PREPARING ROW
|
STA
|
71.490
|
$3,000.000
|
$1,533.000
|
$2,425.000
|
$3,300.000
|
$500.000
|
$3,400.000
|
$3,400.000
|
$400.000
|
$1,500.000
|
$3,500.000
|
$1,230.730
|
|
|
REMOVING CONC (PAV)
|
SY
|
1,415.000
|
$15.000
|
$8.770
|
$10.000
|
$12.000
|
$19.000
|
$10.000
|
$15.000
|
$13.250
|
$19.000
|
$15.000
|
$13.020
|
|
|
REMOVING CONC (CURB)
|
LF
|
510.000
|
$9.500
|
$2.850
|
$3.000
|
$2.500
|
$1.000
|
$5.000
|
$5.000
|
$7.500
|
$7.250
|
$12.500
|
$7.810
|
|
|
REMOVING CONC (FLUME)
|
SY
|
1,267.000
|
$12.000
|
$3.300
|
$10.000
|
$8.500
|
$3.000
|
$10.000
|
$5.000
|
$10.950
|
$7.000
|
$20.000
|
$26.050
|
|
|
REMOVING STAB BASE & ASPH PAV(14")
|
SY
|
5,817.000
|
$8.000
|
$6.020
|
$7.500
|
$7.000
|
$12.000
|
$8.000
|
$10.000
|
$8.150
|
$8.500
|
$10.000
|
$9.120
|
|
|
REMOVING STAB BASE & ASPH PAV (12")
|
SY
|
1,415.000
|
$14.000
|
$6.520
|
$7.000
|
$7.250
|
$11.000
|
$7.500
|
$8.000
|
$8.250
|
$9.000
|
$10.000
|
$8.470
|
|
|
REMOV STAB BASE AND ASPH PAV (22")
|
SY
|
839.000
|
$11.500
|
$11.090
|
$16.000
|
$12.150
|
$21.000
|
$17.000
|
$15.000
|
$13.500
|
$16.500
|
$20.000
|
$19.540
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
10,196.300
|
$12.000
|
$8.930
|
$15.000
|
$10.000
|
$14.000
|
$15.000
|
$13.000
|
$18.250
|
$15.000
|
$15.000
|
$23.270
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
2,922.100
|
$15.000
|
$8.320
|
$11.000
|
$10.000
|
$8.000
|
$20.000
|
$20.000
|
$29.500
|
$24.000
|
$20.000
|
$34.530
|
|
|
BACKFILL (TY A OR B)
|
STA
|
54.470
|
$225.000
|
$483.150
|
$250.000
|
$180.000
|
$320.000
|
$180.000
|
$350.000
|
$275.000
|
$282.000
|
$250.000
|
$227.910
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
14,094.000
|
$1.500
|
$1.750
|
$1.250
|
$2.000
|
$4.000
|
$1.250
|
$3.500
|
$1.250
|
$2.250
|
$3.000
|
$0.940
|
|
|
BLOCK SODDING
|
SY
|
14,094.000
|
$3.250
|
$2.780
|
$3.000
|
$3.200
|
$3.000
|
$3.750
|
$2.900
|
$3.000
|
$3.000
|
$4.000
|
$3.580
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
14,094.000
|
$0.200
|
$0.170
|
$0.010
|
$0.180
|
$0.170
|
$0.160
|
$0.210
|
$0.180
|
$0.250
|
$0.500
|
$0.260
|
|
|
VEGETATIVE WATERING
|
MG
|
4,194.000
|
$10.000
|
$15.850
|
$1.050
|
$9.000
|
$12.000
|
$1.000
|
$19.000
|
$6.750
|
$14.920
|
$15.000
|
$35.580
|
|
|
FL BS (CMP IN PLC)(TY D GR1-2)(8")
|
SY
|
6,016.000
|
$17.500
|
$12.000
|
$10.500
|
$12.000
|
$12.000
|
$15.000
|
$13.000
|
$15.650
|
$17.000
|
$16.500
|
$16.310
|
|
|
FL BS (CMP IN PLC)(TY D GR1-2)(12")
|
SY
|
5,548.000
|
$21.000
|
$16.960
|
$16.000
|
$17.000
|
$26.000
|
$22.000
|
$16.000
|
$21.400
|
$27.000
|
$22.000
|
$22.050
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
1,810.000
|
$4.500
|
$2.500
|
$4.000
|
$4.000
|
$6.000
|
$2.500
|
$2.600
|
$3.350
|
$5.500
|
$6.000
|
$4.040
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
361.000
|
$8.000
|
$4.000
|
$11.000
|
$11.000
|
$6.000
|
$10.000
