FORT BEND SH 99 (3510-04-070)

Items: 231

County: FORT BEND
Length: 0.0000 MILES (1.6238 MILES)
Highway: SH 99
District: HOUSTON
Control Number: 3510-04-070
DBE Goal: 0.0%
Project: STP 2B26(002)MM
Guaranty: $100,000.00
Time: 357 WORKING DAYS
Engineer's Estimate: $31,713,551.79
Date: 08/05/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263007
Type: CONSTRUCT FRONTAGE ROADS
Project ID: A00191471
Contract Type: FEDERAL
Project Description: CONSTRUCT 2-LANE NORTHBOUND FRONTAGE ROAD ON NEW LOCATION
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$31,713,551.79
$25,954,399.85
Over/Under Est: -18.16% -$5,759,151.94
Over/Under Est: -17.33% -$5,495,854.48
Amt Left: 1.01% $263,297.46
$26,274,848.30
Over/Under Est: -17.15% -$5,438,703.49
Amt Left: 1.23% $320,448.45
Delta: -0.22% -$57,150.99
Over/Under Est: -15.03% -$4,767,988.19
Amt Left: 3.82% $991,163.75
Delta: -2.55% -$670,715.30
Over/Under Est: -7.24% -$2,295,673.40
Amt Left: 13.34% $3,463,478.54
Delta: -9.18% -$2,472,314.79
Over/Under Est: -6.53% -$2,069,841.40
Amt Left: 14.21% $3,689,310.54
Delta: -0.77% -$225,832.00
Over/Under Est: -2.49% -$788,558.53
Amt Left: 19.15% $4,970,593.41
Delta: -4.32% -$1,281,282.87
Over/Under Est: -0.37% -$118,645.21
Amt Left: 21.73% $5,640,506.73
Delta: -2.17% -$669,913.32

Bid Items & Bid Tabulations

231 Total 0 of 231
FORT BEND  |  SH 99  |  HOUSTON  |  3510-04-070  |  08/05/2026 1:00 PM CDT  |  $31,713,551.79  |  STP 2B26(002)MM  |  CONSTRUCT FRONTAGE ROADS  |  357 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAMES CONSTRUCTION GROUP, LLC
HARPER BROTHERS CONSTRUCTION LLC
MC2 CIVIL, LLC
SER CONSTRUCTION PARTNERS, LLC
GRANITE CONSTRUCTION COMPANY
R CONSTRUCTION CIVIL, LLC
PULICE CONSTRUCTION, INC.
V&S CONSTRUCTION COMPANY LLC
PREPARING ROW
STA 118.180 $4,000.000 $6,097.400 $3,050.000 $750.000 $1,650.000 $14,380.000 $900.000 $19,125.000 $289.200
REMOV CONC (PAV)
SY 17,365.000 $10.000 $4.200 $8.500 $9.000 $6.400 $4.200 $9.000 $15.000 $4.500
REMOV CONC (RIPRAP)
SY 1,165.000 $20.000 $3.000 $10.000 $9.000 $6.400 $3.700 $3.150 $9.130 $3.200
REMOV CONC (SAWCUT)
LF 1,567.000 $11.000 $15.000 $6.500 $12.000 $20.000 $6.500 $9.750 $7.960 $9.100
REMOV CONC (RETAINING WALLS)
SY 39.000 $60.000 $55.000 $105.000 $70.000 $23.900 $31.000 $38.000 $21.800 $32.000
REMOV CONC (WINGWALL)
CY 7.000 $800.000 $157.680 $1,100.000 $200.000 $119.900 $260.000 $67.000 $611.000 $2,572.000
REMOV CONC (RAIL)
LF 961.000 $10.000 $9.000 $9.000 $10.000 $5.400 $9.250 $13.000 $6.270 $9.600
REMOV CONC (FLUME)
SY 443.000 $14.000 $5.000 $16.000 $5.000 $6.400 $5.000 $12.000 $10.120 $5.300
RMV (7"-13") TRT/UNTRT BASE & ASPH PAV
SY 20,822.000 $6.350 $3.680 $1.500 $4.000 $5.600 $2.250 $3.850 $3.810 $10.900
EXCAV (ROADWAY)
CY 33,714.000 $10.000 $12.360 $13.000 $15.000 $20.000 $10.000 $23.000 $4.500 $7.400
EMBANK (FNL)(DC)(TY C)
CY 46,644.000 $35.000 $15.850 $7.000 $4.500 $17.600 $25.000 $25.000 $3.240 $30.900
EMBANK (FNL)(DC)(TY E)(CSBE_RWALL IMPR)
CY 940.000 $52.000 $57.110 $70.000 $70.000 $65.100 $71.000 $100.000 $74.550 $103.900
COMPOST MANUF TOPSOIL (4")
SY 33,175.000 $2.200 $0.950 $2.000 $1.000 $0.800 $3.000 $1.000 $6.000 $1.600
BLOCK SODDING
SY 58,194.000 $3.500 $3.390 $3.390 $4.000 $4.000 $1.200 $3.500 $1.170 $4.800
STRAW OR HAY MULCH
SY 16,912.000 $0.750 $0.100 $0.100 $0.350 $0.300 $0.300 $0.100 $0.310 $0.300
BROADCAST SEED (TEMP_WARM)
SY 225.000 $0.500 $0.180 $0.180 $0.600 $0.500 $0.110 $0.190 $0.110 $0.200
BROADCAST SEED (TEMP_WARM_COOL)
SY 33,175.000 $0.330 $0.180 $0.180 $0.100 $0.100 $0.060 $0.190 $0.060 $0.200
DRILL SEED (TEMP_WARM_COOL)
SY 4,471.000 $0.750 $0.200 $0.200 $0.250 $0.200 $3.290 $0.200 $3.360 $0.200
FERTILIZER
AC 19.860 $1,400.000 $625.000 $625.000 $700.000 $581.900 $20.000 $630.000 $744.900 $960.300
VEGETATIVE WATERING
