PREPARING ROW
|
STA
|
6.900
|
$2,500.000
|
$2,500.000
|
$5,000.000
|
$15,000.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
671.000
|
$20.000
|
$18.000
|
$15.000
|
$30.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
367.000
|
$22.000
|
$28.000
|
$20.000
|
$30.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
1,002.000
|
$11.000
|
$3.000
|
$5.000
|
$5.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
SY
|
1,517.000
|
$2.500
|
$1.550
|
$2.000
|
$2.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
840.000
|
$2.500
|
$2.760
|
$3.000
|
$3.000
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
1,179.000
|
$2.000
|
$2.150
|
$2.000
|
$2.000
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
1,178.000
|
$2.000
|
$2.150
|
$2.000
|
$2.000
|
|
|
VEGETATIVE WATERING
|
MG
|
35.000
|
$50.000
|
$25.000
|
$1.000
|
$100.000
|
|
|
SOIL RETENTION BLANKETS (CL 2) (TY G)
|
SY
|
2,357.000
|
$5.000
|
$2.000
|
$2.000
|
$4.000
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
673.000
|
$85.000
|
$60.000
|
$60.000
|
$60.000
|
|
|
CEMENT
|
TON
|
2.000
|
$300.000
|
$1,000.000
|
$250.000
|
$500.000
|
|
|
CEMENT TREAT (NEW BASE) (10")
|
SY
|
114.000
|
$10.000
|
$48.000
|
$175.000
|
$40.000
|
|
|
PRIME COAT (RC-250)
|
GAL
|
575.000
|
$20.000
|
$19.500
|
$10.000
|
$10.000
|
|
|
ASPH (AC-20-5TR)
|
GAL
|
1,748.000
|
$15.000
|
$21.500
|
$10.000
|
$20.000
|
|
|
AGGR(TY-B GR-5 SAC-B)
|
CY
|
18.000
|
$1,000.000
|
$1,275.000
|
$600.000
|
$750.000
|
|
|
AGGR(TY-PB GR-3 SAC-B)
|
CY
|
28.000
|
$800.000
|
$905.000
|
$1,100.000
|
$750.000
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
20.000
|
$800.000
|
$1,240.000
|
$1,100.000
|
$750.000
|
|
|
CEM STABIL BKFL
|
CY
|
71.000
|
$250.000
|
$210.000
|
$225.000
|
$350.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
72.000
|
$15.000
|
$49.980
|
$1.000
|
$10.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
455.000
|
$25.000
|
$52.000
|
$120.000
|
$10.000
|
|
|
CL C CONC (CULV)
|
CY
|
50.900
|
$1,100.000
|
$1,400.000
|
$1,200.000
|
$1,300.000
|
|
|
REINF CONC SLAB
|
SF
|
1,173.600
|
$28.000
|
$30.000
|
$25.000
|
$30.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
27.000
|
$600.000
|
$600.000
|
$600.000
|
$800.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
151.000
|
$170.000
|
$150.000
|
$150.000
|
$165.000
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
1,075.000
|
$200.000
|
$120.000
|
$150.000
|
$165.000
|
|
|
GABION MATTRESSES (GALV)(12 IN)
|
SY
|
241.000
|
$90.000
|
$180.000
|
$200.000
|
$150.000
|
|
|
GABION (1.5' X 3')(GALV)
|
CY
|
85.000
|
$300.000
|
$325.000
|
$280.000
|
$450.000
|
|
|
CONC BOX CULV (9FT X 4FT)
|
LF
|
85.000
|
$900.000
|
$1,150.000
|
$1,000.000
|
$1,400.000
|
|
|
SET (TY I)(S= 9 FT)(HW= 5 FT)(3:1) (C)
|
EA
|
2.000
|
$13,000.000
|
$12,500.000
|
$20,000.000
|
$15,000.000
|
|
|
SET (TY I)(S= 9 FT)(HW= 6 FT)(3:1) (C)
|
EA
|
6.000
|
$13,000.000
|
$13,500.000
|
$24,000.000
|
$15,000.000
|
|
|
SET (TY I)(S= 9 FT)(HW= 7 FT)(3:1) (C)
|
EA
|
2.000
|
$13,500.000
|
$15,500.000
|
$35,000.000
|
$18,000.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
2.000
|
$15,000.000
|
$12,500.000
|
$30,000.000
|
$15,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$83,000.000
|
$104,000.000
|
$95,000.000
|
$125,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$4,500.000
|
$3,200.000
|
$2,500.000
|
$2,500.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
85.000
|
$12.000
|
$11.350
|
$1.000
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
520.000
|
$5.000
|
$3.800
|
$1.000
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
520.000
|
$1.500
|
$1.700
|
$1.000
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
265.000
|
$6.000
|
$6.050
|
$8.000
|
$8.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
265.000
|
$1.500
|
$1.300
|
$1.000
|
$1.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2) (6:1)
|
LF
|
85.000
|
$60.000
|
$48.100
|
$1.000
|
$50.000
|
|
|
WIRE FENCE (TY C)
|
LF
|
155.000
|
$30.000
|
$20.000
|
$20.000
|
$25.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
2.000
|
$150.000
|
$100.000
|
$100.000
|
$500.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
4.000
|
$115.000
|
$200.000
|
$80.000
|
$200.000
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
4.000
|
$20.000
|
$100.000
|
$20.000
|
$50.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
|
EA
|
4.000
|
$125.000
|
$200.000
|
$50.000
|
$200.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
5,120.000
|
$1.000
|
$2.100
|
$1.000
|
$2.500
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
172.000
|
$2.000
|
$5.650
|
$5.000
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
1,370.000
|
$1.000
|
$2.150
|
$2.500
|
$2.500
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
810.000
|
$1.000
|
$3.250
|
$2.500
|
$3.500
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
935.000
|
$1.000
|
$3.250
|
$3.000
|
$3.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
46.000
|
$10.000
|
$12.050
|
$20.000
|
$15.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
6,305.000
|
$1.500
|
$0.550
|
$1.000
|
$1.000
|
|
|
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
|
LF
|
240.000
|
$22.000
|
$16.000
|
$20.000
|
$25.000
|
|
|
TMA (STATIONARY)
|
DAY
|
28.000
|
$250.000
|
$375.000
|
$200.000
|
$200.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
128.000
|
$70.000
|
$74.000
|
$50.000
|
$75.000
|
|
Totals: |
$1,059,302.300
|
$1,064,649.960
|
$1,210,014.000
|
$1,243,743.500
|