|
$7.400
|
$6.000
|
$11.000
|
$20.000
|
$13.020
|
|
|
PLANE ASPH CONC PAV (5")
|
SY
|
17,879.000
|
$4.000
|
$2.800
|
$3.000
|
$3.000
|
$3.500
|
$2.600
|
$1.590
|
$3.200
|
$2.750
|
$4.000
|
$3.390
|
|
|
CONC PVMT (CONT REINF - CRCP) (9")
|
SY
|
2,752.000
|
$70.000
|
$85.810
|
$65.000
|
$68.000
|
$79.000
|
$85.000
|
$80.000
|
$113.000
|
$91.110
|
$62.000
|
$32.560
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
98.000
|
$11.000
|
$1.660
|
$15.000
|
$10.000
|
$2.000
|
$1.000
|
$11.000
|
$28.000
|
$5.500
|
$10.000
|
$19.540
|
|
|
DRILL SHAFT (SIGN MTS) (24 IN)
|
LF
|
23.000
|
$140.000
|
$200.270
|
$186.380
|
$190.000
|
$220.000
|
$235.820
|
$205.000
|
$220.500
|
$233.000
|
$265.000
|
$255.260
|
|
|
DRILL SHAFT (SIGN MTS) (54 IN)
|
LF
|
17.000
|
$490.000
|
$502.780
|
$692.250
|
$675.000
|
$620.000
|
$485.710
|
$585.000
|
$630.000
|
$635.000
|
$525.000
|
$726.720
|
|
|
DRILL SHAFT (RDWY ILL POLE) (30 IN)
|
LF
|
72.000
|
$250.000
|
$325.000
|
$346.130
|
$340.000
|
$230.000
|
$285.000
|
$210.000
|
$225.000
|
$265.000
|
$325.000
|
$259.170
|
|
|
RIPRAP (CONC)(CL B)
|
CY
|
3.150
|
$600.000
|
$900.860
|
$1,250.000
|
$825.000
|
$1,700.000
|
$650.000
|
$750.000
|
$850.000
|
$1,300.000
|
$650.000
|
$543.950
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
98.000
|
$88.000
|
$223.230
|
$125.000
|
$150.000
|
$290.000
|
$120.000
|
$200.000
|
$185.600
|
$375.000
|
$125.000
|
$90.500
|
|
|
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
|
EA
|
5.000
|
$5,500.000
|
$5,139.170
|
$6,000.000
|
$7,000.000
|
$7,600.000
|
$4,000.000
|
$6,000.000
|
$6,750.000
|
$7,100.000
|
$8,500.000
|
$9,637.470
|
|
|
CL C CONC (INLET) (TOP)
|
SY
|
5.000
|
$1,000.000
|
$2,357.040
|
$1,000.000
|
$3,000.000
|
$1,300.000
|
$500.000
|
$1,000.000
|
$2,800.000
|
$1,800.000
|
$250.000
|
$1,953.540
|
|
|
REMOV STR (INLET)
|
EA
|
2.000
|
$720.000
|
$721.140
|
$1,000.000
|
$2,500.000
|
$1,900.000
|
$450.000
|
$500.000
|
$1,125.000
|
$1,000.000
|
$2,500.000
|
$717.410
|
|
|
REMOV STR (PIPE)
|
LF
|
80.000
|
$25.000
|
$30.450
|
$15.000
|
$40.000
|
$29.000
|
$25.000
|
$30.000
|
$39.350
|
$25.000
|
$30.000
|
$17.580
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$227,493.720
|
$214,000.000
|
$225,500.000
|
$236,000.000
|
$240,000.000
|
$240,000.000
|
$200,000.000
|
$260,000.000
|
$270,000.000
|
$250,000.000
|
$299,543.080
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
8.000
|
$10,000.000
|
$1,564.930
|
$21,000.000
|
$10,500.000
|
$5,500.000
|
$16,800.000
|
$10,000.000
|
$21,000.000
|
$10,000.000
|
$8,500.000
|
$26,047.220
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
17.000
|
$55.000
|
$67.720
|
$37.280
|
$69.000
|
$350.000
|
$65.000
|
$57.000
|
$70.000
|
$73.000
|
$30.000
|
$91.170
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
17.000
|
$13.500
|
$36.460
|
$18.640
|
$35.000
|
$120.000
|
$35.000
|
