FISHER CR 305 (0908-23-058)
Items: 49
County: FISHER
Length: 0.0000 MILES (0.3803 MILES)
Highway: CR 305
District: ABILENE
Control Number: 0908-23-058
DBE Goal: 0.0%
Project: BR 2024(403)
Guaranty: $50,000.00
Time: 255 WORKING DAYS
Engineer's Estimate: $2,507,178.28
Date: 04/08/2026 1:00 PM CDT (5 months ago) Changed
Contract Number: 4263035
Type: BRIDGE REPLACEMENT
Project ID: A00194074
Contract Type: FEDERAL
Project Description: REPLACE BRIDGE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
BRYCE TURENTINE
CAL HAYS
JOSE CABRERA
MICHAEL WITTIE
FISHER CR 305 (0908-23-058)
Project Name: N/A
Project: BR 2024(403)
Engineer's Estimate: $744,831.50
Length: 0.0000 MILES (0.0291 MILES)
Project Class: BRIDGE REPLACEMENT
Limits From: ALKALI CRK TRIB
Limits To: .
Project Description: REPLACE BRIDGE
FISHER CR 902 (0908-23-059)
Project Name: REPLACE BRIDGE CR 424 @ PLUM BRANCH
Project: BR 2024(368)
Engineer's Estimate: $677,937.00
Length: N/A (0.0233 MILES)
Project Class: BRIDGE REPLACEMENT
Limits From: AT PLUM BRANCH
Limits To: .
Project Description: REPLACE BRIDGE
TAYLOR CR 172 (0908-33-109)
Project Name: REPLACE BRIDGE CR 172 @ RED BANK CREEK
Project: BR 2024(560)
Engineer's Estimate: $1,084,409.78
Length: N/A (0.3279 MILES)
Project Class: BRIDGE REPLACEMENT
Limits From: AT RED BANK CREEK
Limits To: .
Project Description: REPLACE BRIDGE
Bidders (7)
E
Engineer's Estimate
$2,507,178.28
1
Awarded
$1,880,830.34
Over/Under Est:
-24.98%
-$626,347.94
$1,910,910.90
Over/Under Est:
-23.78%
-$596,267.38
Amt Left:
1.6%
$30,080.56
$1,915,919.44
Over/Under Est:
-23.58%
-$591,258.84
Amt Left:
1.87%
$35,089.10
Delta:
-0.26%
-$5,008.54
$2,008,199.00
Over/Under Est:
-19.9%
-$498,979.28
Amt Left:
6.77%
$127,368.66
Delta:
-4.82%
-$92,279.56
$2,228,174.72
Over/Under Est:
-11.13%
-$279,003.56
Amt Left:
18.47%
$347,344.38
Delta:
-10.95%
-$219,975.72
$2,418,192.80
Over/Under Est:
-3.55%
-$88,985.48
Amt Left:
28.57%
$537,362.46
Delta:
-8.53%
-$190,018.08
$2,507,699.50
Over/Under Est:
0.02%
$521.22
Amt Left:
33.33%
$626,869.16
Delta:
-3.70%
-$89,506.70
Bid Items & Bid Tabulations
49
Total
0 of 49
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| Total: | $6,000.00 |