Show Job Controls
Bid Cobra

FRANKLIN COUNTY ROAD 1018 (0901-21-022)

Items: 38

County: FRANKLIN
Length: 0.2170 MILES
Highway: COUNTY ROAD 1018
District: PARIS
Control Number: 0901-21-022
DBE Goal: 0.0%
Project: BR 2B25(155)
Guaranty: $31,000.00
Time: 203 WORKING DAYS
Engineer's Estimate: $1,535,801.14
Date: 08/06/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263236
Type: BRIDGE REPLACEMENT
Project ID: A00190819
Contract Type: FEDERAL
Project Description: BRIDGE REPLACEMENT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Documents 2 files available
Bidders (5)
E
Engineer's Estimate
$1,535,801.14
Over/Under Est: -2.82% -$43,335.44
$1,522,872.71
Over/Under Est: -0.84% -$12,928.43
Amt Left: 2.04% $30,407.01
$1,629,405.04
Over/Under Est: 6.09% $93,603.90
Amt Left: 9.18% $136,939.34
Delta: -7.00% -$106,532.33
Over/Under Est: 16.67% $256,057.76
Amt Left: 20.06% $299,393.20
Delta: -9.97% -$162,453.86
Over/Under Est: 18.81% $288,918.69
Amt Left: 22.26% $332,254.13
Delta: -1.83% -$32,860.93

Bid Items & Bid Tabulations

38 Total 0 of 38
FRANKLIN  |  COUNTY ROAD 1018  |  PARIS  |  0901-21-022  |  08/06/2026 1:00 PM CDT  |  $1,535,801.14  |  BR 2B25(155)  |  BRIDGE REPL  |  203 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HODGES AND SON CONSTRUCTION COMPANY, INC.
THK CONSTRUCTION LLC
RB CONTRACTING, LLC
HIGHWAY 19 CONSTRUCTION LLC
SCOUT 5 CONSTRUCTION LLC
PREPARING ROW
STA 11.000 $2,000.000 $3,500.000 $1,500.000 $5,380.000 $5,000.000 $1,500.000
EXCAV (ROADWAY)
CY 293.000 $15.000 $20.000 $15.000 $20.000 $15.000 $50.110
EXCAV (CHANNEL)
CY 969.000 $15.000 $10.000 $15.000 $10.000 $25.000 $58.500
EMBANK (FNL)(OC)(TY B)
CY 1,143.000 $25.000 $15.000 $18.000 $15.000 $18.000 $50.000
BROADCAST SEED (TEMP_WARM)
SY 1,404.000 $0.170 $1.500 $2.100 $2.680 $1.000 $0.195
BROADCAST SEED (TEMP_COOL)
SY 1,404.000 $0.170 $1.500 $2.100 $2.680 $1.000 $0.200
STRAW/HAY MLCH SEED(PERM_RURAL_CLAY)
SY 2,806.000 $0.300 $2.500 $2.630 $3.350 $1.000 $1.500
VEGETATIVE WATERING
TGL 19.200 $20.000 $1.000 $1.000 $10.000 $100.000 $45.000
SOIL RET BLKT(CHAN_PERM_8 PSF)
SY 1,530.000 $5.000 $3.500 $5.250 $6.700 $3.000 $0.240
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 1,512.000 $40.000 $40.000 $40.000 $40.000 $35.000 $18.900
REWORK BS MTL (TY B)(8")(ORD COMP)
SY 752.000 $20.000 $12.000 $20.000 $15.000 $10.000 $3.900
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 180.000 $250.000 $320.000 $225.000 $150.000 $180.000 $390.000
CEM STABIL BKFL
CY 150.000 $250.000 $250.000 $275.000 $275.000 $250.000 $206.750
DRILL SHAFT (24 IN)
LF 330.000 $200.000 $160.000 $135.710 $280.000 $180.000 $186.390
DRILL SHAFT (36 IN)
LF 615.000 $200.000 $210.000 $292.330 $300.000 $350.000 $346.430
CL C CONC (ABUT)
CY 93.600 $1,100.000 $1,400.000 $975.000 $975.000 $1,104.000 $457.800
CL C CONC (CAP)
CY 13.000 $900.000 $1,500.000 $1,500.000 $1,400.000 $1,600.000 $832.160
CL C CONC (COLUMN)
CY 12.000 $1,400.000 $1,400.000 $1,000.000 $1,500.000 $1.000 $690.080
REINF CONC SLAB
SF 6,240.000 $25.000 $26.000 $33.000 $30.000 $39.000 $20.690
PRESTR CONC GIRDER (TX28)
LF 455.700 $225.000 $260.000 $291.350 $340.000 $330.000 $251.610
PRESTR CONC GIRDER (TX34)
LF 338.000 $250.000 $250.000 $314.650 $350.000 $330.000 $234.940
PRESTR CONC SLAB BEAM (5SB12)
LF 197.500 $205.000 $305.000 $320.980 $365.000 $425.000 $294.420
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,122.000 $185.000 $190.000 $160.000 $185.000 $180.000 $156.320
RAIL (TY T631LS)
LF 580.000 $65.000 $50.000 $51.450 $63.000 $60.000 $50.440
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 3.000 $15,000.000 $7,500.000 $7,000.000 $5,000.000 $20,000.000 $25,000.000
MOBILIZATION
LS 1.000 $140,135.380 $130,000.000 $110,000.000 $65,000.000 $150,000.000 $75,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $1,800.000 $1,500.000 $1,518.710 $1,000.000 $2,500.000 $30,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 160.000 $40.000 $1.000 $30.000 $70.000 $55.000 $28.900
ROCK FILTER DAMS (REMOVE)
LF 160.000 $10.000 $1.000 $1.000 $15.000 $10.000 $11.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 228.000 $30.000 $1.000 $1.000 $1.000 $1.000 $32.570
CONSTRUCTION EXITS (REMOVE)
SY 228.000 $10.000 $1.000 $1.000 $1.000 $1.000 $9.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,060.000 $3.880 $1.000 $3.500 $5.000 $5.000 $1.530
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,060.000 $1.080 $1.000 $1.000 $1.000 $1.000 $1.150
MTL W-BEAM GD FEN (STEEL POST)
LF 300.000 $30.000 $28.000 $29.140 $40.000 $30.000 $29.900
GUARDRAIL END TREATMENT (INSTALL)
EA 12.000 $3,250.000 $3,200.000 $3,333.750 $4,400.000 $3,375.000 $3,120.000
REMOVE SM RD SN SUP&AM
EA 4.000 $100.000 $20.000 $250.000 $100.000 $100.000 $75.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 18.000 $20.000 $20.000 $26.250 $30.000 $45.000 $14.300
REMOVE LEAD-CONTAINING COATING (OTHER)
LS 2.000 $35,000.000 $500.000 $6,000.000 $5,000.000 $5,000.000 $6,416.800
Totals: $1,535,801.140 $1,492,465.700 $1,522,872.705 $1,629,405.040 $1,791,858.900 $1,824,719.827
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $28,027.08
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $14,013.54
Total: $42,040.62