
$69.000
|
$15.400
|
$20.000
|
$9.000
|
$13.650
|
$15.400
|
|
|
CONC CURB (TY I)
|
LF
|
840.000
|
$28.000
|
$45.000
|
$64.000
|
$18.000
|
$60.000
|
$69.760
|
$35.000
|
|
|
CONC CURB (MONO) (TY II)
|
LF
|
2,994.000
|
$6.000
|
$46.000
|
$5.000
|
$12.000
|
$2.000
|
$3.150
|
$4.000
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
802.230
|
$88.000
|
$84.000
|
$100.000
|
$110.000
|
$80.000
|
$126.000
|
$69.000
|
|
|
CONC SIDEWALKS (5")
|
SY
|
657.000
|
$50.000
|
$69.000
|
$80.000
|
$60.000
|
$57.000
|
$84.000
|
$68.810
|
|
|
CURB RAMPS (TY 1)
|
EA
|
1.000
|
$1,900.000
|
$2,062.000
|
$2,000.000
|
$2,000.000
|
$850.000
|
$2,100.000
|
$1,672.000
|
|
|
CURB RAMPS (TY 7)
|
EA
|
7.000
|
$1,450.000
|
$2,062.000
|
$1,750.000
|
$2,000.000
|
$1,365.000
|
$2,100.000
|
$1,672.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
292.000
|
$7.500
|
$32.000
|
$16.500
|
$15.000
|
$12.000
|
$15.750
|
$16.500
|
|
|
CONDT (PVC) (SCH 40) (2") (BORE)
|
LF
|
78.000
|
$26.000
|
$28.000
|
$37.400
|
$40.000
|
$27.000
|
$35.700
|
$37.400
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
2.000
|
$1,050.000
|
$903.000
|
$1,485.000
|
$850.000
|
$864.000
|
$1,417.500
|
$1,485.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
2,581.000
|
$0.260
|
$2.000
|
$2.200
|
$1.000
|
$2.200
|
$2.100
|
$1.650
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
1,933.000
|
$0.780
|
$1.000
|
$1.100
|
$1.000
|
$1.100
|
$1.050
|
$2.750
|
|
|
WK ZN PAV MRK REMOV (W)(ARROW)
|
EA
|
4.000
|
$135.000
|
$229.000
|
$220.000
|
$250.000
|
$220.000
|
$210.000
|
$259.600
|
|
|
WK ZN PAV MRK REMOV (W)(DBL ARROW)
|
EA
|
4.000
|
$125.000
|
$344.000
|
$330.000
|
$250.000
|
$330.000
|
$315.000
|
$481.800
|
|
|
WK ZN PAV MRK REMOV (W)(UTURN ARROW)
|
EA
|
1.000
|
$99.000
|
$344.000
|
$330.000
|
$250.000
|
$330.000
|
$315.000
|
$533.500
|
|
|
WK ZN PAV MRK REMOV (W)(WORD)
|
EA
|
2.000
|
$160.000
|
$286.000
|
$275.000
|
$250.000
|
$275.000
|
$262.500
|
$294.800
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
2,322.000
|
$0.800
|
$1.000
|
$1.100
|
$1.000
|
$1.100
|
$1.050
|
$2.810
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
835.000
|
$1.050
|
$1.000
|
$1.100
|
$6.000
|
$1.100
|
$1.050
|
$2.370
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
427.000
|
$4.500
|
$4.000
|
$3.850
|
$6.000
|
$3.850
|
$3.680
|
$5.280
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
60.000
|
$6.250
|
$7.000
|
$6.600
|
$20.000
|
$6.600
|
$6.300
|
$9.300
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
63.000
|
$140.000
|
$160.000
|
$154.000
|
$250.000
|
$154.000
|
$147.000
|
$140.800
|
|
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
|
EA
|
3.000
|
$1,000.000
|
$401.000
|
$385.000
|
$500.000
|
$385.000
|
$367.500
|
$870.100
|
|
|
PAVEMENT SEALER 4"
|
LF
|
54,327.000
|
$0.170
|
$0.150
|
$0.130
|
$0.500
|
$0.130
|
$0.130
|
$0.280
|
|
|
PAVEMENT SEALER 8"
|
LF
|
985.000
|
$0.350
|
$0.300
|
$0.280
|
$1.000
|
$0.280
|
$0.260
|
$1.490
|
|
|
PAVEMENT SEALER 12"
|
LF
|
427.000
|
$1.000
|
$1.000
|
$1.050
|
$1.000
|
$1.050
|
$1.000
|
$1.930
|
|
|
PAVEMENT SEALER 24"
|
LF
|
60.000
|
$2.640
|
$3.000
|
$3.300
|
$1.000
|
$3.300
|
$3.150
|
$2.530
