PREPARING ROW
|
STA
|
21.580
|
$12,000.000
|
$5,000.000
|
$35,000.000
|
$16,000.000
|
$41,765.140
|
$50,000.000
|
$15,000.000
|
|
|
REMOV CONC (PAV)
|
SY
|
4,456.000
|
$25.000
|
$55.000
|
$20.000
|
$30.000
|
$21.190
|
$13.000
|
$20.000
|
|
|
REMOV CONC (MEDIANS)
|
SY
|
105.000
|
$55.000
|
$25.000
|
$20.000
|
$30.000
|
$33.910
|
$20.000
|
$55.000
|
|
|
REMOV CONC (PAVERS)
|
SY
|
212.000
|
$35.000
|
$25.000
|
$20.000
|
$35.000
|
$10.340
|
$19.000
|
$65.000
|
|
|
REMOV CONC (CURB)
|
LF
|
1,554.000
|
$20.000
|
$10.000
|
$20.000
|
$18.000
|
$12.290
|
$8.000
|
$15.000
|
|
|
REMOV CONC (APPR SLAB)
|
SY
|
360.000
|
$185.000
|
$55.000
|
$100.000
|
$20.000
|
$317.880
|
$32.000
|
$35.000
|
|
|
REMOV CONC (RAIL W/ METAL ELEMENT)
|
LF
|
48.000
|
$30.000
|
$100.000
|
$50.000
|
$50.000
|
$42.380
|
$52.000
|
$55.000
|
|
|
RMV (10"-14") TRT/UNTRT BASE & ASPH PAV
|
SY
|
1,134.000
|
$50.000
|
$15.000
|
$20.000
|
$17.000
|
$13.940
|
$17.300
|
$25.000
|
|
|
EXCAV (ROADWAY)
|
CY
|
74.000
|
$35.000
|
$50.000
|
$20.000
|
$88.000
|
$20.170
|
$1,000.000
|
$190.000
|
|
|
EMBANK (FNL)(DC)(TY C)
|
CY
|
1,960.000
|
$40.000
|
$35.000
|
$40.000
|
$85.000
|
$23.160
|
$40.000
|
$95.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
9,155.000
|
$5.000
|
$3.000
|
$6.000
|
$2.000
|
$2.870
|
$1.000
|
$8.000
|
|
|
BLOCK SODDING
|
SY
|
9,155.000
|
$11.000
|
$5.000
|
$6.000
|
$9.000
|
$6.870
|
$8.200
|
$7.000
|
|
|
DRILL SEED (TEMP_WARM_COOL)
|
SY
|
6,438.000
|
$0.500
|
$0.450
|
$0.500
|
$0.500
|
$0.250
|
$0.420
|
$1.000
|
|
|
VEGETATIVE WATERING
|
TGL
|
2,320.000
|
$36.000
|
$10.000
|
$20.000
|
$1.000
|
$31.010
|
$20.000
|
$60.000
|
|
|
FL BS (CMP IN PLC)(TY D GR 1-2) (8")
|
SY
|
1,084.000
|
$25.000
|
$35.000
|
$25.000
|
$25.000
|
$25.430
|
$26.000
|
$55.000
|
|
|
LIME (COM OR QK)(SLURRY)
|
TON
|
103.000
|
$400.000
|
$450.000
|
$400.000
|
$440.000
|
$297.590
|
$315.000
|
$375.000
|
|
|
LIME TRT (EXIST MATL)(6")
|
SY
|
1,084.000
|
$15.000
|
$11.000
|
$12.000
|
$20.000
|
$9.920
|
$11.000
|
$18.000
|
|
|
LIME TRT (EXIST MATL)(8")
|
SY
|
4,920.000
|
$15.000
|
$11.000
|
$12.000
|
$11.000
|
$5.510
|
$7.000
|
$15.000
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
217.000
|
$10.000
|
$50.000
|
$10.000
|
$12.000
|
$6.190
|
$13.000
|
$25.000
|
|
|
SP MIXES SP-B PG64-22
|
TON
|
224.000
|
$170.000
|
$300.000
|
$200.000
|
$190.000
|
$114.440
|
$233.000
|
$195.000
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
112.000
|
$200.000
|
$320.000
|
$250.000
|
$225.000
|
$116.130
|
$180.000
|
$205.000
|
|
|
TACK COAT
|
GAL
|
65.000
|
$5.000
|
$5.000
|
$10.000
|
$28.000
|
$3.800
|
$20.000
|
$2.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
225.000
|
$8.000
|
$25.000
|
$20.000
|
$17.000
|
$6.500
|
$4.500
|
$20.000
|
|
|
PLANE ASPH CONC PAV(4")
|
SY
|
2,362.000
|
$14.000
|
$17.000
|