TGL 2,383.000 $50.000 $28.000 $28.000 $20.000 $31.200 $17.500 $39.000 $18.670 $23.000
LIME (COM OR QK)(SLURRY) OR QK(DRY)
TON 549.490 $350.000 $352.950 $400.000 $360.000 $354.600 $350.000 $350.000 $300.000 $360.300
LIME TRT (EXIST MATL)(6")
SY 40,762.000 $4.000 $4.510 $3.500 $5.000 $6.300 $4.500 $3.150 $3.750 $12.800
CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(6")
SY 40,762.000 $18.000 $18.670 $18.000 $19.000 $15.700 $16.000 $18.500 $20.000 $17.800
ASPHALT TRT BASE (GR 4)(PG 64)
TON 2,288.470 $112.000 $145.000 $130.000 $140.000 $122.200 $150.000 $182.000 $155.200 $181.400
CONC PVMT (CRCP) (10")
SY 13,247.000 $82.000 $83.850 $85.000 $88.000 $83.600 $92.000 $93.000 $94.000 $71.900
CONC PVMT (CRCP) (12")
SY 24,296.000 $102.000 $92.680 $90.000 $98.000 $91.400 $96.000 $102.000 $100.000 $114.800
STRUCT EXCAV
CY 2,788.000 $30.000 $8.540 $10.000 $5.000 $19.100 $18.000 $23.000 $14.260 $20.400
STRUCT EXCAV (BOX)
CY 5,755.000 $18.000 $10.030 $9.000 $5.000 $20.000 $0.010 $24.000 $7.590 $36.700
STRUCT EXCAV (PIPE)
CY 2,581.000 $18.000 $10.030 $10.000 $5.000 $16.500 $0.010 $24.000 $7.590 $22.900
CEM STABIL BKFL
CY 4,623.000 $75.000 $58.450 $65.000 $55.000 $59.100 $58.000 $76.000 $61.500 $52.900
CEMENT STAB BACKFILL (INLET OR MH)
CY 268.000 $55.000 $57.380 $200.000 $55.000 $75.000 $58.000 $76.000 $435.950 $55.800
TRENCH EXCAVATION PROTECTION
LF 5,933.000 $6.000 $1.070 $5.000 $5.000 $0.100 $2.000 $5.500 $3.790 $5.700
TEMPORARY SPL SHORING
SF 19,291.000 $23.000 $44.400 $15.000 $1.000 $5.000 $50.000 $32.000 $11.000 $78.000
DRILL SHAFT (18 IN)
LF 160.000 $150.000 $151.040 $115.000 $200.000 $115.700 $95.000 $125.000 $94.000 $175.900
DRILL SHAFT (30 IN)
LF 6,873.000 $250.000 $197.760 $175.000 $210.000 $217.200 $200.000 $200.000 $195.000 $223.600
DRILL SHAFT (36 IN)
LF 286.000 $285.000 $289.110 $390.000 $400.000 $503.800 $370.000 $375.000 $315.000 $298.800
DRILL SHAFT (54 IN)
LF 404.000 $675.000 $458.160 $950.000 $970.000 $1,098.900 $950.000 $800.000 $925.000 $541.100
DRILL SHAFT (SIGN MTS) (42 IN)
LF 150.000 $545.000 $475.000 $462.000 $600.000 $478.000 $480.000 $500.000 $482.230 $506.900
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 104.000 $250.000 $250.000 $220.250 $280.000 $228.500 $255.000 $265.000 $253.810 $266.800
SOUND WALL
SF 106,040.000 $56.000 $32.870 $32.000 $32.000 $34.800 $35.000 $40.000 $38.000 $30.700
CL C CONC (ABUT)(EXTEND)
CY 74.600 $2,215.000 $1,405.830 $1,500.000 $2,800.000 $1,460.700 $1,400.000 $900.000 $1,500.000 $2,042.800
CL C CONC (CAP)
CY 32.600 $1,865.000 $2,316.620 $2,000.000 $2,200.000 $1,691.100 $1,550.000 $1,050.000 $2,450.000 $3,054.500
CL C CONC (COLUMN)
CY 26.200 $1,440.000 $1,191.830 $2,200.000 $1,500.000 $1,200.200 $2,100.000 $1,250.000 $2,400.000 $1,913.900
CL C CONC (RAIL FOUNDATION)
CY 125.000 $500.000 $440.970 $400.000 $150.000 $537.700 $700.000 $420.000 $750.000 $651.300
CL C CONC (SIGN COLUMN)
CY 105.500 $1,600.000 $1,562.200 $1,500.000 $2,000.000 $1,309.700 $1,450.000 $1,400.000 $1,400.000 $1,063.100
CL C CONC (SIGN FOOTING)
CY 39.200 $2,500.000 $976.650 $1,600.000 $1,500.000 $1,332.900 $950.000 $1,050.000 $1,850.000 $612.200
REINF CONC SLAB (EXTEND SLAB)
SF 9,222.000 $40.000 $38.940 $29.000 $38.000 $32.000 $50.000 $29.000 $45.000 $28.500
APPROACH SLAB
CY 52.400 $850.000 $705.330 $950.000 $900.000 $578.900 $915.240 $800.000 $1,400.000 $605.000
RETAINING WALL (MSE)
SF 17,935.000 $65.000 $36.390 $73.000 $60.000 $38.800 $56.000 $49.000 $68.000 $66.200
RETAINING WALL (CAST-IN-PLACE)
SF 714.000 $126.000 $70.340 $140.000 $130.000 $89.900 $115.000 $73.000 $72.000 $143.500
PRESTR CONC GIRDER (TX46)
LF 641.000 $225.000 $221.900 $250.000 $232.000 $282.800 $315.000 $210.000 $210.000 $395.000
PRESTR CONC GIRDER (TX54)