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
15.000
|
$30.000
|
$40.000
|
$38.500
|
$150.000
|
$38.500
|
$36.750
|
$25.300
|
|
|
PAVEMENT SEALER (EXIT GORE)
|
EA
|
3.000
|
$370.000
|
$229.000
|
$220.000
|
$150.000
|
$220.000
|
$210.000
|
$301.400
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
6,212.000
|
$0.500
|
$1.000
|
$0.770
|
$0.500
|
$0.770
|
$0.740
|
$0.880
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
24,049.000
|
$0.450
|
$1.000
|
$0.660
|
$0.500
|
$0.660
|
$0.630
|
$0.660
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
24,065.000
|
$0.450
|
$1.000
|
$0.660
|
$0.500
|
$0.660
|
$0.630
|
$0.660
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
392.000
|
$5.000
|
$6.000
|
$5.500
|
$15.000
|
$5.500
|
$5.250
|
$9.080
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
54,327.000
|
$0.500
|
$1.000
|
$0.500
|
$0.500
|
$0.500
|
$0.470
|
$0.610
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
835.000
|
$0.750
|
$1.000
|
$0.880
|
$6.000
|
$0.880
|
$0.840
|
$1.870
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
427.000
|
$1.750
|
$2.000
|
$2.200
|
$6.000
|
$2.200
|
$2.100
|
$2.700
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
15.000
|
$45.000
|
$63.000
|
$60.500
|
$150.000
|
$60.500
|
$57.750
|
$62.700
|
|
|
ELIM EXT PAV MRK & MRKS (EXIT GORE)
|
EA
|
3.000
|
$350.000
|
$200.000
|
$192.500
|
$150.000
|
$192.500
|
$183.750
|
$605.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
54,327.000
|
$0.100
|
$0.500
|
$0.030
|
$0.500
|
$0.030
|
$0.030
|
$0.170
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
835.000
|
$0.170
|
$0.500
|
$0.060
|
$0.500
|
$0.060
|
$0.050
|
$1.320
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
427.000
|
$0.500
|
$1.000
|
$0.830
|
$0.500
|
$0.830
|
$0.790
|
$1.100
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
60.000
|
$1.150
|
$2.000
|
$2.200
|
$0.500
|
$2.200
|
$2.100
|
$2.420
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
15.000
|
$20.000
|
$34.000
|
$33.000
|
$150.000
|
$33.000
|
$31.500
|
$24.200
|
|
|
PAV SURF PREP FOR MRK (EXIT GORE)
|
EA
|
3.000
|
$316.000
|
$172.000
|
$165.000
|
$150.000
|
$165.000
|
$157.500
|
$214.500
|
|
|
TRF SIG CBL (TY C)(18 AWG)(2 CONDR)
|
LF
|
589.000
|
$2.000
|
$7.000
|
$4.400
|
$3.000
|
$1.500
|
$4.200
|
$4.400
|
|
|
VEH LP DETECT (SAWCUT)
|
LF
|
271.000
|
$12.000
|
$17.000
|
$49.500
|
$11.000
|
$13.000
|
$47.250
|
$49.500
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$15,000.000
|
$1,375.000
|
$20,000.000
|
$12,500.000
|
$15,000.000
|
$14,700.000
|
$19,500.000
|
|
|
CONDUIT (PREPARE)
|
LF
|
72.000
|
$1.250
|
$7.000
|
$5.500
|
$6.000
|
$6.000
|
$5.250
|
$5.500
|
|
|
GROUND BOX (PREPARE)
|
EA
|
4.000
|
$300.000
|
$286.000
|
$440.000
|
$150.000
|
$275.000
|
$420.000
|
$440.000
|
|
|
TMA (STATIONARY)
|
EA
|
2.000
|
$15,000.000
|
$16,040.000
|
$26,000.000
|
$12,500.000
|
$15,000.000
|
$22,050.000
|
$77,000.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
21.000
|
$290.000
|
$1,350.000
|
$250.000
|
$850.000
|
$550.000
|
$250.000
|
$625.000
|
|
Totals: |
$3,132,828.758
|
$3,472,552.670
|
$3,941,853.244
|
$4,099,363.300
|
$4,226,549.620
|
$4,549,146.206
|
$4,597,314.466
|