$9.250
|
$38.000
|
$40.000
|
$15.000
|
$45.580
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
492.000
|
$23.000
|
$33.860
|
$21.300
|
$35.000
|
$40.000
|
$32.500
|
$21.000
|
$35.000
|
$36.000
|
$40.000
|
$22.140
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
492.000
|
$8.750
|
$10.940
|
$10.650
|
$10.000
|
$9.000
|
$10.500
|
$9.250
|
$11.250
|
$12.000
|
$20.000
|
$12.050
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
15,658.000
|
$2.250
|
$2.140
|
$1.490
|
$2.800
|
$2.500
|
$2.050
|
$1.750
|
$2.130
|
$2.300
|
$3.000
|
$3.910
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
15,658.000
|
$0.650
|
$0.570
|
$0.110
|
$0.500
|
$0.600
|
$0.550
|
$0.520
|
$0.580
|
$0.600
|
$1.000
|
$1.300
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
1,663.000
|
$3.250
|
$4.690
|
$3.140
|
$4.800
|
$5.000
|
$4.500
|
$3.000
|
$4.750
|
$5.000
|
$15.000
|
$5.180
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,663.000
|
$1.000
|
$0.890
|
$1.070
|
$0.800
|
$0.900
|
$0.850
|
$0.900
|
$0.900
|
$0.950
|
$5.000
|
$1.470
|
|
|
CONC CURB (TY II)
|
LF
|
374.000
|
$21.000
|
$6.880
|
$25.000
|
$30.000
|
$49.000
|
$10.000
|
$20.000
|
$22.500
|
$24.000
|
$20.000
|
$11.770
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
1,058.000
|
$2.000
|
$4.500
|
$4.250
|
$4.250
|
$5.000
|
$4.500
|
$4.750
|
$5.600
|
$5.000
|
$5.000
|
$10.440
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
125.000
|
$22.000
|
$25.000
|
$19.170
|
$20.000
|
$23.000
|
$18.000
|
$19.000
|
$28.000
|
$19.000
|
$25.000
|
$25.290
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
1.000
|
$1,200.000
|
$1,250.000
|
$1,171.500
|
$2,000.000
|
$1,500.000
|
$1,100.000
|
$1,150.000
|
$1,400.000
|
$1,200.000
|
$1,850.000
|
$1,488.610
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
771.000
|
$3.500
|
$4.000
|
$3.200
|
$3.200
|
$5.500
|
$3.000
|
$3.150
|
$4.500
|
$3.000
|
$3.000
|
$3.360
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
2.000
|
$200.000
|
$300.000
|
$159.750
|
$170.000
|
$260.000
|
$150.000
|
$158.000
|
$350.000
|
$160.000
|
$500.000
|
$526.100
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
1.000
|
$3,000.000
|
$2,650.000
|
$2,635.880
|
$4,000.000
|
$2,900.000
|
$2,475.000
|
$2,600.000
|
$3,000.000
|
$2,800.000
|
$2,850.000
|
$3,184.870
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$190.000
|
$300.000
|
$234.300
|
$750.000
|
$260.000
|
$220.000
|
$231.000
|
$350.000
|
$235.000
|
$1,500.000
|
$358.210
|
|
|
RELOCATE RD IL ASM (TRANS-BASE)
|
EA
|
9.000
|
$2,900.000
|
$2,875.000
|
$3,061.880
|
$5,000.000
|
$2,000.000
|
$1,500.000
|
$1,900.000
|
$2,050.000
|
$3,900.000
|
$1,500.000
|
$2,357.270
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
1,289.000
|
$8.000
|
$9.500
|
$10.120
|
$10.000
|
$15.000
|
$8.950
|
$14.000
|
$15.000
|
$11.000
|
$10.000
|
$17.320
|
|
|
CONDT (PVC) (SCH 40) (2") (BORE)
