DALLAS SL 12 (0581-01-177)

Items: 28

County: DALLAS
Length: 0.0000 MILES (3.9445 MILES)
Highway: SL 12
District: DALLAS
Control Number: 0581-01-177
DBE Goal: 0.0%
Project: STP 2026(862)HES
Guaranty: $62,000.00
Time: 180 WORKING DAYS
Engineer's Estimate: $3,098,427.50
Date: 08/06/2026 1:00 PM CDT (6 weeks ago) Changed
Contract Number: 8263026
Type: INSTALL ILLUMINATION
Project ID: A00206666
Contract Type: FEDERAL
Project Description: SAFETY LIGHTING
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 2 files available
Bidders (10)
E
Engineer's Estimate
$3,098,427.50
$2,138,842.27
Over/Under Est: -30.97% -$959,585.23
Over/Under Est: -27.2% -$842,764.19
Amt Left: 5.46% $116,821.04
Over/Under Est: -24.52% -$759,687.45
Amt Left: 9.35% $199,897.78
Delta: -3.68% -$83,076.74
$2,502,635.65
Over/Under Est: -19.23% -$595,791.85
Amt Left: 17.01% $363,793.38
Delta: -7.01% -$163,895.60
$2,520,779.79
Over/Under Est: -18.64% -$577,647.71
Amt Left: 17.86% $381,937.52
Delta: -0.73% -$18,144.14
Over/Under Est: -11.02% -$341,427.50
Amt Left: 28.9% $618,157.73
Delta: -9.37% -$236,220.21
$2,861,321.81
Over/Under Est: -7.65% -$237,105.69
Amt Left: 33.78% $722,479.54
Delta: -3.78% -$104,321.81
Over/Under Est: -5.59% -$173,203.75
Amt Left: 36.77% $786,381.48
Delta: -2.23% -$63,901.94
Over/Under Est: -1.78% -$55,218.50
Amt Left: 42.28% $904,366.73
Delta: -4.03% -$117,985.25
Over/Under Est: -1.36% -$42,111.10
Amt Left: 42.9% $917,474.13
Delta: -0.43% -$13,107.40

