PREPARING ROW
|
STA
|
98.700
|
$4,200.000
|
$1,394.000
|
$1,000.000
|
$1,500.000
|
$1,890.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
2,293.000
|
$13.340
|
$7.000
|
$20.000
|
$20.000
|
$15.750
|
|
|
REMOVING STAB BASE AND ASPH PAV (3")
|
SY
|
17,412.000
|
$5.500
|
$4.000
|
$3.000
|
$3.250
|
$4.200
|
|
|
REMOVING STAB BASE AND ASPH PAV (7")
|
SY
|
3,556.000
|
$7.320
|
$5.000
|
$5.000
|
$4.350
|
$5.250
|
|
|
REMOVE STAB BASE & ASPH PAV (13"-18")
|
SY
|
9,593.000
|
$4.120
|
$9.000
|
$10.000
|
$9.800
|
$14.700
|
|
|
REMOVING STAB BASE AND ASPH PAV (2"-8")
|
SY
|
7,240.000
|
$2.800
|
$5.000
|
$5.000
|
$5.000
|
$5.250
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
4,900.000
|
$8.670
|
$16.000
|
$22.000
|
$20.000
|
$15.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
98.700
|
$300.000
|
$50.000
|
$500.000
|
$205.000
|
$150.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
32,892.000
|
$1.110
|
$2.550
|
$2.000
|
$1.000
|
$3.250
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
32,892.000
|
$0.130
|
$0.150
|
$0.150
|
$0.160
|
$1.440
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
32,892.000
|
$0.230
|
$0.130
|
$0.150
|
$0.140
|
$0.400
|
|
|
VEGETATIVE WATERING
|
MG
|
4,894.000
|
$13.500
|
$18.000
|
$1.000
|
$16.000
|
$1.000
|
|
|
FL BS (CMP IN PLC) (TY D GR 1-2) (24")
|
SY
|
9,742.000
|
$38.000
|
$50.000
|
$70.000
|
$80.000
|
$60.000
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
2,393.000
|
$3.760
|
$4.650
|
$5.000
|
$5.000
|
$4.200
|
|
|
SUPERPAVE MIXTURES SP-D SAC-B PG64-22
|
TON
|
3,617.000
|
$78.000
|
$84.000
|
$80.000
|
$98.000
|
$103.950
|
|
|
FULL-DEPTH REPAIR CRCP (5"-9")
|
SY
|
1,155.000
|
$230.000
|
$251.000
|
$250.000
|
$240.000
|
$315.000
|
|
|
CMP (GAL STL 12 IN)
|
LF
|
149.000
|
$61.000
|
$35.000
|
$50.000
|
$52.000
|
$40.000
|
|
|
CMP (GAL STL 18 IN)
|
LF
|
129.000
|
$76.480
|
$45.000
|
$65.000
|
$55.000
|
$50.000
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
116.000
|
$78.290
|
$60.000
|
$75.000
|
$60.000
|
$60.000
|
|
|
RC PIPE (CL III)(12 IN)
|
LF
|
186.000
|
$66.700
|
$45.000
|
$45.000
|
$48.000
|
$50.000
|
|
|
RC PIPE (CL III)(15 IN)
|
LF
|
85.000
|
$52.380
|
$60.000
|
$55.000
|
$54.000
|
$45.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
887.000
|
$51.970
|
$65.000
|
$60.000
|
$59.000
|
$50.000
|
|
|
RC PIPE (CL III)(21 IN)
|
LF
|
106.000
|
$125.460
|
$70.000
|
$65.000
|
$63.250
|
$60.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
54.000
|
$66.770
|
$90.000
|
$70.000
|
$74.000
|
$70.000
|
|
|
RC PIPE (CL III)(60 IN)
|
LF
|
65.000
|
$250.000
|
$400.000
|
$450.000
|
$345.000
|
$250.000
|
|
|
SET (TY II) (12 IN) (CMP) (6: 1) (P)
|
EA
|
8.000
|
$990.970
|
$800.000
|
$650.000
|
$850.000
|
$630.000
|
|
|
SET (TY II) (12 IN) (RCP) (6: 1) (P)
|
EA
|
12.000
|
$600.390
|
$800.000
|
$650.000
|
$830.000
|
$525.000
|
|
|
SET (TY II) (15 IN) (RCP) (6: 1) (C)
|
EA
|
2.000
|
$450.000
|
$825.000
|
$750.000
|
$860.000
|
$630.000
|
|
|
SET (TY II) (18 IN) (CMP) (6: 1) (P)
|
EA
|
6.000
|
$877.740
|
$850.000
|
$850.000
|
$955.000
|
$735.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
34.000
|
$851.250
|
$850.000
|
$850.000
|
$950.000
|
$735.000
|
|
|
SET (TY II) (21 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,390.000
|
$900.000
|
$950.000
|
$1,150.000
|
$1,050.000
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
8.000
|
$1,208.000
|
$1,000.000
|
$1,000.000
|
$1,220.000
|
$1,365.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,033.590
|
$1,000.000
|
$1,000.000
|
$1,300.000
|
$1,470.000
|
|
|
SET (TY II) (60 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$8,500.000