$20.000
|
$6.000
|
$6.500
|
$10.000
|
$15.000
|
|
|
CONC PVMT (CRCP) (9")
|
SY
|
4,247.000
|
$140.000
|
$117.000
|
$100.000
|
$176.000
|
$155.370
|
$94.000
|
$135.000
|
|
|
STRUCT EXCAV
|
CY
|
4,472.000
|
$35.000
|
$25.000
|
$50.000
|
$20.000
|
$29.670
|
$32.000
|
$35.000
|
|
|
CEM STABIL BKFL
|
CY
|
1,333.000
|
$240.000
|
$350.000
|
$250.000
|
$240.000
|
$139.510
|
$132.000
|
$210.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
161.000
|
$11.000
|
$10.000
|
$10.000
|
$20.000
|
$13.560
|
$0.010
|
$15.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
11,273.000
|
$35.000
|
$65.000
|
$55.000
|
$45.000
|
$180.840
|
$122.000
|
$45.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
128.000
|
$145.000
|
$200.000
|
$200.000
|
$200.000
|
$160.200
|
$120.000
|
$195.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
1,188.000
|
$145.000
|
$299.000
|
$250.000
|
$340.000
|
$131.990
|
$143.000
|
$200.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
256.000
|
$230.000
|
$416.000
|
$350.000
|
$375.000
|
$214.240
|
$213.000
|
$295.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
100.700
|
$1,700.000
|
$1,500.000
|
$2,000.000
|
$2,500.000
|
$1,706.350
|
$1,050.000
|
$3,000.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
38.200
|
$1,500.000
|
$1,700.000
|
$2,000.000
|
$3,000.000
|
$1,903.430
|
$2,100.000
|
$6,000.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
4,500.000
|
$30.000
|
$29.000
|
$20.000
|
$45.000
|
$63.460
|
$34.000
|
$35.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
212.000
|
$810.000
|
$850.000
|
$2,000.000
|
$1,200.000
|
$738.450
|
$657.000
|
$1,235.000
|
|
|
BRIDGE MEDIAN (HPC)
|
SF
|
360.000
|
$20.000
|
$180.000
|
$20.000
|
$35.000
|
$11.020
|
$20.000
|
$25.000
|
|
|
BRIDGE SIDEWALK(HPC)
|
SF
|
1,020.000
|
$20.000
|
$85.000
|
$20.000
|
$35.000
|
$50.200
|
$16.500
|
$25.000
|
|
|
SLAB SPAN (HPC)
|
CY
|
236.000
|
$1,600.000
|
$1,900.000
|
$2,000.000
|
$3,000.000
|
$1,491.790
|
$2,300.000
|
$7,000.000
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
622.500
|
$200.000
|
$353.000
|
$225.000
|
$340.000
|
$319.430
|
$275.000
|
$390.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
89.000
|
$750.000
|
$550.000
|
$550.000
|
$900.000
|
$448.960
|
$706.000
|
$1,142.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
970.000
|
$185.000
|
$180.000
|
$150.000
|
$185.000
|
$145.540
|
$183.000
|
$168.160
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
138.000
|
$250.000
|
$250.000
|
$250.000
|
$200.000
|
$209.100
|
$194.000
|
$187.000
|
|
|
STR STEEL (MISC NON-BRIDGE)
|
LB
|
420.000
|
$25.000
|
$55.000
|
$20.000
|
$45.000
|
$16.950
|
$20.000
|
$37.000
|
|
|
RAIL (TY T223)(HPC)
|
LF
|
322.000
|
$170.000
|
$150.000
|
$250.000
|
$195.000
|
$181.770
|
$146.000
|
$365.000
|
|
|
RAIL (TY C223)(HPC)
|