|
LF
|
1,610.000
|
$18.000
|
$20.400
|
$21.730
|
$21.000
|
$20.000
|
$15.150
|
$19.000
|
$20.650
|
$27.000
|
$20.000
|
$23.900
|
|
|
ELEC CONDR (NO.8) BARE
|
LF
|
3,059.000
|
$1.000
|
$1.500
|
$1.600
|
$1.550
|
$1.700
|
$1.130
|
$1.650
|
$1.750
|
$1.600
|
$3.000
|
$2.020
|
|
|
ELEC CONDR (NO.8) INSULATED
|
LF
|
6,118.000
|
$1.000
|
$1.600
|
$1.700
|
$1.650
|
$2.000
|
$1.150
|
$1.800
|
$1.930
|
$2.200
|
$3.000
|
$2.210
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
4.000
|
$1,300.000
|
$1,250.000
|
$1,331.250
|
$1,400.000
|
$1,700.000
|
$989.210
|
$1,554.000
|
$1,675.000
|
$1,300.000
|
$1,100.000
|
$1,927.490
|
|
|
REMOVE GROUND BOX
|
EA
|
4.000
|
$100.000
|
$400.000
|
$426.000
|
$800.000
|
$400.000
|
$357.110
|
$378.000
|
$425.000
|
$275.000
|
$500.000
|
$468.850
|
|
|
ALUMINUM SIGNS (TY G)
|
SF
|
122.500
|
$28.000
|
$27.470
|
$25.560
|
$25.000
|
$26.000
|
$27.270
|
$26.000
|
$28.000
|
$32.000
|
$30.000
|
$32.300
|
|
|
ALUMINUM SIGNS (TY O)
|
SF
|
271.000
|
$30.000
|
$25.180
|
$23.430
|
$23.000
|
$31.000
|
$26.310
|
$30.000
|
$31.750
|
$32.000
|
$30.000
|
$36.790
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
3.000
|
$490.000
|
$532.150
|
$495.230
|
$500.000
|
$850.000
|
$587.000
|
$767.000
|
$820.000
|
$700.000
|
$850.000
|
$950.720
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
7.000
|
$620.000
|
$715.260
|
$665.630
|
$650.000
|
$1,000.000
|
$695.000
|
$935.000
|
$1,000.000
|
$700.000
|
$850.000
|
$1,160.400
|
|
|
IN SM RD SN SUP&AM TY10BWG(2)SA(P-EXAL)
|
EA
|
1.000
|
$1,740.000
|
$1,773.840
|
$1,650.750
|
$1,600.000
|
$2,400.000
|
$1,575.000
|
$2,268.000
|
$2,425.000
|
$1,850.000
|
$850.000
|
$2,813.100
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
1.000
|
$850.000
|
$898.360
|
$836.030
|
$800.000
|
$1,100.000
|
$975.000
|
$1,045.000
|
$1,125.000
|
$900.000
|
$850.000
|
$1,295.850
|
|
|
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
|
EA
|
1.000
|
$1,740.000
|
$2,231.610
|
$2,076.750
|
$2,000.000
|
$3,200.000
|
$1,573.060
|
$3,035.000
|
$3,250.000
|
$1,600.000
|
$850.000
|
$3,763.820
|
|
|
INSTALL LRSS (STRUCT STEEL)
|
LB
|
1,164.000
|
$7.500
|
$5.660
|
$5.270
|
$5.250
|
$5.500
|
$10.900
|
$5.200
|
$5.600
|
$11.000
|
$12.000
|
$6.450
|
|
|
RELOCATE LRSA
|
EA
|
1.000
|
$2,500.000
|
$3,433.240
|
$3,195.000
|
$15,000.000
|
$1,600.000
|
$2,519.320
|
$2,050.000
|
$2,225.000
|
$5,300.000
|
$3,000.000
|
$2,572.160
|
|
|
REMOVE LRSA
|
EA
|
4.000
|
$975.000
|
$1,716.620
|
$1,597.500
|
$5,000.000
|
$800.000
|
$1,145.140
|
$750.000
|
$800.000
|
$1,600.000
|
$1,500.000
|
$931.190
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
5.000
|
$53.000
|
$45.000
|
$48.460
|
$47.000
|
$90.000
|
$45.500
|
$86.000
|
$50.500
|
$50.000
|
$100.000
|
$103.440
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
2.000
|
$40.000
|
$45.000
|
$50.000
|
$40.000
|
$90.000