LF 641.000 $251.000 $224.290 $270.000 $234.000 $273.500 $316.000 $220.000 $215.000 $355.300
RIPRAP (CONC)(4 IN)
CY 508.130 $500.000 $409.160 $500.000 $500.000 $471.100 $440.000 $630.000 $489.550 $430.800
RIPRAP (CONC)(5 IN)
CY 210.000 $550.000 $400.230 $510.000 $600.000 $405.100 $440.000 $810.000 $521.480 $493.500
RIPRAP (CONC)(CL B)
CY 2.800 $800.000 $833.270 $800.000 $1,000.000 $1,260.300 $1,550.000 $895.000 $1,048.280 $787.700
RIPRAP (CONC) (CL B) (4 IN)
CY 261.800 $540.000 $472.300 $500.000 $800.000 $2,000.000 $725.000 $950.000 $638.550 $392.400
RIPRAP (CONC)(FLUME)
CY 239.000 $600.000 $648.280 $600.000 $650.000 $590.600 $600.000 $610.000 $686.440 $459.500
RIPRAP (MOW STRIP)(4 IN)
CY 302.000 $600.000 $677.310 $700.000 $600.000 $533.100 $600.000 $735.000 $675.800 $362.900
BEDDING MATERIAL (3 IN)
CY 33.000 $140.000 $104.820 $450.000 $150.000 $127.500 $90.000 $85.000 $179.790 $83.600
RAIL (TY SSTR)
LF 5,679.000 $75.000 $60.400 $86.230 $70.000 $55.300 $78.000 $113.000 $69.000 $62.400
RAIL (TY PR11)
LF 355.000 $145.000 $108.280 $120.000 $120.000 $104.800 $140.000 $195.000 $138.500 $147.800
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 59.000 $250.000 $214.830 $250.000 $300.000 $219.500 $265.000 $206.000 $275.000 $389.900
CONC BOX CULV (3 FT X 2 FT)
LF 2,636.000 $250.000 $255.260 $300.000 $280.000 $271.500 $300.000 $258.000 $285.000 $366.600
CONC BOX CULV (8 FT X 3 FT)
LF 2,155.000 $650.000 $648.400 $700.000 $690.000 $617.800 $685.000 $610.000 $680.000 $998.500
CONC BOX CULV (8 FT X 7 FT)(EXTEND)
LF 153.000 $1,250.000 $988.430 $1,400.000 $1,400.000 $922.000 $891.000 $820.000 $1,600.000 $1,360.500
CONC BOX CULV (8 FT X 8 FT)(EXTEND)
LF 25.000 $1,500.000 $1,672.050 $2,800.000 $2,200.000 $1,396.000 $1,950.000 $950.000 $1,950.000 $2,216.900
RC PIPE (CL III)(18 IN)
LF 143.000 $100.000 $64.970 $95.000 $88.000 $94.000 $86.000 $90.000 $85.000 $161.100
RC PIPE (CL III)(24 IN)
LF 1,860.000 $100.000 $79.850 $110.000 $108.000 $102.800 $97.000 $80.000 $110.000 $196.800
RC PIPE (CL III)(30 IN)
LF 98.000 $130.000 $145.270 $110.000 $148.000 $122.700 $114.000 $142.000 $145.000 $243.000
RC PIPE (CL III)(36 IN)
LF 75.000 $160.000 $154.580 $250.000 $226.000 $140.600 $148.000 $165.000 $175.000 $286.800
RC PIPE (CL III)(42 IN)
LF 122.000 $200.000 $166.050 $260.000 $254.000 $187.700 $190.000 $270.000 $250.000 $389.600
RC PIPE (CL V)(24 IN)
LF 46.000 $152.000 $115.780 $160.000 $150.000 $107.300 $124.000 $190.000 $200.000 $256.300
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 4.000 $7,000.000 $4,165.090 $7,000.000 $3,500.000 $2,768.400 $4,900.000 $4,550.000 $6,429.590 $9,725.900
JCTBOX(COMPL)(PJB)(4FTX4FT)
EA 1.000 $8,000.000 $4,496.650 $6,900.000 $4,500.000 $3,937.300 $5,200.000 $5,950.000 $8,002.730 $11,026.500
INLET (COMPL)(POD)(FG)(3FTX3FT)
EA 4.000 $5,000.000 $5,238.940 $5,000.000 $7,500.000 $3,224.400 $6,500.000 $2,700.000 $8,750.830 $9,537.900
JUNCT BOX (COMPL)(JB)(7FT X 7FT)(FTW)
EA 1.000 $17,900.000 $14,873.910 $15,000.000 $20,000.000 $9,871.800 $11,700.000 $13,700.000 $18,993.460 $26,447.800
INLET (COMPL)(CURB)(TY C1)(NONE)(HOU)
EA 18.000 $6,940.000 $5,705.080 $7,500.000 $9,000.000 $7,580.700 $6,900.000 $5,500.000 $10,677.210 $9,551.300
INLET (COMPL)(CURB)(TY C1)(LEFT)(HOU)
EA 4.000 $8,500.000 $5,811.800 $7,500.000 $8,000.000 $7,678.400 $7,000.000 $6,400.000 $10,895.700 $6,969.800
INLET (COMPL)(CURB)(TY C1)(RIGHT)(HOU)
EA 7.000 $7,040.000 $8,111.440 $9,500.000 $10,000.000 $7,951.300 $9,200.000 $6,550.000 $12,549.910 $11,731.100
INLET (COMPL)(CURB)(TY C1)(BOTH)(HOU)
EA 9.000 $9,500.000 $9,992.430 $11,000.000 $12,000.000 $9,604.100 $10,300.000 $7,750.000 $13,900.250 $12,871.400
INLET (COMPL)(TY A)(HOU)
EA 1.000 $7,000.000 $4,034.570 $5,000.000 $4,000.000 $3,732.100 $5,400.000 $3,700.000 $7,285.330 $8,729.500
