FRIO US 57 (0276-07-035)

Items: 73

County: FRIO
Length: 0.0000 MILES (10.4878 MILES)
Highway: US 57
District: SAN ANTONIO
Control Number: 0276-07-035
DBE Goal: 0.0%
Project: F 2B26(011)
Guaranty: $100,000.00
Time: 206 WORKING DAYS
Engineer's Estimate: $8,663,166.47
Date: 08/05/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263013
Type: RESURFACE ROADWAY
Project ID: A00197422
Contract Type: FEDERAL
Project Description: SPOT BASE REPAIR, OVERLAY, AND PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
ENRIQUE MANUEL GONZALEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$8,663,166.47
$7,430,847.08
Over/Under Est: -14.22% -$1,232,319.39
Over/Under Est: -13.18% -$1,141,996.25
Amt Left: 1.22% $90,323.14
Over/Under Est: -1.51% -$130,856.33
Amt Left: 14.82% $1,101,463.06
Delta: -13.44% -$1,011,139.92
Over/Under Est: 3.77% $326,533.41
Amt Left: 20.98% $1,558,852.80
Delta: -5.36% -$457,389.74
Over/Under Est: 3.81% $329,880.42
Amt Left: 21.02% $1,562,199.81
Delta: -0.04% -$3,347.01
$9,680,424.80
Over/Under Est: 11.74% $1,017,258.33
Amt Left: 30.27% $2,249,577.72
Delta: -7.64% -$687,377.91

Bid Items & Bid Tabulations

73 Total 0 of 73
FRIO  |  US 57  |  SAN ANTONIO  |  0276-07-035  |  08/05/2026 1:00 PM CDT  |  $8,663,166.47  |  F 2B26(011)  |  RESURF ROADWAY  |  206 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CLARK CONSTRUCTION OF TEXAS, INC.
HUNTER INDUSTRIES, LTD.
ANDERSON COLUMBIA CO., INC.
LONE STAR PAVING COMPANY
TEXAS MATERIALS GROUP, INC.
CK NEWBERRY, LLC
PREPARING ROW
STA 5.000 $1,800.000 $1,500.000 $1,894.200 $2,000.000 $2,500.000 $2,900.000 $1,000.000
BACKFILL (TY A)
STA 7.680 $231.000 $150.000 $115.500 $500.000 $325.000 $520.000 $700.000
COMPOST MANUF TOPSOIL (4")
SY 3,113.000 $2.000 $2.000 $2.740 $4.000 $4.000 $3.900 $3.250
DRILL SEED (PERM_RURAL_SAND)
SY 3,113.000 $0.250 $4.000 $0.800 $0.840 $3.000 $0.800 $0.500
DRILL SEED (TEMP_WARM_COOL)
SY 3,113.000 $0.250 $4.000 $0.700 $0.740 $1.000 $0.700 $0.500
VEGETATIVE WATERING
TGL 48.600 $24.000 $50.000 $22.960 $45.000 $50.000 $65.000 $50.000
D-GR HMA TY-D PG76-22
TON 28,281.000 $121.000 $104.560 $91.360 $108.000 $117.000 $103.000 $110.000
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 4,017.000 $99.000 $129.350 $90.580 $114.000 $136.000 $119.000 $140.000
TOM-C PG76-22 SAC-B
TON 17,580.000 $121.000 $130.120 $103.180 $127.000 $146.000 $147.000 $135.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 16,951.000 $35.000 $36.360 $33.510 $38.000 $42.000 $37.500 $45.000
PLANE ASPH CONC PAV(0" TO 0.5")
SY 213,355.000 $0.300 $0.260 $0.550 $0.800 $0.750 $0.560 $1.100
PLANE ASPH CONC PAV (2.5")
SY 26,860.000 $1.400 $2.250 $1.430 $2.300 $2.850 $2.550 $2.000
PLANE ASPH CONC PAV (0" TO 2-1/2")
SY 9,054.000 $1.400 $2.500 $1.430 $2.300 $2.100 $1.700 $1.000
FLOWABLE FILL (EMBANKMENT)
CY 5.000 $500.000 $250.000 $1,100.000 $300.000 $500.000 $1,200.000 $1,000.000
RIPRAP (MOW STRIP)(4 IN)
CY 38.000 $700.000 $695.000 $650.000 $675.000 $605.000 $605.000 $700.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 4.000 $2,860.000 $2,400.000 $3,600.000 $2,200.000 $2,295.000 $2,295.000 $3,500.000
