REMOVING CONC (MEDIANS)
|
SY
|
41.200
|
$18.000
|
$215.000
|
$40.000
|
$40.000
|
|
|
REMOVING CONC (CURB)
|
LF
|
103.000
|
$6.000
|
$35.000
|
$10.000
|
$25.000
|
|
|
REMOVING STAB BASE & ASPH PAV (12")
|
SY
|
1,121.000
|
$20.000
|
$41.000
|
$40.000
|
$25.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
999.900
|
$25.000
|
$55.000
|
$34.000
|
$35.000
|
|
|
FURNISHING AND PLACING TOPSOIL
|
CY
|
1,682.000
|
$6.000
|
$89.000
|
$50.000
|
$40.000
|
|
|
BLOCK SODDING
|
SY
|
1,121.000
|
$5.000
|
$11.000
|
$3.500
|
$6.000
|
|
|
FERTILIZER
|
AC
|
0.230
|
$580.000
|
$4,765.000
|
$850.000
|
$2,000.000
|
|
|
VEGETATIVE WATERING
|
MG
|
27.790
|
$10.000
|
$450.000
|
$35.000
|
$45.000
|
|
|
ASPHALT STAB BASE (GR 2)(PG 64)
|
TON
|
1,820.000
|
$80.000
|
$175.000
|
$160.000
|
$200.000
|
|
|
SALV, HAUL & STKPL RCL APH PV (3 1/2")
|
SY
|
1,121.000
|
$6.000
|
$28.000
|
$3.000
|
$15.000
|
|
|
D-GR HMA(SQ) TY-D PG64-22
|
TON
|
910.000
|
$150.000
|
$180.000
|
$200.000
|
$220.000
|
|
|
TACK COAT
|
GAL
|
464.500
|
$4.340
|
$11.000
|
$2.000
|
$9.000
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
43.850
|
$500.000
|
$1,116.000
|
$500.000
|
$570.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$250,000.000
|
$104,000.000
|
$240,000.000
|
$280,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
9.000
|
$8,000.000
|
$9,000.000
|
$10,000.000
|
$6,500.000
|
|
|
CONC CURB (DOWEL)
|
LF
|
19,641.000
|
$24.000
|
$13.000
|
$15.000
|
$8.000
|
|
|
CONC DIRECTIONAL ISLAND (12")
|
LF
|
9,113.000
|
$38.000
|
$27.000
|
$35.000
|
$10.000
|
|
|
CONC DIRECTIONAL ISLAND (24")
|
LF
|
6,176.000
|
$45.000
|
$28.500
|
$40.000
|
$12.000
|
|
|
CONDT (PVC) (SCH 80) (6") (BORE)
|
LF
|
350.000
|
$40.000
|
$61.500
|
$70.000
|
$61.170
|
|
|
GROUND BOX TY A (122311)
|
EA
|
14.000
|
$678.000
|
$900.000
|
$1,000.000
|
$889.740
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
2.000
|
$320.000
|
$635.000
|
$600.000
|
$556.090
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
12.000
|
$150.000
|
$130.000
|
$120.000
|
$111.220
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
201.000
|
$0.350
|
$0.560
|
$0.600
|
$0.560
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
12,575.000
|
$0.600
|
$0.670
|
$0.700
|
$0.670
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
162.000
|
$1.250
|
$2.250
|
$2.500
|
$2.220
|
|
|
WK ZN PAV MRK NON-REMOV (W)(ARROW)
|
EA
|
112.000
|
$60.000
|
$39.100
|
$40.000
|
$38.930
|
|
|
WK ZN PAV MRK NON-REMOV(W)(WORD)
|
EA
|
105.000
|
$65.000
|
$50.300
|
$55.000
|
$50.050
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
133.000
|
$0.350
|
$0.560
|
$0.600
|
$0.560
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
12,575.000
|
$0.950
|
$0.760
|
$0.800
|
$0.760
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
162.000
|
$6.500
|
$5.600