INLET (COMPL)(TY AAD)(HOU)
EA 10.000 $7,000.000 $6,516.780 $10,000.000 $6,000.000 $7,542.800 $7,700.000 $5,000.000 $10,404.550 $9,494.500
INLET (COMPL)(TY AZR)(HOU)
EA 2.000 $10,000.000 $5,036.020 $9,500.000 $7,000.000 $6,868.300 $6,700.000 $5,700.000 $9,568.820 $8,625.400
MANH (COMPL)(TY A)(HOU)
EA 11.000 $5,000.000 $5,006.910 $9,000.000 $6,000.000 $4,607.400 $6,600.000 $7,300.000 $9,624.110 $14,815.000
WINGWALL (PW - 1) (HW=13 FT)
EA 1.000 $45,000.000 $107,382.520 $80,000.000 $90,000.000 $144,842.200 $98,000.000 $19,000.000 $89,150.420 $59,950.700
WINGWALL (PW - 2) (HW=16 FT)
EA 1.000 $75,000.000 $110,071.610 $110,000.000 $150,000.000 $205,476.800 $152,000.000 $154,000.000 $183,470.310 $99,471.600
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 1.000 $1,500.000 $1,192.990 $1,500.000 $1,500.000 $1,168.600 $1,620.000 $2,250.000 $2,155.800 $5,025.600
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $1,900.000 $1,551.290 $2,000.000 $1,800.000 $1,683.600 $1,950.000 $2,800.000 $2,606.210 $4,169.100
PRE-CAST TRENCH DRAIN (IN CONC PAVEMNT)
LF 120.000 $350.000 $132.030 $280.000 $300.000 $458.800 $283.000 $450.000 $495.830 $467.100
ADJUSTING INLETS
EA 1.000 $1,700.000 $1,548.990 $1,600.000 $2,000.000 $296.600 $1,900.000 $500.000 $965.860 $8,773.100
REMOV STR (INLET)
EA 9.000 $900.000 $730.780 $990.000 $1,000.000 $557.200 $870.000 $790.000 $1,697.560 $2,695.300
REMOV STR (SET)
EA 3.000 $575.000 $592.430 $850.000 $350.000 $156.000 $840.000 $2,400.000 $1,406.190 $1,991.400
REMOV STR (HEADWALL)
EA 1.000 $2,000.000 $1,300.710 $9,000.000 $14,000.000 $4,130.300 $1,850.000 $2,700.000 $2,774.360 $15,750.000
REMOV STR (PIPE)
LF 286.000 $30.000 $11.560 $15.000 $20.000 $13.600 $24.000 $37.000 $142.590 $80.500
REMOV STR (BOX CULVERT)
LF 71.000 $55.000 $63.130 $70.000 $75.000 $120.700 $55.000 $98.000 $259.070 $302.100
REMOVE STR (RAIL)
LF 580.000 $35.000 $22.470 $10.000 $10.000 $9.900 $22.000 $93.000 $23.220 $109.400
REMOV STR (RET WALL)
LF 607.000 $125.000 $62.930 $10.500 $20.000 $28.600 $15.000 $55.000 $42.570 $178.900
MOBILIZATION
LS 1.000 $2,832,504.000 $2,500,000.000 $2,155,000.000 $2,500,000.000 $2,500,000.000 $2,930,000.000 $2,800,000.000 $3,092,499.320 $3,159,200.270
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $10,000.000 $8,884.630 $5,000.000 $12,600.000 $20,178.900 $19,000.000 $8,650.000 $20,000.000 $5,678.200
PORTABLE CHANGEABLE MESSAGE SIGN
EA 6.000 $7,000.000 $5,347.760 $10,000.000 $20,000.000 $11,536.000 $12,500.000 $31,000.000 $25,608.230 $40,547.600
TMA (STATIONARY)
DAY 48.000 $250.000 $239.400 $300.000 $250.000 $312.400 $191.670 $735.000 $302.300 $1,173.800
TMA (MOBILE OPERATION)
DAY 116.000 $237.000 $587.890 $500.000 $750.000 $654.900 $1,045.000 $1,125.000 $906.920 $1,440.500
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 25.000 $45.000 $30.000 $30.000 $40.000 $39.100 $42.690 $32.000 $43.560 $64.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 100.000 $155.000 $42.000 $43.000 $110.000 $111.200 $53.790 $44.000 $54.900 $106.700
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 20.000 $85.000 $48.000 $48.000 $50.000 $51.500 $54.560 $50.000 $55.680 $117.400
ROCK FILTER DAMS (REMOVE)
LF 145.000 $16.000 $20.000 $20.000 $15.000 $14.400 $12.000 $21.000 $12.240 $21.300
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 738.000 $30.000 $30.000 $30.000 $40.000 $30.800 $27.000 $31.000 $27.550 $29.900
CONSTRUCTION EXITS (REMOVE)
SY 738.000 $10.000 $20.000 $20.000 $6.000 $9.500 $15.400 $21.000 $15.710 $10.700
SANDBAGS FOR EROSION CONTROL
EA 28.000 $15.000 $5.000 $5.000 $20.000 $20.100 $0.320 $5.000 $0.330 $53.400
TEMP SEDMT CONT FENCE (INSTALL)
LF 11,759.000 $4.500 $2.950 $2.950 $2.500 $2.300 $2.720 $3.000 $2.780 $1.900
TEMP SEDMT CONT FENCE (REMOVE)