SET (TY II) (DES 2) (CMP) (6: 1) (P)
EA 4.000 $2,860.000 $2,800.000 $3,100.000 $2,700.000 $3,187.500 $3,190.000 $3,000.000
SET (TY II) (DES 3) (CMP) (6: 1) (P)
EA 4.000 $2,860.000 $3,200.000 $3,855.000 $3,400.000 $3,187.500 $3,190.000 $3,200.000
CLEAN EXIST CULVERTS
EA 25.000 $2,500.000 $500.000 $2,300.000 $4,500.000 $2,905.000 $2,905.000 $3,000.000
MOBILIZATION
LS 1.000 $401,162.690 $211,000.000 $534,678.020 $400,000.000 $605,000.000 $785,000.000 $900,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $2,000.000 $2,165.000 $3,290.520 $2,500.000 $10,100.000 $2,600.000 $5,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 412.000 $80.000 $86.000 $27.060 $40.000 $75.000 $25.000 $50.000
TMA (STATIONARY)
DAY 227.000 $208.000 $115.000 $81.190 $300.000 $150.000 $25.000 $300.000
TMA (MOBILE OPERATION)
DAY 96.000 $242.000 $115.000 $119.080 $650.000 $150.000 $50.000 $25.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 720.000 $5.000 $8.000 $7.250 $7.650 $6.000 $7.250 $6.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 720.000 $1.000 $1.000 $2.000 $2.100 $1.000 $2.000 $2.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 510.000 $65.000 $1.000 $77.000 $20.000 $25.000 $60.000 $40.000
ONE-WAY TRAF CONT (PILOT CAR)
HR 2,060.000 $90.000 $1.000 $93.500 $50.000 $25.000 $145.000 $150.000
DRIVEWAYS (ACP)
SY 2,055.000 $64.000 $32.340 $22.200 $41.000 $41.000 $34.000 $20.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 116,390.000 $0.150 $0.160 $0.070 $0.150 $0.130 $0.170 $0.150
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 56,160.000 $0.150 $0.160 $0.100 $0.170 $0.160 $0.170 $0.150
MTL W-BEAM GD FEN (TIM POST)
LF 350.000 $28.000 $40.000 $25.750 $28.000 $35.000 $25.750 $30.000
REMOVE METAL BEAM GUARD FENCE
LF 434.000 $6.000 $4.000 $1.750 $2.000 $3.000 $1.750 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $220.000 $350.000 $125.000 $140.000 $500.000 $125.000 $135.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,700.000 $3,500.000 $3,650.000 $3,800.000 $5,000.000 $3,650.000 $4,000.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 41.000 $50.000 $32.290 $32.290 $34.000 $32.290 $32.300 $30.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 34.000 $670.000 $632.110 $632.110 $650.000 $632.110 $633.000 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $1,200.000 $737.750 $737.750 $750.000 $737.750 $738.000 $850.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 12.000 $1,000.000 $877.910 $877.910 $900.000 $877.910 $878.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $1,020.000 $841.170 $841.170 $850.000 $841.170 $842.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,325.000 $953.860 $953.860 $1,000.000 $953.860 $954.000 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 1.000 $1,325.000 $1,237.220 $1,237.220 $1,250.000 $1,237.220 $1,238.000 $1,800.000
REMOVE SM RD SN SUP&AM
EA 53.000 $122.000 $90.000 $90.000 $100.000 $90.000 $90.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GF2