|
$6.000
|
$5.560
|
|
REFL PAV MRK TY II (W) 12" (SLD)
|
LF
|
982.000
|
$1.520
|
$1.120
|
$1.200
|
$1.110
|
|
REFL PAV MRK TY II (W) 18" (SLD)
|
LF
|
1,332.000
|
$2.370
|
$1.680
|
$1.900
|
$1.670
|
|
REFL PAV MRK TY II (Y) 12" (SLD)
|
LF
|
13,296.000
|
$2.470
|
$1.120
|
$1.300
|
$1.110
|
|
REFL PAV MRK TY II (Y) 24" (SLD)
|
LF
|
6,177.000
|
$2.910
|
$1.950
|
$2.000
|
$1.950
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
201.000
|
$0.650
|
$0.500
|
$0.500
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
133.000
|
$0.650
|
$0.500
|
$0.500
|
$0.500
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
112.000
|
$210.000
|
$167.560
|
$172.000
|
$166.830
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
105.000
|
$265.000
|
$223.400
|
$230.000
|
$222.430
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
641.000
|
$3.520
|
$4.470
|
$4.600
|
$4.450
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
58,435.000
|
$0.500
|
$0.250
|
$0.300
|
$0.240
|
|
|
ELIM EXT PAV MRK & MRKS (8")
|
LF
|
3,867.000
|
$0.500
|
$0.390
|
$0.400
|
$0.390
|
|
|
ELIM EXT PAV MRK & MRKS (12")
|
LF
|
144.000
|
$2.000
|
$0.840
|
$1.000
|
$0.830
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
338.000
|
$2.200
|
$1.230
|
$1.300
|
$1.220
|
|
|
ELIM EXT PAV MRK & MRKS (ARROW)
|
EA
|
64.000
|
$101.000
|
$28.000
|
$33.000
|
$27.800
|
|
|
ELIM EXT PAV MRK & MRKS (WORD)
|
EA
|
45.000
|
$109.000
|
$33.500
|
$40.000
|
$33.370
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
334.000
|
$0.130
|
$0.020
|
$0.020
|
$0.020
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
12,575.000
|
$0.120
|
$0.040
|
$0.050
|
$0.040
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
14,278.000
|
$0.440
|
$0.070
|
$0.070
|
$0.670
|
|
|
PAV SURF PREP FOR MRK (18")
|
LF
|
1,332.000
|
$0.650
|
$0.100
|
$0.100
|
$0.100
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
6,339.000
|
$1.050
|
$0.130
|
$0.150
|
$0.130
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
112.000
|
$24.000
|
$3.350
|
$4.000
|
$3.340
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
105.000
|
$25.390
|
$5.600
|
$6.000
|
$5.560
|
|
|
BACKPLATE W/REF BRDR(3 SEC)(VENT)ALUM
|
EA
|
151.000
|
$145.000
|
$140.000
|
$160.000
|
$139.020
|
|
|
BACKPLATE W/REF BRDR(4 SEC)(VENT)ALUM
|
EA
|
45.000
|
$155.000
|
$168.000
|
$190.000
|
$166.830
|
|
|
BACKPLATE W/REF BRDR(5 SEC)(VENT)ALUM
|
EA
|
3.000
|
$165.000
|
$179.000
|
$210.000
|
$177.950
|
|
|
PATTERNED ASPHALT PAV (NON-VEHICULAR)
|
SY
|
6,994.000
|
$85.000
|
$63.500
|
$55.000
|
$167.000
|
|
|
TMA (STATIONARY)
|
DAY
|
117.000
|
$177.000
|
$300.000
|
$300.000
|
$155.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
11.000
|
$204.000
|
$335.000
|
$250.000
|
$55.000
|
|
Totals: |
$2,675,945.110
|
$2,396,293.690
|
$2,495,675.390
|
$2,801,664.090
|