LF 11,759.000 $1.000 $1.000 $1.000 $1.000 $0.800 $0.990 $1.000 $1.010 $0.600
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 300.000 $6.250 $8.000 $8.000 $8.000 $7.400 $5.000 $8.000 $5.100 $5.300
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,396.000 $8.000 $8.500 $8.500 $8.000 $7.100 $6.800 $9.000 $6.940 $7.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,696.000 $1.900 $2.000 $2.000 $1.000 $0.800 $1.000 $2.000 $1.020 $2.100
CONSTRUCTING DETOURS
SY 1,592.000 $110.000 $125.730 $150.000 $92.000 $99.900 $110.140 $125.000 $108.710 $143.500
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 8,329.000 $25.000 $10.980 $11.000 $13.000 $15.500 $9.130 $28.000 $16.340 $15.300
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 6,240.000 $20.000 $9.760 $12.000 $13.000 $14.000 $8.750 $26.000 $20.000 $13.900
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 180.000 $25.000 $8.540 $20.000 $13.000 $15.500 $20.920 $49.000 $25.290 $13.900
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 5,779.000 $10.000 $5.610 $8.000 $9.000 $10.200 $5.700 $9.000 $7.750 $4.600
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 5,040.000 $10.000 $3.510 $7.000 $9.000 $10.900 $4.520 $8.000 $9.950 $4.600
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 120.000 $14.500 $3.510 $8.000 $9.000 $14.200 $10.280 $11.000 $35.700 $4.600
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 8,329.000 $18.000 $10.860 $11.000 $10.000 $15.500 $8.170 $20.000 $16.340 $9.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 6,240.000 $12.000 $9.660 $11.500 $10.000 $14.000 $7.190 $6.000 $10.240 $11.800
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 180.000 $28.000 $9.660 $24.000 $10.000 $15.500 $18.410 $7.000 $10.240 $11.800
CONC CURB (MONO) (TY II)
LF 14,017.000 $10.000 $3.620 $7.000 $5.000 $3.800 $3.410 $10.000 $50.000 $23.900
CONC SIDEWALKS (5")
SY 8,231.000 $80.000 $58.480 $75.000 $63.000 $62.200 $48.840 $84.000 $60.000 $32.600
MTL W-BEAM GD FEN (TIM POST)
LF 450.000 $28.000 $25.500 $28.500 $32.000 $34.500 $25.620 $42.000 $28.500 $30.400
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 1.000 $1,750.000 $1,750.000 $2,450.000 $2,500.000 $2,369.000 $1,758.420 $3,050.000 $2,450.000 $2,614.300
REMOVE METAL BEAM GUARD FENCE
LF 1,150.000 $4.500 $3.000 $3.000 $4.000 $3.900 $3.010 $4.000 $3.000 $3.200
REMOVE TERMINAL ANCHOR SECTION
EA 2.000 $310.000 $200.000 $250.000 $250.000 $463.500 $200.960 $300.000 $250.000 $266.800
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,170.000 $3,500.000 $3,650.000 $4,000.000 $3,914.000 $3,516.840 $5,100.000 $3,650.000 $3,894.700
GUARDRAIL END TREATMENT (REMOVE)
EA 7.000 $300.000 $200.000 $200.000 $350.000 $358.400 $200.960 $450.000 $200.000 $213.400
CRASH CUSH ATTEN (MOVE & RESET)
EA 5.000 $3,000.000 $3,000.000 $4,950.000 $1,600.000 $1,512.000 $3,858.720 $1,585.000 $4,950.000 $5,281.900
CRASH CUSH ATTEN (REMOVE)
EA 5.000 $2,400.000 $1,000.000 $1,500.000 $1,000.000 $755.000 $2,756.230 $850.000 $1,500.000 $1,600.600
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 5.000 $26,500.000 $24,550.000 $25,200.000 $27,000.000 $25,836.500 $31,845.490 $28,100.000 $25,200.000 $26,889.500
CCA (INSTL)(N)(TL3)(WORK ZONE)
EA 5.000 $8,000.000 $24,550.000 $25,200.000 $27,000.000 $25,836.500 $10,214.590 $28,100.000 $2,500.000 $26,889.500
PIPE UNDERDRAINS (TY 6) (6")
LF 1,880.000 $30.000 $34.900 $33.830 $40.000 $28.600 $31.340 $44.000 $49.330 $20.400
RELOCATE RD IL ASM (TRANS-BASE)
EA 7.000 $3,465.000 $1,325.000 $2,695.000 $1,400.000 $2,796.800 $1,338.380 $1,400.000 $1,345.180 $1,413.800
REMOVE RD IL ASM (TRANS-BASE)
EA 6.000 $725.000 $475.000 $1,433.000 $500.000 $1,487.400 $479.800 $500.000 $482.230 $506.900
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 4.000 $5,400.000 $5,175.000 $5,780.000 $5,500.000 $5,999.500 $5,227.270 $5,475.000 $5,253.810 $5,521.900