LF
|
144.000
|
$200.000
|
$230.000
|
$250.000
|
$225.000
|
$181.770
|
$216.000
|
$500.000
|
|
|
TYPE A JOINT
|
LF
|
150.000
|
$47.500
|
$180.000
|
$100.000
|
$40.000
|
$211.920
|
$67.000
|
$300.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
72.000
|
$260.000
|
$180.000
|
$100.000
|
$350.000
|
$280.570
|
$223.000
|
$395.000
|
|
|
CONC BOX CULV (9 FT X 7 FT)
|
LF
|
322.000
|
$1,500.000
|
$900.000
|
$1,500.000
|
$1,650.000
|
$787.720
|
$1,120.000
|
$3,500.000
|
|
|
RC PIPE (CL III)(15 IN)
|
LF
|
52.000
|
$120.000
|
$80.000
|
$85.000
|
$485.000
|
$55.540
|
$150.000
|
$275.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
20.000
|
$120.000
|
$95.000
|
$95.000
|
$900.000
|
$58.390
|
$200.000
|
$305.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
5.000
|
$140.000
|
$100.000
|
$105.000
|
$725.000
|
$84.020
|
$500.000
|
$762.000
|
|
|
INLET (COMPL)(PCO)(5FT)(NONE)
|
EA
|
6.000
|
$6,460.000
|
$9,500.000
|
$12,500.000
|
$8,600.000
|
$7,704.500
|
$6,000.000
|
$9,100.000
|
|
|
WINGWALL (FW - 0) (HW=16 FT)
|
EA
|
1.000
|
$100,000.000
|
$71,000.000
|
$100,000.000
|
$50,000.000
|
$72,992.020
|
$50,000.000
|
$93,500.000
|
|
|
WINGWALL (PW - 1) (HW=11 FT)
|
EA
|
1.000
|
$100,000.000
|
$75,000.000
|
$85,000.000
|
$45,000.000
|
$67,815.290
|
$50,000.000
|
$65,000.000
|
|
|
ADJUSTING MANHOLES
|
EA
|
2.000
|
$3,000.000
|
$1,000.000
|
$2,000.000
|
$2,000.000
|
$2,398.120
|
$1,700.000
|
$6,100.000
|
|
|
ADJUSTING INLETS
|
EA
|
1.000
|
$1,500.000
|
$5,000.000
|
$2,500.000
|
$5,200.000
|
$1,695.380
|
$1,500.000
|
$4,500.000
|
|
|
ADJUSTING MANHOLES (WATER VALVE BOX)
|
EA
|
1.000
|
$1,500.000
|
$500.000
|
$1,000.000
|
$1,250.000
|
$847.690
|
$3,500.000
|
$3,800.000
|
|
|
REMOV STR (INLET)
|
EA
|
6.000
|
$1,300.000
|
$1,000.000
|
$3,000.000
|
$2,900.000
|
$1,059.610
|
$1,000.000
|
$3,800.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
2.000
|
$2,500.000
|
$1,000.000
|
$3,000.000
|
$5,000.000
|
$2,119.230
|
$4,230.000
|
$6,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
48.000
|
$40.000
|
$50.000
|
$50.000
|
$30.000
|
$26.620
|
$31.000
|
$150.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
507.000
|
$100.000
|
$100.000
|
$100.000
|
$200.000
|
$89.010
|
$322.000
|
$150.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
1.000
|
$70,000.000
|
$100,000.000
|
$65,000.000
|
$200,000.000
|
$33,907.650
|
$350,000.000
|
$115,000.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$90,000.000
|
$150,000.000
|
$200,000.000
|
$125,000.000
|
$79,732.140
|
$420,000.000
|
$8,100.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$636,561.400
|
$600,000.000
|
$800,000.000
|
$896,000.000
|
$905,843.620
|
$1,000,000.000
|
$1,100,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
30.000
|
$20,000.000
|
$10,000.000
|
$8,500.000
|
$10,000.000
|
