PREPARING ROW
|
STA
|
25.500
|
$10,000.000
|
$5,000.000
|
$40,727.680
|
$42,000.000
|
$46,000.000
|
$5,500.000
|
|
|
EXCAV (ROADWAY)
|
CY
|
1,312.000
|
$40.000
|
$38.000
|
$47.000
|
$30.130
|
$70.000
|
$65.000
|
|
|
EMBANK (FNL)(DC)(TY C2)
|
CY
|
17,028.000
|
$60.000
|
$40.000
|
$50.000
|
$37.910
|
$45.600
|
$40.000
|
|
|
EMBANK (FNL)(DC)(TY D)
|
CY
|
1,312.000
|
$40.000
|
$55.000
|
$50.000
|
$30.130
|
$44.000
|
$65.000
|
|
|
BACKFILL (TY A)
|
STA
|
25.500
|
$220.000
|
$900.000
|
$400.000
|
$1,004.500
|
$3,723.000
|
$1,500.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
13,532.000
|
$7.000
|
$9.750
|
$2.000
|
$11.180
|
$5.000
|
$10.000
|
|
|
BROADCAST SEED (PERM_RURAL_SAND)
|
SY
|
13,532.000
|
$1.000
|
$0.340
|
$0.200
|
$1.090
|
$0.260
|
$0.300
|
|
|
STRAW/HAY MLCH SEED (TEMP_WARM)
|
SY
|
6,766.000
|
$3.000
|
$0.850
|
$0.850
|
$1.090
|
$0.500
|
$1.000
|
|
|
STRAW/HAY MLCH SEED (TEMP_COOL)
|
SY
|
6,766.000
|
$3.000
|
$0.900
|
$0.850
|
$1.090
|
$0.580
|
$1.000
|
|
|
VEGETATIVE WATERING
|
TGL
|
946.000
|
$90.000
|
$25.000
|
$21.000
|
$81.990
|
$60.600
|
$200.000
|
|
|
SOIL RET BLKT(CHAN_TEMP_4 PSF)
|
SY
|
3,040.000
|
$10.000
|
$4.250
|
$2.500
|
$7.110
|
$2.700
|
$4.000
|
|
|
FL BS (RDWY DEL)(TY A GR 1-2)(FNAL POS)
|
CY
|
2,457.000
|
$125.000
|
$110.000
|
$95.000
|
$145.100
|
$73.000
|
$76.000
|
|
|
LIME (COM OR QK)(SLURRY)
|
TON
|
171.000
|
$400.000
|
$350.000
|
$310.000
|
$343.840
|
$300.000
|
$550.000
|
|
|
LIME TRT (EXIST MATL)(8")
|
SY
|
10,262.000
|
$5.000
|
$7.750
|
$8.000
|
$15.070
|
$5.500
|
$5.000
|
|
|
SALV, HAUL & STKPL RCL APH PV (6 TO 8")
|
SY
|
8,116.000
|
$10.000
|
$9.000
|
$7.000
|
$6.030
|
$11.100
|
$15.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
6,156.000
|
$10.000
|
$7.000
|
$8.000
|
$8.750
|
$5.700
|
$10.000
|
|
|
D-GR HMA TY-B SAC-B PG64-22
|
TON
|
3,569.000
|
$155.000
|
$185.000
|
$200.000
|
$191.310
|
$141.100
|
$175.000
|
|
|
TACK COAT
|
GAL
|
4,069.000
|
$7.000
|
$4.500
|
$8.000
|
$16.400
|
$6.200
|
$10.000
|
|
|
SP MIXES SP-C SAC-A PG70-28
|
TON
|
1,160.000
|
$180.000
|
$260.000
|
$290.000
|
$202.240
|
$235.600
|
$300.000
|
|
|
CEM STABIL BKFL
|
CY
|
340.000
|
$210.000
|
$345.000
|
$250.000
|
$248.820
|
$164.400
|
$600.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
7,327.000
|
$80.000
|
$32.000
|
$35.000
|
$32.400
|
$19.200
|
$90.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
830.000
|
$350.000
|
$595.000
|
$361.000
|
$498.060
|
$414.000
|
$565.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
105.600
|
$1,700.000
|
$2,250.000
|
$1,100.000
|
$1,894.870
|
$1,249.000
|
$2,300.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
83.200
|
$1,900.000
|
$2,250.000
|
$1,300.000
|
$1,726.910
|
$4,000.000
|
$1,870.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
59.200
|
$1,800.000
|
$2,250.000
|
$1,800.000
|
$1,997.890
|
$3,000.000
|
$1,950.000
|
|
|
CL C CONC (COLLAR)
|
EA
|
2.000
|
$2,000.000
|
$2,000.000
|
$1,800.000
|
$438.810
|
$1,420.000
|
$5,000.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
16,790.000
|
$40.000
|
$37.500
|
$25.000
|
$33.150
|
$34.100
|
$45.000
|
|
|
APPROACH SLAB (HPC)
|
CY
|
141.200
|
$900.000
|
$920.000
|
$925.000
|
$778.230
|
$750.500
|
$1,550.000
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
2,172.000
|
$250.000
|
$350.000
|
$250.000
|
$303.050
|
$223.000
|
$350.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
76.000
|
$725.000
|
$950.000
|
$976.000
|
$808.040
|
$696.000
|
$800.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
2,343.000
|
$200.000
|
$160.000
|
$180.000
|
$141.170
|
$176.500
|
$300.000
|
|
|
RIPRAP (STONE PROTECTION)(30 IN)
|
CY
|
4,185.000
|
$250.000
|