IN RD IL (TY AL) 40T-8 (250W EQ) LED
EA 6.000 $12,000.000 $5,995.000 $6,192.000 $6,300.000 $6,427.900 $6,055.560 $6,300.000 $6,086.300 $6,396.900
IN RD IL (TY SA) 50T-12 (400W EQ) LED
EA 8.000 $5,400.000 $5,675.000 $6,378.000 $6,000.000 $6,620.400 $5,732.320 $6,000.000 $5,761.420 $6,055.500
CONDT (PVC) (SCH 40) (2")
LF 720.000 $15.000 $11.150 $5.950 $12.000 $6.200 $11.260 $12.000 $11.320 $11.900
CONDT (PVC) (SCH 80) (2")
LF 2,055.000 $12.000 $11.250 $6.360 $13.000 $6.600 $11.360 $12.000 $11.420 $12.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 4,360.000 $20.000 $11.750 $11.920 $14.000 $12.400 $11.870 $12.000 $11.930 $12.500
CONDT (PVC) (SCH 80) (3")
LF 50.000 $17.500 $18.850 $12.400 $21.000 $12.900 $19.040 $20.000 $19.140 $20.100
CONDT (PVC) (SCH 80) (3") (BORE)
LF 6,120.000 $28.000 $32.500 $42.550 $35.000 $44.200 $32.830 $34.000 $32.990 $34.700
CONDT (RM) (2")
LF 380.000 $30.000 $38.150 $35.580 $42.000 $36.900 $38.540 $40.000 $38.730 $40.700
ITS MULTI-DUCT CND (PVC-80)(BORE)
LF 12,180.000 $48.000 $37.500 $42.490 $40.000 $44.100 $37.880 $39.000 $38.070 $40.000
ELEC CONDR (NO.14) INSULATED
LF 6,710.000 $1.250 $1.550 $0.570 $1.700 $0.600 $1.570 $1.600 $1.570 $1.700
ELEC CONDR (NO.12) BARE
LF 230.000 $1.750 $1.500 $1.390 $1.700 $1.400 $1.520 $1.550 $1.520 $1.600
ELEC CONDR (NO.12) INSULATED
LF 460.000 $1.800 $1.600 $1.450 $1.800 $1.500 $1.620 $1.650 $1.620 $1.700
ELEC CONDR (NO.8) BARE
LF 7,855.000 $2.000 $2.200 $1.200 $2.400 $1.200 $2.220 $2.350 $2.230 $2.400
ELEC CONDR (NO.8) INSULATED
LF 15,910.000 $2.500 $2.250 $1.510 $2.500 $1.600 $2.270 $2.350 $2.280 $2.400
ELEC CONDR (NO.6) BARE
LF 8,850.000 $1.900 $2.350 $1.660 $2.600 $1.700 $2.370 $2.500 $2.390 $2.500
ELEC CONDR (NO.6) INSULATED
LF 4,425.000 $2.000 $2.650 $2.200 $2.800 $2.300 $2.680 $2.800 $2.690 $2.800
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 14.000 $4,500.000 $4,475.000 $5,160.950 $4,800.000 $5,357.700 $4,520.200 $4,700.000 $4,543.150 $4,775.000
REMOVE ITS GROUND BOX
EA 9.000 $844.250 $475.000 $906.000 $500.000 $940.100 $479.800 $480.000 $482.230 $506.900
GROUND BOX TY A (122311)W/APRON
EA 8.000 $1,400.000 $1,295.000 $946.030 $1,400.000 $982.100 $1,308.080 $1,350.000 $1,314.720 $1,381.800
GROUND BOX TY C (162911)W/APRON
EA 5.000 $1,750.000 $1,925.000 $1,104.030 $2,100.000 $1,146.100 $1,944.440 $2,000.000 $1,954.310 $2,054.100
REMOVE GROUND BOX
EA 11.000 $375.000 $255.000 $486.000 $300.000 $504.500 $257.580 $270.000 $258.880 $272.100
RELOCATE ELECTRICAL SERVICES
EA 1.000 $815.000 $2,595.000 $3,605.000 $2,750.000 $3,741.800 $2,621.210 $2,700.000 $2,634.520 $2,769.000
REMOVE ELECTRICAL SERVICES
EA 2.000 $815.000 $725.000 $1,241.000 $750.000 $1,287.900 $732.330 $740.000 $736.040 $773.600
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 1.000 $11,000.000 $8,450.000 $9,800.000 $9,000.000 $9,978.800 $8,535.350 $8,600.000 $8,578.680 $9,016.500
ELC SRV TY A 240/480 060(SS)SS(E)GC(O)
EA 2.000 $11,150.000 $9,800.000 $10,327.000 $11,000.000 $10,718.900 $9,898.990 $10,300.000 $9,949.240 $10,457.000
ELC SRV TY A 240/480 060(SS)SS(E)SP(U)
EA 2.000 $7,500.000 $7,195.000 $7,964.000 $8,000.000 $8,266.900 $7,267.680 $7,600.000 $7,304.570 $7,677.400
ALUMINUM SIGNS (TY G)
SF 30.000 $75.000 $38.400 $65.000 $35.000 $66.800 $65.550 $38.000 $50.000 $44.800
ALUMINUM SIGNS (TY O)
SF 857.250 $50.000 $35.750 $32.760 $38.000 $34.000 $33.350 $38.000 $36.290 $38.200
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 16.000 $630.000 $615.000 $615.000 $750.000 $710.700 $780.000 $940.000 $615.000 $656.200
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 18.000 $800.000 $825.000 $825.000 $1,000.000 $1,014.600 $820.000 $1,250.000 $825.000 $880.300
