PREPARING ROW
|
AC
|
2.430
|
$13,500.000
|
$40,000.000
|
$35,119.340
|
$75,000.000
|
$46,000.000
|
|
|
REMOVING CONC (FLUME)
|
SY
|
170.000
|
$25.000
|
$5.000
|
$33.000
|
$20.000
|
$45.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
3,597.000
|
$21.000
|
$20.000
|
$28.000
|
$25.000
|
$19.500
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
3,306.000
|
$29.000
|
$20.000
|
$25.000
|
$25.000
|
$35.000
|
|
|
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
|
CY
|
417.000
|
$80.000
|
$30.000
|
$165.000
|
$150.000
|
$175.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
AC
|
3.000
|
$845.000
|
$2,000.000
|
$890.000
|
$1,000.000
|
$930.000
|
|
|
DRILL SEEDING (TEMP)(WARM OR COOL)
|
AC
|
3.000
|
$630.000
|
$2,000.000
|
$748.000
|
$800.000
|
$780.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY D)
|
SY
|
1,848.000
|
$2.650
|
$3.000
|
$1.300
|
$2.000
|
$1.500
|
|
|
FL BS(CMP IN PLC)(TY A,B OR D GR4)(12")
|
SY
|
2,698.000
|
$40.000
|
$50.000
|
$63.000
|
$40.000
|
$48.500
|
|
|
CEMENT
|
TON
|
28.000
|
$250.000
|
$250.000
|
$250.000
|
$300.000
|
$320.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
2,698.000
|
$9.250
|
$20.000
|
$18.000
|
$15.000
|
$13.150
|
|
|
PRIME COAT (MC-30)
|
GAL
|
676.000
|
$9.000
|
$15.000
|
$20.000
|
$8.500
|
$11.000
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
1,281.000
|
$7.600
|
$10.000
|
$6.000
|
$7.000
|
$8.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
1,027.000
|
$8.000
|
$20.000
|
$13.000
|
$30.000
|
$13.600
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,103.000
|
$40.000
|
$30.000
|
$75.000
|
$70.000
|
$85.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
360.000
|
$250.000
|
$150.000
|
$96.000
|
$90.000
|
$110.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
720.000
|
$450.000
|
$390.000
|
$303.000
|
$300.000
|
$360.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
91.200
|
$1,500.000
|
$1,800.000
|
$2,000.000
|
$1,500.000
|
$1,800.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
41.000
|
$1,800.000
|
$1,800.000
|
$2,400.000
|
$1,500.000
|
$2,540.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
19.800
|
$1,700.000
|
$1,800.000
|
$2,750.000
|
$1,500.000
|
$1,950.000
|
|
|
CL C CONC (RAIL FOUNDATION)(SRC)
|
CY
|
4.400
|
$850.000
|
$2,000.000
|
$3,341.000
|
$4,500.000
|
$1,600.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
12,994.000
|
$35.000
|
$40.000
|
$39.000
|
$45.000
|
$42.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
99.500
|
$800.000
|
$1,000.000
|
$1,061.000
|
$1,500.000
|
$1,100.000
|
|
|
INTEGRAL ABUT BKWL (HPC)
|
CY
|
18.800
|
$1,800.000
|
$2,250.000
|
$2,660.000
|
$1,500.000
|
$3,300.000
|
|
|
PRESTR CONC GIRDER (TX46)
|
LF
|
1,681.000
|
$260.000
|
$300.000
|
$252.000
|
$300.000
|
$325.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
147.000
|
$700.000
|
$750.000
|
$1,203.000
|
$800.000
|
$815.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
329.000
|
$175.000
|
$250.000
|
$376.000
|
$300.000
|
$250.000
|
|
|
RAIL (TY SSTR)(HPC)
|
LF
|
688.000
|
$98.000
|
$150.000
|
$212.000
|
$135.000
|
$315.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
25.000
|
$120.000
|
$250.000
|
$386.000
|
$200.000
|
$155.000
|
|
|
CMP (GAL STL 54 IN)
|
LF
|
8.000
|
$260.000
|
$1,000.000
|
$1,076.000
|
$1,200.000
|
$265.000
|
|
|
SET (TY I) (54 IN) (4: 1) (C)
|
EA
|
2.000
|
$5,600.000
|
$15,000.000
|
$39,717.000
|
$25,000.000
|
$21,500.000
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
2.000
|
$2,850.000
|
$2,500.000
|
$6,901.210
|
$2,500.000
|
$4,700.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
2.000
|
$2,000.000
|
$2,500.000
|
$1,824.000
|
$1,000.000
|
$3,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
29.000
|
$40.000
|
$10.000
|
$146.000
|
$50.000
|
$100.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$120,000.000
|
$200,000.000
|
$60,000.000
|
$350,000.000
|
$160,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$297,000.000
|
$400,000.000
|
$379,000.000
|
$445,000.000
|
$460,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$14,000.000
|
$3,000.000
|
$1,400.000
|
$20,000.000
|
$25,500.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
675.000
|
$7.000
|
$8.000
|
$3.290
|
$6.000
|
$9.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
