PREPARING ROW
|
STA
|
56.600
|
$2,000.000
|
$1,545.000
|
$2,000.000
|
$4,400.000
|
$1,588.500
|
|
|
REMOVING STAB BASE AND ASPH PAV (6")
|
SY
|
41,265.000
|
$2.370
|
$1.000
|
$4.250
|
$2.450
|
$6.150
|
|
|
OBLITERATING ABANDONED ROAD
|
STA
|
54.000
|
$576.500
|
$1,150.000
|
$450.000
|
$1,000.000
|
$3,937.500
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
316.000
|
$10.000
|
$16.000
|
$25.000
|
$13.000
|
$10.500
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
77,653.000
|
$6.000
|
$21.000
|
$25.000
|
$30.000
|
$24.300
|
|
|
BACKFILL (TY B)
|
STA
|
56.600
|
$150.000
|
$2,350.000
|
$100.000
|
$1,400.000
|
$206.150
|
|
|
BLOCK SODDING
|
SY
|
71,295.000
|
$3.000
|
$3.750
|
$3.250
|
$3.500
|
$6.150
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
114,422.000
|
$0.070
|
$0.150
|
$0.150
|
$0.050
|
$0.150
|
|
|
CELL FBR MLCH SEED(PERM)(SPECIAL MIX)
|
SY
|
42,349.000
|
$0.500
|
$0.600
|
$0.600
|
$0.350
|
$0.450
|
|
|
FERTILIZER
|
AC
|
47.120
|
$1,100.000
|
$725.000
|
$500.000
|
$972.000
|
$583.000
|
|
|
VEGETATIVE WATERING
|
MG
|
5,653.510
|
$14.800
|
$7.000
|
$18.750
|
$7.000
|
$26.150
|
|
|
CEMENT
|
TON
|
547.100
|
$132.830
|
$175.000
|
$175.000
|
$155.000
|
$144.700
|
|
|
CEMENT TREAT (EXIST MATL) (6")
|
SY
|
40,925.000
|
$2.700
|
$3.600
|
$4.000
|
$3.750
|
$4.180
|
|
|
ASPHALT STAB BASE (GR 2)(PG 70)
|
TON
|
13,224.200
|
$85.000
|
$89.000
|
$75.000
|
$85.000
|
$130.000
|
|
|
ASPHALT STAB BASE (GR 4)(PG 64)
|
TON
|
61.440
|
$72.600
|
$134.000
|
$200.000
|
$85.000
|
$257.000
|
|
|
SALV,HAUL & STKPL RCL ASPH PV (1 TO 3")
|
SY
|
36,231.000
|
$5.000
|
$1.000
|
$2.250
|
$2.500
|
$3.450
|
|
|
SALV, HAUL & STKPL RCL ASPH PV (10")
|
SY
|
4,842.000
|
$4.150
|
$3.500
|
$7.500
|
$7.500
|
$14.000
|
|
|
D-GR HMA(SQ) TY-D SAC-A PG70-22
|
TON
|
2,198.700
|
$110.000
|
$115.000
|
$100.000
|
$98.000
|
$178.250
|
|
|
D-GR HMA(SQ) TY-D PG70-22
|
TON
|
2,250.600
|
$105.000
|
$111.000
|
$95.000
|
$98.000
|
$173.500
|
|
|
CONC PVMT (CONT REINF - CRCP) (8")
|
SY
|
1,117.000
|
$44.500
|
$87.000
|
$100.000
|
$135.000
|
$86.450
|
|
|
CEM STABIL BKFL
|
CY
|
11.000
|
$39.400
|
$90.000
|
$100.000
|
$215.000
|
$113.650
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
72.000
|
$600.000
|
$550.000
|
$750.000
|
$400.000
|
$461.450
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
68.000
|
$500.000
|
$80.000
|
$130.000
|
$135.000
|
$136.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$175.000
|
$1,200.000
|
$2,400.000
|
$2,280.000
|
$3,260.000
|
|
|
PIPE (MISC) (6 IN)
|
LF
|
2,357.000
|
$18.000
|
$10.000
|
$20.000
|
$14.500
|
$8.900
|
|
|
PIPE (MISC) (8 IN)
|
LF
|
1,644.000
|
$20.000
|
$13.000
|
$24.000
|
$18.000
|
$9.300
|
|
|
REMOV STR (PIPE)
|
LF
|
370.000
|
$950.000
|
$15.000
|
$20.000
|
$22.000
|
$39.500
|
|
|
REMOV STR (PICNIC AREA)
|
EA
|
1.000
|
$6,000.000
|
$2,100.000
|
$2,800.000
|
$6,500.000
|
$3,910.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$513,812.000
|
$160,000.000
|
$300,000.000
|
$800,000.000
|
$141,745.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
10.000
|
$3,500.000
|
$1,000.000
|
$1,000.000
|
$3,200.000
|
$55.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
115.000
|
$27.500
|
$35.000
|
$35.000
|
$20.000
|
$28.500
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
115.000
|
$9.000
|
$8.000
|
$15.000
|
$11.000
|
$28.500
|
|
|
CONSTRUCTION PERIMETER FENCE
|
LF
|
1,240.000
|
$1.300
|
$6.000
|
$5.000
|
$2.250
|
$1.850
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
26,555.000
|
$2.500
|
$2.500
|
$2.000
|
$2.250
|
$1.650
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