EA 6.000 $40.000 $21.850 $25.000 $24.000 $21.850 $22.000 $22.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 69.000 $80.000 $85.000 $85.000 $90.000 $85.000 $85.000 $85.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 78.000 $24.000 $24.000 $24.000 $25.000 $24.000 $24.000 $15.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 11,114.000 $0.250 $0.220 $0.220 $0.230 $0.220 $0.220 $0.250
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 177,004.000 $0.250 $0.190 $0.190 $0.200 $0.190 $0.190 $0.200
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 4,387.000 $0.500 $0.300 $0.300 $0.320 $0.300 $0.300 $0.300
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 94.000 $15.000 $3.000 $3.000 $3.100 $3.000 $3.000 $3.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 6,232.000 $0.300 $0.200 $0.200 $0.210 $0.200 $0.200 $0.200
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 198,531.000 $0.250 $0.210 $0.210 $0.220 $0.210 $0.210 $0.250
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 38,671.000 $1.000 $0.580 $1.190 $1.500 $1.000 $1.390 $0.550
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 28,455.000 $1.000 $0.580 $1.190 $1.500 $1.000 $1.390 $0.550
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,018.000 $1.000 $0.870 $0.870 $0.920 $0.870 $0.870 $0.900
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 56.000 $12.000 $3.790 $3.790 $4.000 $3.790 $3.790 $4.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 18.000 $175.000 $146.130 $146.130 $150.000 $146.130 $147.000 $150.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 10.000 $200.000 $176.000 $176.000 $180.000 $176.000 $176.000 $190.000
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 16.000 $70.000 $37.230 $37.230 $40.000 $37.230 $38.000 $40.000
PAVEMENT SLER 6"
LF 232,790.000 $0.150 $0.190 $0.190 $0.200 $0.190 $0.190 $0.200
PAVEMENT SLER 8"
LF 2,018.000 $0.450 $0.250 $0.250 $0.260 $0.250 $0.250 $0.250
PAVEMENT SLER 24"
LF 56.000 $0.600 $2.000 $2.000 $2.000 $2.000 $2.000 $2.000
PAVEMENT SLER (ARROW)
EA 18.000 $45.000 $47.200 $47.200 $50.000 $47.200 $47.200 $50.000
PAVEMENT SLER (WORD)
EA 10.000 $65.000 $49.330 $49.330 $50.000 $49.330 $49.330 $50.000
PAVEMENT SLER (YLD TRI)
EA 16.000 $5.000 $10.000 $10.000 $10.000 $10.000 $10.000 $10.000
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 11,686.000 $0.550 $0.490 $0.490 $0.520 $0.490 $0.490 $0.500
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 116,795.000 $0.550 $0.500 $0.500 $0.530 $0.500 $0.500 $0.500
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 4,068.000 $0.550 $0.490 $0.490 $0.520 $0.490 $0.490 $0.500
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 100,241.000 $0.550 $0.500 $0.500 $0.530 $0.500 $0.500 $0.500
REFL PAV MRKR TY I-C
EA 502.000 $3.700 $3.490 $3.490 $4.000 $3.490 $3.500 $3.500
REFL PAV MRKR TY II-A-A
EA 1,638.000 $3.700 $3.460 $3.460 $4.000 $3.460 $3.500 $3.500
UNDERSEAL COURSE
GAL 76,155.000 $3.850 $0.010 $4.540 $3.900 $0.250 $3.950 $4.000
BONDING COURSE
GAL 61,109.000 $3.600 $0.010 $3.140 $2.000 $0.010 $0.010 $4.000
Totals: $8,663,166.470 $7,430,847.080 $7,521,170.216 $8,532,310.140 $8,989,699.880 $8,993,046.890 $9,680,424.800
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
Total: $3,000.00