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $830.000 $985.000 $985.000 $1,500.000 $1,030.000 $1,000.000 $1,900.000 $985.000 $1,051.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 4.000 $875.000 $1,050.000 $1,050.000 $1,300.000 $2,575.000 $1,250.000 $1,600.000 $1,050.000 $1,120.400
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
EA 1.000 $1,800.000 $1,950.000 $1,950.000 $2,800.000 $721.000 $2,200.000 $3,500.000 $1,950.000 $2,080.700
REMOVE SM RD SN SUP&AM
EA 22.000 $110.000 $150.000 $150.000 $125.000 $154.500 $100.000 $150.000 $150.000 $160.100
INSTALL LRSS (STRUCT STEEL)
LB 325.000 $25.000 $7.500 $11.000 $8.000 $11.200 $11.000 $11.000 $7.750 $26.700
RELOCATE LRSA
EA 1.000 $3,500.000 $5,000.000 $2,400.000 $9,000.000 $2,401.500 $2,355.140 $11,500.000 $9,000.000 $6,402.300
REMOVE LRSA
EA 5.000 $1,345.000 $625.000 $2,100.000 $800.000 $2,171.700 $2,129.780 $1,000.000 $1,000.000 $6,402.300
INS OH SN SUP(35 FT CANT)(SPAN ONLY)
EA 1.000 $25,000.000 $23,385.000 $31,000.000 $24,000.000 $32,132.700 $31,511.870 $24,000.000 $23,741.120 $24,952.800
INS OH SN SUP(40 FT CANT)(SPAN ONLY)
EA 3.000 $29,000.000 $24,575.000 $29,000.000 $25,000.000 $29,374.300 $28,806.760 $25,000.000 $24,949.240 $26,222.600
REMOVE OVERHD SIGN SUP
EA 4.000 $12,000.000 $4,250.000 $6,702.790 $4,500.000 $6,958.400 $6,823.920 $4,400.000 $4,314.720 $4,534.900
REMOVE OVERHD SIGN SUP (SIGN ONLY)
EA 2.000 $2,180.000 $1,775.000 $776.780 $2,000.000 $806.400 $790.800 $1,800.000 $1,802.030 $1,894.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 35.000 $6.000 $25.000 $25.000 $25.000 $206.000 $15.000 $33.000 $25.000 $26.700
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 18.000 $30.000 $35.000 $35.000 $30.000 $206.000 $22.000 $40.000 $35.000 $37.400
INSTL DEL ASSM (D-SY)SZ 1(BRF)CTB
EA 6.000 $12.000 $25.000 $25.000 $25.000 $206.000 $15.000 $32.000 $25.000 $26.700
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 6.000 $35.000 $25.000 $35.000 $30.000 $206.000 $22.000 $42.000 $35.000 $37.400
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 9,041.000 $1.500 $1.650 $2.870 $1.750 $1.700 $1.670 $3.650 $1.680 $1.800
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 30,161.000 $1.000 $1.650 $1.280 $1.750 $1.700 $1.670 $1.600 $1.680 $1.800
WK ZN PAV MRK REMOV (W)8"(SLD)
LF 1,331.000 $1.500 $2.250 $2.300 $2.400 $2.300 $2.270 $2.800 $2.300 $2.400
WK ZN PAV MRK REMOV (W)6"(BKN W/MRKR)
LF 560.000 $1.500 $1.880 $3.450 $2.000 $1.900 $1.900 $4.200 $1.920 $2.000
WK ZN PAV MRK REMOV (W)(ARROW)
EA 8.000 $150.000 $150.000 $195.000 $160.000 $154.500 $151.520 $240.000 $153.060 $160.100
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 16,796.000 $1.300 $1.650 $1.280 $1.750 $1.700 $1.670 $1.600 $1.680 $1.800
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 76.000 $2.000 $2.000 $5.000 $2.000 $9.300 $1.000 $6.000 $24.910 $6.900
RE PM TY III (W)(6")(SLD)
LF 18,008.000 $1.000 $0.880 $1.050 $0.900 $0.900 $0.890 $1.300 $0.900 $0.900
RE PM TY III (W)(6")(BRK)
LF 4,578.000 $1.100 $0.880 $1.050 $0.900 $0.900 $0.890 $3.100 $0.900 $0.900
RE PM TY III (W)(8")(SLD)
LF 4,510.000 $2.000 $1.250 $2.500 $1.400 $1.300 $1.260 $3.100 $1.280 $1.300
RE PM TY III (W)(12")(SLD)
LF 2,656.000 $3.500 $3.150 $4.500 $3.500 $3.200 $3.180 $5.500 $3.210 $3.400
RE PM TY III (W)(12")(DOT)
LF 459.000 $3.000 $3.150 $5.000 $3.500 $3.200 $3.180 $6.100 $3.210 $3.400
RE PM TY III (W)(24")(SLD)
LF 62.000 $7.600 $8.000 $10.000 $9.000 $8.200 $8.080 $12.500 $8.160 $8.500
RE PM TY III (Y)(6")(SLD)
LF 12,568.000 $1.200 $0.880 $1.050 $0.900 $0.900 $0.890 $1.300 $0.900 $0.900
RE PM TY III (BLK)(6")(SHADOW)
LF 3,411.000 $0.900 $0.890 $1.050 $1.000 $0.900 $0.900 $1.300 $0.910 $1.000
PAVEMENT SLER (ARROW)
EA 8.000 $20.000 $50.000 $5.000 $55.000 $51.500 $50.510 $6.100 $51.020 $53.400