|
$21,702.000
|
$17,500.000
|
$1,220.000
|
$8,400.000
|
|
|
REMOV STR (DRIVEWAY CULVERT)
|
EA
|
36.000
|
$828.680
|
$250.000
|
$500.000
|
$230.000
|
$525.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$311,783.790
|
$225,000.000
|
$310,000.000
|
$320,000.000
|
$600,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
6.000
|
$20,000.000
|
$1,100.000
|
$16,500.000
|
$18,000.000
|
$73,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
90.000
|
$30.700
|
$24.500
|
$30.000
|
$22.000
|
$26.250
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
90.000
|
$9.590
|
$10.000
|
$10.000
|
$6.000
|
$10.500
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$22.350
|
$19.250
|
$25.000
|
$12.000
|
$21.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$8.240
|
$10.000
|
$7.000
|
$5.000
|
$7.350
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
1,000.000
|
$2.370
|
$1.650
|
$5.000
|
$2.250
|
$1.520
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
1,000.000
|
$0.770
|
$0.500
|
$0.500
|
$0.600
|
$0.160
|
|
|
INTERSECTIONS (CONC)
|
SY
|
391.000
|
$91.280
|
$90.000
|
$125.000
|
$97.000
|
$84.000
|
|
|
INTERSECTIONS (ACP)
|
SY
|
550.000
|
$39.090
|
$100.430
|
$30.000
|
$34.000
|
$48.600
|
|
|
DRIVEWAYS (ACP)
|
SY
|
6,690.000
|
$39.860
|
$30.000
|
$30.000
|
$34.500
|
$44.540
|
|
|
DRIVEWAYS (CONC) (HES)
|
SY
|
1,902.000
|
$110.030
|
$70.000
|
$100.000
|
$99.000
|
$189.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
3.000
|
$260.000
|
$400.000
|
$250.000
|
$170.000
|
$157.500
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,506.000
|
$2,675.000
|
$2,500.000
|
$2,615.000
|
$3,438.750
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
1.000
|
$424.320
|
$450.000
|
$300.000
|
$375.000
|
$341.250
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 1
|
EA
|
3.000
|
$272.000
|
$185.000
|
$300.000
|
$260.000
|
$236.250
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 1
|
EA
|
1.000
|
$230.000
|
$200.000
|
$300.000
|
$280.000
|
$257.250
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
2.000
|
$335.660
|
$450.000
|
$300.000
|
$520.000
|
$472.500
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
13.000
|
$506.170
|
$300.000
|
$300.000
|
$450.000
|
$347.490
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$614.620
|
$400.000
|
$475.000
|
$575.000
|
$326.130
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
|
EA
|
2.000
|
$15.810
|
$27.000
|
$15.000
|
$21.000
|
$18.900
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
8.000
|
$31.200
|
$29.000
|
$25.000
|
$38.000
|
$34.650
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
19,735.000
|
$0.590
|
$0.750
|
$0.400
|
$0.460
|
$0.420
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
986.000
|
$1.320
|
$1.250
|
$1.000
|
$1.300
|
$2.190
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
24.000
|
$5.980
|
$8.000
|
$7.000
|
$6.330
|
$5.780
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
19,735.000
|
$0.470
|
$0.330
|
$0.400
|
$0.460
|
$0.420
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
19,735.000
|
$0.470
|
$0.330
|
$0.400
|
$0.460
|
$0.420
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
494.000
|
$2.630
|
$3.200
|
$4.000
|
$4.600
|
$4.200
|
|
|
FULL - WIDTH MOWING
|
AC
|
21.000
|
$150.000
|
$1,000.000
|
$150.000
|
$350.000
|
$210.000
|
|
|
CAM (ASPHALT) PG(70-22)
|
TON
|
77.000
|
$123.710
|
$160.000
|
$135.000
|
$180.000
|
$525.000
|
|
|
CAM (AGGREGATE)
|
TON
|
1,097.000
|
$109.530
|
$160.000
|
$135.000
|
$180.000
|
$129.150
|
|
Totals: |
$3,141,357.400
|
$2,889,061.760
|
$3,187,710.600
|
$3,445,015.020
|
$4,292,305.740
|