$9,889.730
|
$45,250.000
|
$8,426.740
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$18,000.000
|
$15,000.000
|
$20,000.000
|
$32,500.000
|
$8,148.120
|
$25,000.000
|
$61,572.520
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
6.000
|
$400.000
|
$1,000.000
|
$550.000
|
$250.000
|
$211.920
|
$677.000
|
$173.480
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
81.000
|
$48.000
|
$55.000
|
$30.000
|
$30.000
|
$33.910
|
$43.000
|
$72.450
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
97.000
|
$95.000
|
$180.000
|
$50.000
|
$80.000
|
$78.590
|
$104.000
|
$141.040
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
178.000
|
$25.000
|
$20.000
|
$20.000
|
$14.000
|
$14.440
|
$24.000
|
$54.980
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
936.000
|
$35.000
|
$35.000
|
$50.000
|
$40.000
|
$28.820
|
$35.000
|
$70.800
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
936.000
|
$15.000
|
$10.000
|
$20.000
|
$15.000
|
$10.730
|
$10.000
|
$52.530
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,455.000
|
$6.000
|
$4.000
|
$4.000
|
$8.000
|
$3.870
|
$3.600
|
$7.270
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,455.000
|
$2.000
|
$1.000
|
$2.000
|
$4.000
|
$1.170
|
$1.250
|
$2.750
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
120.000
|
$10.000
|
$10.000
|
$18.000
|
$12.000
|
$6.400
|
$5.000
|
$17.710
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
120.000
|
$2.000
|
$2.000
|
$9.000
|
$6.000
|
$1.700
|
$1.250
|
$8.550
|
|
|
CONSTRUCTING DETOURS
|
SY
|
1,789.000
|
$150.000
|
$110.000
|
$50.000
|
$135.000
|
$108.650
|
$200.000
|
$182.850
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
570.000
|
$60.000
|
$100.000
|
$100.000
|
$70.000
|
$10.990
|
$28.000
|
$83.670
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
820.000
|
$60.000
|
$100.000
|
$100.000
|
$70.000
|
$42.380
|
$39.000
|
$99.350
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
100.000
|
$100.000
|
$100.000
|
$100.000
|
$70.000
|
$73.660
|
$41.000
|
$92.020
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
570.000
|
$13.000
|
$25.000
|
$20.000
|
$20.000
|
$13.990
|
$11.000
|
$21.100
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
1,260.000
|
$15.000
|
$25.000
|
$20.000
|
$20.000
|
$12.720
|
$11.000
|
$33.240
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
120.000
|
$25.000
|
$25.000
|
$20.000
|
$20.000
|
$12.450
|
$11.500
|
$33.250
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
570.000
|
$15.000
|
$25.000
|
$20.000
|
$30.000
|
$17.830
|
$11.700
|
$20.770
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
820.000
|
$20.000
|
$25.000
|
$20.000
|
$30.000
|
$16.950
|
$14.000
|
$21.740
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
100.000
|
$30.000
|
$25.000
|
$20.000
|
$30.000
|
$17.230
|
$16.000