$165.000
|
$241.000
|
$149.450
|
$185.000
|
$325.000
|
|
|
RAIL (TY SSTR)(HPC)
|
LF
|
826.000
|
$110.000
|
$250.000
|
$105.000
|
$174.910
|
$119.000
|
$245.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
168.000
|
$145.000
|
$200.000
|
$125.000
|
$184.430
|
$118.000
|
$210.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
57.000
|
$250.000
|
$150.000
|
$156.000
|
$143.360
|
$161.000
|
$200.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
20.000
|
$300.000
|
$200.000
|
$190.000
|
$170.810
|
$300.000
|
$200.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 24 IN)
|
EA
|
2.000
|
$5,000.000
|
$10,000.000
|
$10,000.000
|
$18,336.730
|
$6,300.000
|
$30,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$2,000.000
|
$2,500.000
|
$3,000.000
|
$1,625.780
|
$10,000.000
|
$7,000.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
2.000
|
$1,200.000
|
$2,000.000
|
$9,000.000
|
$3,173.340
|
$1,778.000
|
$8,500.000
|
|
|
REMOV STR (PIPE)
|
LF
|
51.000
|
$50.000
|
$50.000
|
$35.000
|
$92.120
|
$35.500
|
$75.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
2.000
|
$200,000.000
|
$150,000.000
|
$85,000.000
|
$60,836.470
|
$902,500.000
|
$325,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,034,781.000
|
$975,000.000
|
$1,060,000.000
|
$1,070,000.000
|
$1,190,000.000
|
$1,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
24.000
|
$28,000.000
|
$4,300.000
|
$20,000.000
|
$6,559.190
|
$49,500.000
|
$20,000.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$20,000.000
|
$29,000.000
|
$60,000.000
|
$27,329.950
|
$50,000.000
|
$30,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
212.000
|
$285.000
|
$250.000
|
$300.000
|
$437.280
|
$346.000
|
$200.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
32.000
|
$475.000
|
$100.000
|
$400.000
|
$874.560
|
$662.000
|
$900.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
330.000
|
$50.000
|
$80.000
|
$60.000
|
$54.660
|
$36.250
|
$70.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
330.000
|
$25.000
|
$20.000
|
$11.000
|
$27.330
|
$15.000
|
$20.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
450.000
|
$50.000
|
$60.000
|
$57.000
|
$54.900
|
$35.350
|
$60.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
450.000
|
$20.000
|
$20.000
|
$11.000
|
$21.960
|
$12.000
|
$20.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,946.000
|
$4.000
|
$9.000
|
$7.000
|
$5.490
|
$5.000
|
$5.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,946.000
|
$1.500
|
$2.250
|
$1.000
|
$2.200
|
$1.500
|
$2.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
2,089.000
|
$150.000
|
$75.000
|
$120.000
|
$185.840
|
$75.600
|
$160.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
24.000
|
$7,500.000
|
$5,500.000
|
$6,000.000
|
$5,465.990
|
$3,000.000
|
$4,500.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
3,600.000
|
$70.000
|
$100.000
|
$114.000
|
$110.160
|
$42.900
|
$75.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
5,940.000
|
$25.000
|
$19.000
|
$14.000
|
$29.400
|
$12.500
|
$40.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
3,600.000
|
$20.000
|
$22.000
|
$17.000
|
$32.200
|
$12.200
|
$40.000
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
153.000
|
$50.000
|
$75.000
|
$125.000
|
$54.660
|
$160.000
|
$113.000
|
|
|
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
|
LF
|
4,210.000
|
$0.500
|
$3.750
|
$3.000
|
$4.370
|
$0.820
|
$4.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,000.000
|
$30.000
|
$37.500
|
$26.000
|
$32.800
|
$24.950
|
$35.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$2,500.000
|
$3,230.000
|
$2,700.000
|
$2,789.120
|
$2,800.000
|