26,555.000
|
$0.900
|
$1.000
|
$1.000
|
$0.800
|
$0.660
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
160.000
|
$5.000
|
$10.000
|
$25.000
|
$7.000
|
$4.950
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
160.000
|
$0.850
|
$3.000
|
$2.500
|
$3.000
|
$1.100
|
|
|
CONC CURB (DOWEL)
|
LF
|
1,440.000
|
$7.200
|
$13.000
|
$20.000
|
$22.000
|
$8.100
|
|
|
DRIVEWAYS (CONC)
|
SY
|
7,924.000
|
$68.000
|
$88.000
|
$110.000
|
$80.000
|
$70.650
|
|
|
CONC SIDEWALKS (4")
|
SY
|
996.000
|
$55.000
|
$56.000
|
$67.000
|
$85.000
|
$87.200
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
65.000
|
$462.000
|
$450.000
|
$675.000
|
$455.300
|
$410.750
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
5.000
|
$780.000
|
$500.000
|
$875.000
|
$541.460
|
$472.500
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
745.000
|
$2.000
|
$1.200
|
$1.000
|
$1.500
|
$1.100
|
|
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
|
LF
|
100.000
|
$3.500
|
$4.750
|
$3.000
|
$3.400
|
$4.400
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
490.000
|
$5.900
|
$8.000
|
$5.000
|
$6.800
|
$7.700
|
|
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
|
LF
|
145.000
|
$0.900
|
$1.200
|
$1.000
|
$1.500
|
$1.100
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
19,465.000
|
$0.650
|
$0.800
|
$0.400
|
$1.050
|
$0.850
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
1,470.000
|
$0.330
|
$0.400
|
$0.500
|
$1.050
|
$0.450
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
6,030.000
|
$0.650
|
$0.400
|
$0.500
|
$1.050
|
$0.450
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
370.000
|
$0.460
|
$1.000
|
$1.000
|
$1.150
|
$1.100
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
1.000
|
$331.000
|
$325.000
|
$250.000
|
$315.000
|
$315.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
1.000
|
$355.000
|
$325.000
|
$350.000
|
$375.000
|
$325.000
|
|
PRE PM TY C(ACC PRK)(BL&WH)(W/BORDR)LG
|
EA
|
18.000
|
$250.000
|
$325.000
|
$500.000
|
$290.000
|
$325.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
14.000
|
$3.150
|
$6.000
|
$10.000
|
$4.000
|
$6.600
|
|
|
ELIM EXT PAV MRK & MRKS (6")
|
LF
|
370.000
|
$0.650
|
$1.000
|
$1.000
|
$0.750
|
$1.100
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
26,965.000
|
$0.260
|
$0.050
|
$0.010
|
$0.010
|
$0.010
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
370.000
|
$0.640
|
$0.050
|
$0.010
|
$0.010
|
$0.020
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
890.000
|
$0.570
|
$0.050
|
$0.010
|
$0.010
|
$0.060
|
|
|
PAV SURF PREP FOR MRK (12")
|
LF
|
100.000
|
$1.000
|
$0.250
|
$0.010
|
$0.010
|
$0.330
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
490.000
|
$2.000
|
$0.250
|
$0.010
|
$0.010
|
$0.330
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
1.000
|
$22.500
|
$5.000
|
$1.000
|
$0.010
|
$5.500
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
1.000
|
$28.500
|
$5.000
|
$1.000
|
$0.010
|
$5.500
|
|
|
PAV SURF PREP FOR MRK (ACC PRK)(LRG)
|
EA
|
18.000
|
$55.000
|
$5.000
|
$500.000
|
$0.010
|
$5.500
|
|
|
REINFORCED GRASS PAVING
|
SY
|
14,698.000
|
$50.000
|
$62.000
|
$58.000
|
$60.000
|
$78.590
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
10.000
|
$35.000
|
$140.000
|
$200.000
|
$126.000
|
$140.000
|
|
|
TMA (STATIONARY)
|
DAY
|
7.000
|
$252.000
|
$200.000
|
$750.000
|
$450.000
|
$550.000
|
|
|
CASING STEEL (18IN)
|
LF
|
832.000
|
$130.000
|
$145.000
|
$95.000
|
$205.000
|
$116.750
|
|
Totals: |
$5,816,585.225
|
$6,676,661.130
|
$7,163,856.412
|
$8,182,306.410
|
$8,468,238.382
|