EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
|
CY
|
316.000
|
$40.000
|
$39.420
|
$27.000
|
$31.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
2,705.250
|
$80.000
|
$168.150
|
$100.000
|
$82.000
|
|
|
BLADING
|
HR
|
70.000
|
$100.000
|
$91.200
|
$82.000
|
$93.000
|
|
|
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
|
CY
|
276.000
|
$80.000
|
$96.860
|
$150.000
|
$93.000
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
4,109.000
|
$70.000
|
$81.200
|
$65.000
|
$122.000
|
|
|
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
|
GAL
|
181,594.000
|
$3.500
|
$3.370
|
$2.750
|
$2.900
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
172.000
|
$80.000
|
$94.380
|
$144.000
|
$137.000
|
|
|
D-GR HMA TY-D SAC-B PG70-22
|
TON
|
85,092.000
|
$75.000
|
$80.570
|
$82.400
|
$93.500
|
|
|
TACK COAT
|
GAL
|
43,346.000
|
$2.000
|
$2.930
|
$2.950
|
$2.300
|
|
|
TOM-C (AGGREGATE) SAC-A
|
TON
|
36,887.000
|
$100.000
|
$95.740
|
$110.000
|
$97.000
|
|
|
TOM (ASPHALT) PG 70-22
|
TON
|
2,369.000
|
$150.000
|
$95.740
|
$110.000
|
$97.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
1,000.000
|
$50.000
|
$41.370
|
$43.000
|
$84.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
|
SY
|
1,050.000
|
$60.000
|
$53.470
|
$58.000
|
$91.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
|
SY
|
2,119.000
|
$40.000
|
$28.380
|
$29.000
|
$45.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
376,350.000
|
$1.750
|
$1.640
|
$1.150
|
$2.500
|
|
|
PLANE ASPH CONC PAV (10")
|
SY
|
392.000
|
$6.000
|
$17.160
|
$30.000
|
$19.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
7.800
|
$525.000
|
$700.000
|
$1,350.000
|
$715.000
|
|
|
CLEANING AND SEALING EXISTING JOINTS
|
LF
|
4,078.390
|
$25.000
|
$8.250
|
$21.000
|
$25.500
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,500,000.000
|
$1,301,781.250
|
$1,115,000.000
|
$435,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
16.000
|
$3,500.000
|
$2,775.290
|
$3,000.000
|
$9,200.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
500,218.000
|
$0.200
|
$0.110
|
$0.270
|
$0.160
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
101,121.000
|
$0.200
|
$0.110
|
$0.380
|
$0.160
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,900.000
|
$25.000
|
$22.600
|
$30.000
|
$19.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$1,800.000
|
$1,796.770
|
$2,035.000
|
$1,600.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
700.000
|
$2.000
|
$2.030
|
$15.000
|
$2.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
8.000
|
$175.000
|
$173.880
|
$250.000
|
$200.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
14.000
|
$2,500.000
|
$2,840.060
|
$3,000.000
|
$2,350.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
80.000
|
$30.000
|
$25.500
|
$25.000
|
$20.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
|
LF
|
100,352.000
|
$0.200
|
$0.150
|
$0.150
|
$0.150
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
989,610.000
|
$0.200
|
$0.150
|
$0.150
|
$0.150
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
28,030.000
|
$0.750
|
$0.280
|
$0.280
|
$0.280
|
|
|
WK ZN PAV MRK NON-REMOV (W)18"(SLD)
|
LF
|
90.000
|
$2.200
|
$2.000
|
$2.000
|
$2.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
190.000
|
$3.150
|
$3.000
|
$3.000
|
$3.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
67,811.000
|
$0.250
|
$0.150
|
$0.150
|
$0.150
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
554,057.000
|
$0.200
|
$0.150
|
$0.150
|
$0.150
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
18,282.000
|
$1.250
|
$1.780
|
$0.700
|
$1.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
|
LF
|
18,050.000
|
$0.700
|
$0.700
|
$0.700
|
$0.700
|
|
|
PAVEMENT SEALER 4"
|
LF
|
95,724.000
|
$0.250
|
$0.200
|
$0.200
|
$0.200
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
6.000
|
$45.000
|
$45.000
|
$45.000
|
$45.000
|
|
|
REF PROF PAV MRK TY I(W)4"(SLD)(090MIL)
|
LF
|
95,724.000
|
$0.650
|
$0.600
|
$0.600
|
$0.600
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
244,656.000
|
$0.600
|
$0.300
|
$0.300
|
$0.300
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
27,643.000
|
$0.550
|
$0.300
|
$0.300
|
$0.300
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
58,310.000
|
$0.550
|
$0.300
|
$0.300
|
$0.300
|
|
PREFAB PAV MRK TY C (W) (18") (SLD)
|
LF
|
90.000
|
$12.000
|
$11.000
|
$11.000
|
$11.000
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
422.000
|
$15.000
|
$13.000
|
$13.000
|
$13.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
21.000
|
$200.000
|
$225.000
|
$225.000
|
$225.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
4.000
|
$250.000
|
$275.000
|
$275.000
|
$275.000
|
|
PREFAB PAV MRK TY C (W) (RR XING)
|
EA
|
2.000
|
$600.000
|
$650.000
|
$650.000
|
$650.000
|
|
PREFAB PAV MRK TY C (W) (18")(YLD TRI)
|
EA
|
92.000
|
$35.000
|
$25.000
|
$25.000
|
$25.000
|
|
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
|
EA
|
690.000
|
$45.000
|
$45.000
|
$45.000
|
$45.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
858.000
|
$3.000
|
$3.000
|
$3.000
|
$3.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
2,405.000
|
$3.000
|
$3.000
|
$3.000
|
$3.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
3,089.000
|
$3.000
|
$3.000
|
$3.000
|
$3.000
|
|
|
ELIM EXT PV MRK & MRKS (RUMBLE STRIP)
|
LF
|
140,702.000
|
$0.500
|
$0.250
|
$0.550
|
$1.000
|
|
|
UNDERSEAL COURSE
|
GAL
|
135,635.000
|
$3.200
|
$2.900
|
$2.500
|
$2.600
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$7,500.000
|
$10,000.000
|
$7,100.000
|
|
|
HPPM W/RET REQ TY I(W)4"(BRK)(100MIL)
|
LF
|
61,556.000
|
$0.600
|
$0.360
|
$0.360
|
$0.360
|
|
|
HPPM W/RET REQ TY I(W)4"(SLD)(100MIL)
|
LF
|
214,766.000
|
$0.600
|
$0.330
|
$0.330
|
$0.330
|
|
|
HPPM W/RET REQ TY I(Y)4"(BRK)(100MIL)
|
LF
|
1,000.000
|
$0.550
|
$0.340
|
$0.340
|
$0.340
|
|
|
HPPM W/RET REQ TY I(Y)4"(SLD)(100MIL)
|
LF
|
253,824.000
|
$0.550
|
$0.340
|
$0.340
|
$0.340
|
|
|
PAVEMENT SEALER 4"
|
LF
|
2,413.000
|
$0.400
|
$0.600
|
$0.600
|
$0.600
|
|
|
TMA (STATIONARY)
|
DAY
|
40.000
|
$200.000
|
$300.000
|
$215.000
|
$260.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
105.000
|
$250.000
|
$600.000
|
$215.000
|
$560.000
|
|
Totals: |
$16,067,131.050
|
$15,790,738.505
|
$15,929,013.230
|
$16,572,739.785
|