Bid Items & Bid Tabulations

28 Total 0 of 28
DALLAS  |  SL 12  |  DALLAS  |  0581-01-177  |  08/06/2026 1:00 PM CDT  |  $3,098,427.50  |  STP 2026(862)HES  |  INSTL ILLUM  |  180 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALBATROSS CONSTRUCTION LLC
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
VACA UNDERGROUND UTILITIES INC
MICA CORPORATION
SICE, INC.
FLORIDA TRAFFIC CONTROL DEVICES, INC.
ROAD SOLUTIONS L.L.C.
WG ENGINEERING & CONSTRUCTION, LLC
ELECNOR BELCO ELECTRIC, INC.
SELECT MAINTENANCE, L.L.C.
DRILL SHAFT (HIGH MAST POLE) (60 IN)
LF 144.000 $850.000 $553.090 $760.270 $800.000 $913.500 $832.004 $1,493.000 $1,000.000 $984.000 $715.000 $650.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 1,076.000 $350.000 $186.870 $197.820 $200.000 $163.150 $226.354 $316.000 $320.000 $278.000 $398.000 $200.000
RIPRAP (CONC)(4 IN)
CY 10.240 $850.000 $1,061.000 $826.000 $750.000 $1,260.000 $1,460.693 $1,510.000 $1,062.950 $825.000 $520.000 $900.000
MOBILIZATION
LS 1.000 $230,000.000 $151,077.350 $220,081.190 $100,000.000 $188,810.000 $231,343.780 $174,999.750 $150,000.000 $160,875.000 $340,000.200 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $10,000.000 $3,554.280 $3,137.450 $3,000.000 $25,671.000 $5,505.908 $11,900.000 $12,500.000 $7,225.000 $10,000.000 $27,500.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $150.000 $78.650 $67.570 $250.000 $234.700 $116.236 $164.000 $109.180 $135.000 $193.000 $100.000
TMA (STATIONARY)
DAY 180.000 $250.000 $236.740 $197.360 $150.000 $207.900 $258.166 $80.000 $300.000 $260.000 $155.000 $350.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 500.000 $8.500 $5.700 $8.530 $1.000 $7.350 $7.205 $7.900 $8.830 $7.000 $15.300 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 500.000 $2.000 $2.670 $2.630 $1.000 $2.100 $4.895 $2.250 $2.340 $2.000 $4.900 $1.000
REMOVE RD IL ASM (SHOE-BASE)
EA 22.000 $850.000 $181.910 $771.920 $500.000 $312.000 $183.531 $624.000 $785.830 $1,025.000 $378.000 $500.000
IN RD IL (U/P) (TY 1) (150W EQ) LED
EA 4.000 $2,050.000 $1,590.020 $1,343.110 $1,200.000 $1,542.000 $1,671.931 $1,600.000 $2,012.240 $1,751.000 $1,124.000 $1,250.000
IN RD IL (TY SA) 30T-4-4 (250W EQ) LED
EA 41.000 $6,000.000 $4,820.050 $4,668.560 $5,250.000 $4,031.000 $4,621.639 $4,540.000 $4,750.000 $4,645.000 $4,680.000 $4,500.000
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 91.000 $5,500.000 $4,304.590 $4,260.280 $5,000.000 $3,821.000 $4,395.701 $4,690.000 $4,500.000 $4,400.000 $4,787.000 $4,500.000
IN RD IL (TY SA) 50T-8 (400W EQ) LED
EA 2.000 $6,500.000 $4,708.730 $5,909.920 $6,500.000 $5,133.000 $5,802.102 $6,125.000 $5,100.000 $5,500.000 $6,512.000 $4,500.000
HI MST IL POLE (150 FT)( 80 MPH)
EA 4.000 $50,000.000 $46,882.640 $47,339.690 $51,000.000 $41,968.000 $52,760.241 $46,900.000 $54,216.000 $53,760.000 $61,500.000 $50,000.000
LED HI MST IL ASM (6 FIXT) (TY A)
EA 4.000 $36,210.000 $41,379.060 $40,702.510 $45,000.000 $26,850.000 $35,603.427 $44,100.000 $52,593.000 $40,780.000 $48,600.000 $40,000.000
CONDT (PVC) (SCH 40) (1")
LF 47.000 $16.000 $74.260 $13.920 $14.000 $10.210 $8.204 $14.000 $11.340 $19.000 $16.000 $20.000
CONDT (PVC) (SCH 40) (2")
LF 16,577.000 $18.000 $9.140 $9.810 $10.000 $10.060 $9.015 $11.400 $12.250 $21.000 $16.000 $12.000
CONDT (PVC) (SCH 40) (2") (BORE)
LF 13,794.000 $30.000 $12.120 $11.720 $13.000 $22.010 $19.565 $21.000 $28.000 $27.000 $20.000 $27.000
CONDT (PVC) (SCH 80) (2")
LF 465.000 $25.000 $18.820 $15.330 $13.000 $14.150 $9.564 $13.500 $21.000 $25.000 $18.000 $22.000
CONDT (RM) (1")
LF 133.000 $33.000 $54.140 $51.190 $28.000 $36.500 $30.886 $31.900 $30.890 $56.000 $40.000 $26.000
ELEC CONDR (NO.8) BARE
LF 133.000 $2.000 $15.260 $2.600 $2.250 $1.950 $1.723 $1.700 $2.620 $3.000 $2.000 $2.200
ELEC CONDR (NO.8) INSULATED
LF 266.000 $2.250 $8.170 $2.900 $2.300 $1.950 $1.950 $2.150 $2.720 $3.000 $2.000 $2.500
ELEC CONDR (NO.6) BARE
LF 30,181.000 $2.000 $1.820 $1.620 $2.400 $2.520 $2.286 $2.100 $2.000 $3.000 $2.500 $2.100
ELEC CONDR (NO.6) INSULATED
LF 60,289.000 $2.000 $1.900 $1.990 $3.000 $2.520 $2.555 $2.650 $2.100 $3.250 $2.500 $2.500
ELEC CONDR (NO.4) INSULATED
LF 3,446.000 $4.500 $2.920 $3.040 $4.100 $3.320 $3.405 $3.650 $3.650 $3.250 $3.500 $3.700
GROUND BOX TY A (122311)W/APRON
EA 71.000 $1,450.000 $1,206.040 $1,419.850 $1,250.000 $1,630.000 $1,762.342 $1,465.000 $1,500.000 $1,353.000 $1,345.000 $2,500.000
ELC SRV TY A 240/480 060(NS)SS(E)GC(U)
EA 6.000 $9,500.000 $7,690.950 $8,084.990 $7,500.000 $11,030.000 $8,755.516 $7,000.000 $10,000.000 $8,505.000 $8,500.000 $25,000.000
Totals: $3,098,427.500 $2,138,842.270 $2,255,663.310 $2,338,740.050 $2,502,635.650 $2,520,779.779 $2,757,000.000 $2,861,321.808 $2,925,223.750 $3,043,209.000 $3,056,316.400
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
PUBLIC UTILITY FORCE ACCT WORK (PART) $12,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
PUBLIC UTILITY FORCE ACCT WORK (PART) $6,000.00
Total: $21,000.00