|
$50.000
|
$21.000
|
$50.500
|
$50.000
|
$50.000
|
$33.150
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
2,203.000
|
$1.300
|
$1.160
|
$2.100
|
$1.000
|
$0.900
|
$1.000
|
$0.830
|
$0.900
|
$1.750
|
$1.250
|
$1.300
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
450.000
|
$4.250
|
$5.140
|
$4.200
|
$4.450
|
$4.000
|
$3.600
|
$3.680
|
$4.000
|
$4.000
|
$4.000
|
$4.690
|
|
|
PAVEMENT SEALER 4"
|
LF
|
3,365.000
|
$0.300
|
$0.290
|
$0.270
|
$0.260
|
$0.250
|
$0.250
|
$0.210
|
$0.220
|
$0.400
|
$0.500
|
$0.330
|
|
|
PAVEMENT SEALER 8"
|
LF
|
991.000
|
$0.400
|
$0.590
|
$0.550
|
$0.520
|
$0.500
|
$1.000
|
$0.420
|
$0.450
|
$0.500
|
$1.250
|
$1.300
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
1,680.000
|
$0.750
|
$0.730
|
$0.600
|
$0.650
|
$0.600
|
$1.000
|
$0.530
|
$0.550
|
$1.250
|
$1.250
|
$1.300
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
11,313.000
|
$0.500
|
$0.650
|
$0.600
|
$0.570
|
$0.500
|
$0.750
|
$0.460
|
$0.500
|
$1.000
|
$1.000
|
$0.980
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
8,418.000
|
$0.750
|
$0.650
|
$0.600
|
$0.570
|
$0.500
|
$0.750
|
$0.460
|
$0.500
|
$1.000
|
$1.000
|
$0.980
|
|
REFL PAV MRKR TY I-R
|
EA
|
52.000
|
$5.000
|
$7.340
|
$8.000
|
$6.300
|
$5.500
|
$10.000
|
$5.250
|
$5.650
|
$8.000
|
$15.000
|
$13.020
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
156.000
|
$5.000
|
$7.340
|
$8.000
|
$6.300
|
$5.500
|
$6.000
|
$5.250
|
$5.650
|
$6.000
|
$10.000
|
$7.810
|
|
|
FULL - WIDTH MOWING
|
CYC
|
2.000
|
$4,000.000
|
$5,000.000
|
$1,325.000
|
$760.000
|
$3,900.000
|
$3,000.000
|
$650.000
|
$3,500.000
|
$2,600.000
|
$3,000.000
|
$4,976.130
|
|
|
LITTER REMOVAL
|
CYC
|
3.000
|
$1,500.000
|
$2,046.290
|
$1,575.000
|
$515.000
|
$900.000
|
$2,500.000
|
$1,600.000
|
$2,200.000
|
$3,000.000
|
$3,000.000
|
$2,805.400
|
|
|
SP MIXES SP-C SAC-B PG64-22
|
TON
|
7,054.000
|
$98.500
|
$83.250
|
$81.500
|
$80.000
|
$93.000
|
$83.250
|
$98.000
|
$94.000
|
$84.500
|
$93.000
|
$108.420
|
|
|
TACK COAT
|
GAL
|
2,291.000
|
$3.750
|
$2.750
|
$3.600
|
$3.750
|
$7.000
|
$2.750
|
$2.900
|
$3.500
|
$3.750
|
$6.000
|
$3.580
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$13,000.000
|
$11,157.900
|
$9,000.000
|
$9,250.000
|
$6,000.000
|
$5,000.000
|
$3,200.000
|
$10,000.000
|
$31,200.000
|
$10,000.000
|
$6,511.810
|
|
|
TMA (STATIONARY)
|
DAY
|
115.000
|
$275.000
|
$168.400
|
$175.000
|
$145.000
|
$200.000
|
$430.000
|
$175.000
|
$270.000
|
$150.000
|
$250.000
|
$325.590
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
80.000
|
$75.000
|
$54.810
|
$60.000
|
$70.000
|
$60.000
|
$100.000
|
$55.000
|
$17.500
|
$60.000
|
$55.000
|
$195.350
|
|
Totals: |
$2,510,430.870
|
$2,146,127.956
|
$2,279,937.180
|
$2,361,888.760
|
$2,416,224.130
|
$2,485,268.895
|
$2,490,428.480
|
$2,634,288.715
|
$2,647,017.440
|
$2,751,854.500
|
$2,978,923.852
|