675.000
|
$2.500
|
$2.000
|
$1.000
|
$3.000
|
$3.500
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
12.000
|
$7,000.000
|
$4,000.000
|
$6,407.090
|
$2,100.000
|
$8,900.000
|
|
|
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
|
LF
|
900.000
|
$30.000
|
$50.000
|
$20.000
|
$20.000
|
$22.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
900.000
|
$12.000
|
$10.000
|
$8.000
|
$5.000
|
$15.000
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
900.000
|
$30.000
|
$20.000
|
$14.000
|
$20.000
|
$22.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
125.000
|
$15.000
|
$50.000
|
$35.000
|
$25.000
|
$50.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
900.000
|
$38.000
|
$50.000
|
$30.000
|
$40.000
|
$36.500
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$3,000.000
|
$2,000.000
|
$2,428.000
|
$3,000.000
|
$2,900.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
400.000
|
$3.160
|
$5.000
|
$3.000
|
$5.000
|
$3.250
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
4.000
|
$320.000
|
$100.000
|
$202.000
|
$300.000
|
$320.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,600.000
|
$2,500.000
|
$3,035.000
|
$3,500.000
|
$3,600.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$2,300.000
|
$2,500.000
|
$2,529.000
|
$1,500.000
|
$2,700.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
2.000
|
$1,700.000
|
$2,500.000
|
$1,011.000
|
$1,500.000
|
$1,100.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$9,600.000
|
$10,000.000
|
$11,027.000
|
$8,500.000
|
$8,000.000
|
|
|
WIRE FENCE (TY C)
|
LF
|
1,141.000
|
$23.000
|
$20.000
|
$20.000
|
$25.000
|
$120.000
|
|
|
GATE (TY 1)
|
EA
|
2.000
|
$2,000.000
|
$15,000.000
|
$1,500.000
|
$1,750.000
|
$1,900.000
|
|
|
WIRE FENCE (WATER GAP)
|
LF
|
33.000
|
$65.000
|
$50.000
|
$40.000
|
$50.000
|
$53.000
|
|
|
CORNER OR PULL POST AM(REM/REP)(METAL)
|
EA
|
6.000
|
$2,600.000
|
$250.000
|
$750.000
|
$750.000
|
$800.000
|
|
|
T-POST (REM/REP) (METAL)
|
EA
|
2.000
|
$2,600.000
|
$100.000
|
$10.000
|
$250.000
|
$265.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
8.000
|
$30.000
|
$25.000
|
$15.000
|
$19.000
|
$20.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
19.000
|
$35.000
|
$50.000
|
$10.000
|
$10.000
|
$11.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
13.000
|
$45.000
|
$50.000
|
$45.000
|
$47.500
|
$50.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
|
EA
|
12.000
|
$150.000
|
$100.000
|
$151.000
|
$150.000
|
$160.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
2.000
|
$150.000
|
$100.000
|
$151.000
|
$150.000
|
$160.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
5,600.000
|
$0.900
|
$0.500
|
$0.250
|
$0.250
|
$0.260
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
33.000
|
$20.000
|
$20.000
|
$15.000
|
$15.000
|
$16.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
3,660.000
|
$0.900
|
$0.500
|
$0.250
|
$0.250
|
$0.260
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
184.000
|
$6.000
|
$10.000
|
$7.500
|
$7.500
|
$8.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
1,120.000
|
$1.000
|
$1.250
|
$1.000
|
$1.000
|
$1.100
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
2,702.000
|
$1.000
|
$1.250
|
$1.000
|
$1.000
|
$1.100
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
10,560.000
|
$1.000
|
$1.250
|
$1.000
|
$1.000
|
$1.100
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
66.000
|
$8.000
|
$15.000
|
$10.000
|
$10.000
|
$11.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
9,937.000
|
$1.000
|
$1.500
|
$1.250
|
$1.250
|
$1.500
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
33.000
|
$6.500
|
$15.000
|
$10.000
|
$10.000
|
$11.000
|
|
|
SP MIXES SP-D SAC-A PG70-28
|
TON
|
1,031.000
|
$230.000
|
$200.000
|
$303.000
|
$270.000
|
$210.000
|
|
|
TACK COAT
|
GAL
|
1,371.000
|
$8.000
|
$10.000
|
$15.000
|
$5.000
|
$8.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$12,000.000
|
$10,000.000
|
$10,000.000
|
$20,000.000
|
$8,500.000
|
|
|
TMA (STATIONARY)
|
DAY
|
10.000
|
$160.000
|
$500.000
|
$325.000
|
$950.000
|
$525.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
40.000
|
$180.000
|
$250.000
|
$150.000
|
$95.000
|
$95.000
|
|
Totals: |
$3,586,776.300
|
$3,892,082.000
|
$4,034,270.796
|
$4,464,646.750
|
$4,675,665.200
|