|
$21.750
|
|
|
PORT CTB(FUR & INSTL)(F-SHAPE)(TY T)
|
LF
|
60.000
|
$100.000
|
$150.000
|
$100.000
|
$100.000
|
$50.010
|
$111.000
|
$143.530
|
|
|
PORT CTB(MOVE)(F-SHAPE)(TY T)
|
LF
|
60.000
|
$50.000
|
$30.000
|
$20.000
|
$50.000
|
$11.870
|
$16.000
|
$21.070
|
|
|
PORT CTB(REMOVE)(F-SHAPE)(TY T)
|
LF
|
60.000
|
$50.000
|
$50.000
|
$20.000
|
$100.000
|
$11.870
|
$18.000
|
$20.740
|
|
|
CONC CURB (MONO) (TY II)
|
LF
|
1,019.000
|
$75.000
|
$25.000
|
$20.000
|
$22.000
|
$16.950
|
$14.000
|
$8.200
|
|
|
CONC CURB (DOWELED)
|
LF
|
2,605.000
|
$70.000
|
$35.000
|
$45.000
|
$37.000
|
$56.290
|
$25.000
|
$13.550
|
|
|
CONC CURB (SPECIAL)
|
LF
|
938.000
|
$55.000
|
$65.000
|
$100.000
|
$43.000
|
$127.150
|
$27.000
|
$15.300
|
|
|
DRIVEWAYS (CONC)
|
SY
|
209.000
|
$165.000
|
$120.000
|
$120.000
|
$145.000
|
$101.720
|
$107.000
|
$487.990
|
|
|
CONC SIDEWALKS (4")
|
SY
|
276.000
|
$150.000
|
$85.000
|
$65.000
|
$115.000
|
$76.290
|
$75.000
|
$120.370
|
|
|
CONC MEDIAN
|
SY
|
615.000
|
$150.000
|
$180.000
|
$150.000
|
$155.000
|
$67.160
|
$76.000
|
$118.100
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,175.000
|
$30.000
|
$30.000
|
$30.000
|
$30.000
|
$24.320
|
$24.000
|
$32.370
|
|
|
MTL BEAM GD FEN TRANS (TL2)
|
EA
|
6.000
|
$1,800.000
|
$2,800.000
|
$1,850.000
|
$1,200.000
|
$1,271.540
|
$1,300.000
|
$1,954.680
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,400.000
|
$2,850.000
|
$1,850.000
|
$1,500.000
|
$1,271.540
|
$1,400.000
|
$2,260.100
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
62.000
|
$5.000
|
$10.000
|
$3.000
|
$10.000
|
$2.730
|
$2.500
|
$12.220
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$3,300.000
|
$3,850.000
|
$3,850.000
|
$3,500.000
|
$2,824.120
|
$3,100.000
|
$806.310
|
|
|
RELOCATE EXISTING MAILBOX
|
EA
|
1.000
|
$350.000
|
$350.000
|
$1,100.000
|
$800.000
|
$303.050
|
$325.000
|
$610.840
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
8.000
|
$850.000
|
$1,100.000
|
$1,100.000
|
$1,000.000
|
$611.410
|
$725.000
|
$806.310
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
19.000
|
$50.000
|
$35.000
|
$100.000
|
$30.000
|
$31.920
|
$25.000
|
$34.210
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB (BI)
|
EA
|
8.000
|
$25.000
|
$55.000
|
$100.000
|
$30.000
|
$22.760
|
$23.000
|
$14.660
|
|
|
WK ZN PAV MRK REMOV (W)6"(BRK)
|
LF
|
523.000
|
$1.500
|
$4.000
|
$3.000
|
$2.000
|
$1.530
|
$3.000
|
$3.670
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
9,243.000
|
$2.000
|
$1.150
|
$3.000
|
$2.000
|
$1.170
|
$1.150
|
$1.500
|
|
|
WK ZN PAV MRK REMOV (W)8"(SLD)
|
LF
|
178.000
|
$2.800
|
$3.000
|
$6.000
|
$3.000
|
$2.250
|
$3.000
|
$3.000
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
16,177.000
|
$2.000
|
$1.150
|
$3.000
|
$2.000
|
$1.320
|
$1.150
|
$1.400