PAVEMENT SLER (WORD)
EA 7.000 $25.000 $50.000 $5.000 $55.000 $51.500 $50.510 $6.100 $51.020 $53.400
PAVEMENT SLER (DBL ARROW)
EA 1.000 $25.000 $50.000 $5.000 $55.000 $51.500 $50.510 $6.100 $51.020 $53.400
PAVEMENT SLER (UTURN ARROW)
EA 2.000 $30.000 $50.000 $5.000 $55.000 $51.500 $50.510 $6.100 $51.020 $53.400
PREFAB PM TY C (W)(ARROW)
EA 7.000 $250.000 $250.000 $267.420 $275.000 $257.500 $252.530 $330.000 $255.100 $266.800
PREFAB PM TY C (W)(DBL ARROW)
EA 1.000 $400.000 $300.000 $362.340 $325.000 $309.000 $303.030 $440.000 $306.120 $320.100
PREFAB PM TY C (W)(UTURN ARROW)
EA 2.000 $300.000 $275.000 $373.980 $300.000 $283.300 $277.780 $460.000 $280.610 $293.400
PREFAB PM TY C (W)(WORD)
EA 9.000 $315.000 $250.000 $318.120 $275.000 $257.500 $252.530 $390.000 $255.100 $266.800
REFL PAV MRKR TY II-C-R
EA 637.000 $6.000 $7.000 $6.000 $7.500 $7.200 $7.070 $7.500 $7.140 $7.500
ELIM EXT PM & MRKS (6")
LF 15,062.000 $2.000 $0.350 $0.490 $0.400 $0.400 $0.350 $0.600 $0.360 $0.400
ELIM EXT PM & MRKS (8")
LF 1,822.000 $2.000 $0.400 $0.980 $0.500 $0.400 $0.400 $1.250 $0.410 $0.400
ELIM EXT PM & MRKS (12")
LF 302.000 $3.250 $0.650 $2.000 $0.700 $0.700 $0.660 $2.500 $0.660 $0.700
ELIM EXT PM & MRKS (ARROW)
EA 2.000 $130.000 $25.000 $70.000 $25.000 $25.800 $25.260 $89.000 $25.510 $26.700
ELIM EXT PM & MRKS (DBL ARROW)
EA 1.000 $130.000 $29.000 $75.000 $30.000 $29.900 $29.290 $96.000 $29.590 $30.900
ELIM EXT PM & MRKS (WORD)
EA 2.000 $100.000 $25.000 $75.000 $25.000 $25.800 $25.260 $95.000 $25.510 $26.700
PAV SURF PREP FOR MRK (6")
LF 37,375.000 $1.250 $0.030 $0.020 $0.030 $0.100 $0.030 $0.030 $0.030 $0.040
PAV SURF PREP FOR MRK (8")
LF 4,510.000 $1.250 $0.050 $0.040 $0.050 $0.100 $0.050 $0.050 $0.050 $0.100
PAV SURF PREP FOR MRK (12")
LF 3,115.000 $1.250 $0.100 $0.080 $0.100 $0.100 $0.100 $0.100 $0.100 $0.100
PAV SURF PREP FOR MRK (24")
LF 62.000 $1.000 $0.350 $0.160 $0.350 $0.400 $0.350 $0.200 $0.360 $0.400
PAV SURF PREP FOR MRK (ARROW)
EA 7.000 $25.000 $15.000 $1.000 $15.000 $15.500 $15.150 $1.250 $15.310 $16.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 1.000 $17.000 $15.000 $1.000 $15.000 $15.500 $15.150 $1.250 $15.310 $16.000
PAV SURF PREP FOR MRK (UTURN ARR)
EA 2.000 $20.000 $15.000 $1.000 $15.000 $15.500 $15.150 $1.250 $15.310 $16.000
PAV SURF PREP FOR MRK (WORD)
EA 9.000 $40.000 $15.000 $1.000 $15.000 $15.500 $15.150 $1.250 $15.310 $16.000
PAV SURF PREP FOR MRK (RPM)
EA 329.000 $1.000 $1.000 $0.250 $1.000 $1.000 $1.010 $0.350 $1.020 $1.100
REMOVE LUMINAIRE POLE
EA 6.000 $1,500.000 $475.000 $1,500.000 $500.000 $1,487.400 $479.800 $500.000 $482.230 $506.900
TREE REMOVAL (4" - 12" DIA)
EA 84.000 $100.000 $300.000 $600.000 $175.000 $463.500 $325.000 $450.000 $1,461.440 $480.200
ITS POLE MNT CAB (TY 2)(CONF 2)
EA 1.000 $7,420.000 $7,475.000 $5,000.000 $8,000.000 $7,709.200 $7,550.510 $7,800.000 $7,588.830 $7,976.100
ITS POLE (40 FT)(REM)
EA 1.000 $1,990.000 $1,425.000 $4,970.000 $1,500.000 $5,150.100 $1,439.390 $1,450.000 $1,446.700 $1,520.500
FO CBL (96 SMF)
LF 12,060.000 $6.000 $6.050 $4.230 $6.500 $4.400 $6.110 $6.200 $6.140 $6.500
INSTALL WRONG WAY DRIVER DETECTION SYS
EA 1.000 $11,500.000 $52,775.000 $55,200.000 $55,000.000 $57,279.000 $53,308.080 $54,000.000 $53,578.680 $56,313.200
REMOVE WRONG WAY DRIVER DETECTION SYS
EA 1.000 $1,000.000 $2,500.000 $1,260.000 $3,000.000 $1,307.100 $2,525.250 $2,600.000 $2,538.070 $2,667.600
Totals: $31,713,551.790 $25,954,399.840 $26,217,697.310 $26,274,848.300 $26,945,563.615 $29,417,878.384 $29,643,710.390 $30,924,993.276 $31,594,906.573
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $145,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $150,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $7,000.00
Total: $302,000.00