$2,500.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,377.000
|
$7.000
|
$2.500
|
$4.000
|
$5.470
|
$3.000
|
$15.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$3,500.000
|
$3,750.000
|
$3,200.000
|
$3,552.890
|
$2,860.000
|
$2,500.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
4.000
|
$1,500.000
|
$3,500.000
|
$480.000
|
$2,186.400
|
$300.000
|
$1,500.000
|
|
|
CRASH CUSH ATTEN (REMOVE)
|
EA
|
4.000
|
$1,500.000
|
$1,750.000
|
$1,000.000
|
$1,366.500
|
$750.000
|
$500.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
4.000
|
$15,000.000
|
$12,000.000
|
$12,500.000
|
$10,931.980
|
$7,700.000
|
$7,500.000
|
|
|
WIRE FENCE (TY C)
|
LF
|
260.000
|
$30.000
|
$50.000
|
$75.000
|
$27.330
|
$22.500
|
$60.000
|
|
|
WIRE FENCE (REMOVE)
|
LF
|
260.000
|
$8.000
|
$25.000
|
$8.000
|
$12.860
|
$6.750
|
$5.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
8.000
|
$1,000.000
|
$1,250.000
|
$700.000
|
$901.890
|
$635.000
|
$725.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
12.000
|
$250.000
|
$150.000
|
$120.000
|
$125.720
|
$100.000
|
$145.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
|
EA
|
16.000
|
$40.000
|
$25.000
|
$27.000
|
$21.860
|
$22.500
|
$17.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
30.000
|
$60.000
|
$32.000
|
$34.000
|
$27.330
|
$28.000
|
$33.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
8,896.000
|
$2.000
|
$1.560
|
$2.000
|
$3.500
|
$0.810
|
$2.000
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
88.000
|
$12.000
|
$8.560
|
$10.000
|
$16.940
|
$5.000
|
$25.000
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
888.000
|
$2.000
|
$1.560
|
$2.000
|
$3.610
|
$0.850
|
$5.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,000.000
|
$3.500
|
$1.750
|
$1.500
|
$5.470
|
$1.810
|
$5.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y
|
EA
|
1,000.000
|
$4.500
|
$1.750
|
$1.500
|
$3.280
|
$1.960
|
$5.000
|
|
|
WK ZN PAV MRK SHT TERM RMV (W)(4")
|
LF
|
5,100.000
|
$3.000
|
$1.880
|
$1.000
|
$3.280
|
$0.810
|
$5.000
|
|
|
WK ZN PAV MRK SHT TERM RMV (Y)(4")
|
LF
|
5,100.000
|
$3.500
|
$1.880
|
$1.000
|
$3.280
|
$0.850
|
$5.000
|
|
RE PM TY II (W) 6" (SLD)
|
LF
|
890.000
|
$2.000
|
$0.880
|
$3.000
|
$2.190
|
$1.550
|
$3.000
|
|
RE PM TY II (Y) 6" (SLD)
|
LF
|
110.000
|
$2.000
|
$0.880
|
$3.000
|
$2.190
|
$1.600
|
$3.000
|
|
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
|
LF
|
7,560.000
|
$1.500
|
$6.250
|
$4.000
|
$4.320
|
$2.000
|
$4.000
|
|
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
|
LF
|
1,818.000
|
$1.500
|
$6.250
|
$4.000
|
$4.210
|
$2.000
|
$4.000
|
|
RE PROFILE PM TY I(Y)6"(BRK)(090MIL)
|
LF
|
965.000
|
$1.000
|
$6.250
|
$4.000
|
$4.150
|
$2.100
|
$6.000
|
|
|
PAVEMENT SLER 6"
|
LF
|
10,343.000
|
$0.500
|
$1.000
|
$1.500
|
$2.190
|
$0.800
|
$1.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
70.000
|
$6.000
|
$37.500
|
$18.000
|
$10.930
|
$9.000
|
$10.000
|
|
|
ELIM EXT PM & MRKS (4")
|
LF
|
4,362.000
|
$0.700
|
$1.000
|
$1.500
|
$2.730
|
$0.650
|
$3.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
4,482.000
|
$0.500
|
$1.000
|
$0.700
|
$2.190
|
$0.400
|
$1.000
|
|
|
PAV SURF PREP FOR MRK (RPM)
|
EA
|
32.000
|
$6.000
|
$30.000
|
$4.000
|
$0.550
|
$2.000
|
$2.000
|
|
|
TREE TRIMMING / BRUSH REMOVAL
|
MI
|
0.500
|
$50,000.000
|
$100,000.000
|
$75,000.000
|
$8,356.940
|
$100,000.000
|
$35,000.000
|
|
|
INSTALL FTB
|
LF
|
228.000
|
$80.000
|
$60.000
|
$80.000
|
$219.610
|
$81.000
|
$60.000
|
|
|
REMOVE FTB
|
LF
|
228.000
|
$10.000
|
$20.000
|
$25.000
|
$10.980
|
$23.000
|
$25.000
|
|
Totals: |
$11,062,766.900
|
$9,849,854.950
|
$10,689,050.340
|
$10,774,542.628
|
$12,532,612.060
|
$12,807,839.600
|