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
400.000
|
$2.200
|
$1.350
|
$6.000
|
$2.000
|
$1.100
|
$1.350
|
$1.650
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
43.000
|
$10.000
|
$15.000
|
$20.000
|
$11.000
|
$7.630
|
$15.000
|
$18.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
4.000
|
$200.000
|
$1,000.000
|
$250.000
|
$375.000
|
$169.540
|
$200.000
|
$245.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
4.000
|
$240.000
|
$1,000.000
|
$250.000
|
$500.000
|
$197.940
|
$325.000
|
$400.000
|
|
|
PAVEMENT SLER 6"
|
LF
|
4,544.000
|
$0.700
|
$0.450
|
$3.000
|
$0.500
|
$0.390
|
$0.450
|
$0.550
|
|
|
PAVEMENT SLER 8"
|
LF
|
400.000
|
$1.000
|
$1.000
|
$6.000
|
$0.500
|
$0.530
|
$1.000
|
$1.250
|
|
|
PAVEMENT SLER 24"
|
LF
|
43.000
|
$3.500
|
$3.000
|
$20.000
|
$3.000
|
$2.100
|
$3.000
|
$3.500
|
|
|
PAVEMENT SLER (ARROW)
|
EA
|
4.000
|
$55.000
|
$75.000
|
$250.000
|
$45.000
|
$33.910
|
$75.000
|
$92.000
|
|
|
PAVEMENT SLER (WORD)
|
EA
|
4.000
|
$65.000
|
$95.000
|
$250.000
|
$55.000
|
$38.150
|
$95.000
|
$115.000
|
|
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
|
LF
|
2,894.000
|
$1.000
|
$2.000
|
$3.000
|
$2.000
|
$0.720
|
$2.000
|
$2.000
|
|
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
|
LF
|
878.000
|
$1.000
|
$1.750
|
$3.000
|
$1.500
|
$0.680
|
$1.750
|
$2.000
|
|
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
|
LF
|
2,428.000
|
$1.000
|
$175.000
|
$3.000
|
$1.500
|
$0.660
|
$1.750
|
$2.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
10.000
|
$10.000
|
$6.000
|
$6.000
|
$15.000
|
$4.660
|
$6.000
|
$7.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
188.000
|
$10.000
|
$6.000
|
$6.000
|
$15.000
|
$4.660
|
$6.000
|
$7.000
|
|
|
ELIM EXT PM & MRKS (4")
|
LF
|
1,337.000
|
$1.300
|
$3.000
|
$1.000
|
$2.000
|
$0.640
|
$3.000
|
$3.000
|
|
|
ELIM EXT PM & MRKS (8")
|
LF
|
200.000
|
$2.700
|
$6.000
|
$6.000
|
$2.000
|
$0.850
|
$6.000
|
$7.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
4,544.000
|
$0.500
|
$0.400
|
$1.000
|
$0.250
|
$0.170
|
$0.400
|
$0.500
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
400.000
|
$1.000
|
$0.750
|
$1.000
|
$0.500
|
$0.250
|
$0.750
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
43.000
|
$2.000
|
$2.500
|
$10.000
|
$4.000
|
$0.870
|
$2.500
|
$3.000
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
4.000
|
$50.000
|
$675.000
|
$150.000
|
$40.000
|
$17.800
|
$65.000
|
$80.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
4.000
|
$65.000
|
$150.000
|
$150.000
|
$40.000
|
$22.890
|
$75.000
|
$90.000
|
|
|
POST AND CABLE FENCE (REMOVAL)
|
LF
|
1,152.000
|
$4.000
|
$15.000
|
$10.000
|
$8.000
|
$5.090
|
$2.600
|
$10.000
|
|
Totals: |
$7,689,300.700
|
$8,168,666.000
|
$8,484,378.500
|
$8,962,082.000
|
$9,104,006.997
|
$10,351,512.120
|
$10,850,853.950
|