REMOVING CONC (RIPRAP)
|
SY
|
6,462.000
|
$25.000
|
$2.500
|
$25.000
|
|
|
EXCAVATION (SPECIAL)
|
CY
|
3,229.000
|
$25.000
|
$14.000
|
$18.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
1.200
|
$160.000
|
$2,600.000
|
$1,000.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
5,383.000
|
$20.000
|
$6.500
|
$9.000
|
|
|
GENERAL USE COMPOST (1")
|
SY
|
346.000
|
$29.000
|
$53.000
|
$25.000
|
|
|
BLOCK SODDING
|
SY
|
6,462.000
|
$8.000
|
$3.250
|
$3.500
|
|
|
VEGETATIVE WATERING
|
MG
|
160.000
|
$15.000
|
$26.000
|
$70.000
|
|
|
PLANT BED PREP (TYPE II)
|
SY
|
3,099.000
|
$2.000
|
$2.650
|
$3.500
|
|
|
SALV,HAUL & STKPL RCL APH PV (2")
|
SY
|
132,402.000
|
$1.390
|
$0.500
|
$1.500
|
|
|
ASPH (MULTI OPTION)
|
GAL
|
72,822.000
|
$2.750
|
$3.000
|
$2.100
|
|
|
AGGR(TY-PB GR-4 SAC-B)
|
CY
|
1,325.000
|
$105.000
|
$107.000
|
$125.000
|
|
|
TOM (ASPHALT) PG 76-22
|
TON
|
883.000
|
$120.000
|
$120.000
|
$120.000
|
|
|
TOM-C (AGGREGATE) SAC-A
|
TON
|
6,787.000
|
$112.500
|
$120.000
|
$120.000
|
|
|
TOM-F (AGGREGATE) SAC-B
|
TON
|
5,074.000
|
$100.000
|
$120.000
|
$120.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
|
SY
|
3,000.000
|
$50.000
|
$30.000
|
$27.000
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
48.600
|
$300.000
|
$590.000
|
$900.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$344,000.000
|
$197,000.000
|
$80,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
4.000
|
$5,000.000
|
$2,800.000
|
$4,000.000
|
|
|
LANDSCAPE PAVERS
|
SY
|
3,269.000
|
$85.000
|
$78.000
|
$95.000
|
|
|
CONC CURB (DOWEL)
|
LF
|
15.000
|
$10.500
|
$135.000
|
$80.000
|
|
|
REPLACE EXISTING ALUMINUM SIGNS(TY A)
|
SF
|
143.950
|
$23.500
|
$20.000
|
$25.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
|
LF
|
21,090.000
|
$0.210
|
$0.150
|
$0.250
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
88,677.000
|
$0.200
|
$0.150
|
$0.250
|
|
|
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
|
LF
|
19,461.000
|
$0.420
|
$0.200
|
$0.450
|
|
|
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
|
LF
|
3,021.000
|
$2.000
|
$0.750
|
$1.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
837.000
|
$1.750
|
$0.750
|
$3.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)(ARROW)
|
EA
|
33.000
|
$45.000
|
$57.500
|
$40.000
|
|
|
WK ZN PAV MRK NON-REMOV(W)(WORD)
|
EA
|
30.000
|
$60.000
|
$68.000
|
$40.000
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
|
LF
|
16,860.000
|
$0.200
|
$0.170
|
$0.250
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
90,324.000
|
$0.200
|
$0.170
|
$0.250
|
|
|
WK ZN PAV MRK NON-REMOV (Y)24"(SLD)
|
LF
|
1,575.000
|
$1.000
|
$1.040
|
$3.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
6,487.000
|
$0.950
|
$1.040
|
$1.500
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
1,007.000
|
$2.700
|
$3.130
|
$3.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
279.000
|
$5.100
|
$6.280
|
$7.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
11.000
|
$103.500
|
$157.000
|
$200.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
10.000
|
$130.000
|
$260.000
|
$200.000
|
|
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
|
LF
|
525.000
|
$4.000
|
$6.300
|
$7.000
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
|
LF
|
7,030.000
|
$0.500
|
$0.400
|
$0.420
|
|
|
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
|
LF
|
29,559.000
|
$0.500
|
$0.850
|
$0.580
|
|
|
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
|
LF
|
5,620.000
|
$0.400
|
$0.850
|
$0.580
|
|
|
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
|
LF
|
30,454.000
|
$0.900
|
$0.850
|
$0.580
|
|
REFL PAV MRKR TY I-C
|
EA
|
388.000
|
$3.500
|
$3.200
|
$5.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
362.000
|
$3.500
|
$3.000
|
$5.000
|
|
|
LANDSCAPE SOIL AMENDMENT (TYPE I)
|
SY
|
6,462.000
|
$1.000
|
$0.400
|
$1.250
|
|
|
LANDSCAPE SOIL AMENDMENT (TYPE II)
|
SY
|
5,079.000
|
$1.000
|
$0.500
|
$1.250
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
134.000
|
$64.500
|
$52.250
|
$100.000
|
|
|
TMA (STATIONARY)
|
DAY
|
9.000
|
$200.000
|
$287.000
|
$900.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
54.000
|
$25.000
|
$42.500
|
$150.000
|
|
Totals: |
$3,283,656.625
|
$2,837,928.340
|
$3,092,308.140
|