PREPARING ROW (TREE) (0" TO 6" DIA)
|
EA
|
431.000
|
$300.000
|
$100.000
|
$100.000
|
$135.000
|
$65.000
|
|
|
PREPARING ROW (TREE) (6" TO 24" DIA)
|
EA
|
64.000
|
$500.000
|
$300.000
|
$500.000
|
$935.000
|
$280.000
|
|
|
PREPARING ROW(TREE)(24" TO 36" DIA.)
|
EA
|
9.000
|
$1,500.000
|
$1,000.000
|
$1,000.000
|
$2,650.000
|
$2,000.000
|
|
|
REMOVING CONC (MISC)
|
SY
|
168.000
|
$25.000
|
$30.000
|
$10.000
|
$38.700
|
$35.000
|
|
|
REMOVING STAB BASE AND ASPH PAV (11")
|
SY
|
3,653.000
|
$6.000
|
$6.570
|
$5.000
|
$11.850
|
$15.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
1,689.000
|
$15.000
|
$14.000
|
$20.000
|
$23.350
|
$20.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY A)
|
CY
|
1,027.000
|
$25.000
|
$20.000
|
$20.000
|
$29.000
|
$30.000
|
|
|
DRILL SEEDING (PERM) (RURAL) (SANDY)
|
SY
|
12,265.000
|
$0.750
|
$0.336
|
$0.250
|
$0.350
|
$0.300
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
12,265.000
|
$0.500
|
$0.320
|
$0.250
|
$0.300
|
$0.250
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY D)
|
SY
|
875.000
|
$3.000
|
$2.464
|
$3.000
|
$2.350
|
$2.850
|
|
|
FL BS (CMP IN PLC)(TY A OR B GR4)(12")
|
SY
|
4,462.000
|
$25.000
|
$36.270
|
$30.000
|
$28.500
|
$40.000
|
|
|
CEMENT
|
TON
|
48.000
|
$195.000
|
$220.000
|
$200.000
|
$210.000
|
$180.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
4,462.000
|
$4.000
|
$3.000
|
$10.000
|
$5.600
|
$3.500
|
|
|
PRIME COAT (MC-30)
|
GAL
|
1,088.000
|
$5.000
|
$11.000
|
$12.000
|
$6.250
|
$7.000
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
1,227.000
|
$5.000
|
$8.800
|
$10.000
|
$6.000
|
$7.000
|
|
|
CEM STABIL BKFL
|
CY
|
252.600
|
$225.000
|
$220.000
|
$325.000
|
$220.000
|
$250.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
320.000
|
$125.000
|
$130.880
|
$200.000
|
$140.000
|
$150.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
1,973.000
|
$250.000
|
$156.660
|
$250.000
|
$340.000
|
$330.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
91.200
|
$1,500.000
|
$1,200.000
|
$1,500.000
|
$1,275.000
|
$1,500.000
|
|
|
CL C CONC (CAP)(HPC)
|
CY
|
100.100
|
$1,500.000
|
$1,200.000
|
$1,500.000
|
$1,465.000
|
$2,000.000
|
|
|
CL C CONC (COLUMN)(HPC)
|
CY
|
34.500
|
$1,200.000
|
$1,250.000
|
$1,500.000
|
$1,300.000
|
$1,200.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
18,360.000
|
$27.000
|
$25.000
|
$30.000
|
$30.000
|
$30.000
|
|
|
APPROACH SLAB
|
CY
|
102.600
|
$621.000
|
$650.000
|
$1,000.000
|
$820.000
|
$770.000
|
|
|
PRESTR CONC GIRDER (TX34)
|
LF
|
2,142.000
|
$214.530
|
$187.500
|
$200.000
|
$205.000
|
$175.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
128.000
|
$500.000
|
$500.000
|
$700.000
|
$595.000
|
$542.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(18 IN)
|
CY
|
380.000
|
$150.000
|
$150.000
|
$150.000
|
$182.000
|
$220.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
64.000
|
$500.000
|
$500.000
|
$750.000
|
$735.000
|
$775.000
|
|
|
RAIL (TY T223)(HPC)
|
LF
|
1,184.000
|
$110.000
|
$130.000
|
$125.000
|
$115.000
|
$175.000
|
|
|
HEADER TYPE EXPANSION JOINT
|
LF
|
136.000
|
$110.000
|
$125.000
|
$100.000
|
$230.000
|
$60.000
|
|
|
CMP (ALUMINUM 24")
|
LF
|
72.000
|
$50.000
|
$100.000
|
$100.000
|
$105.000
|
$150.000
|
|
|
SET (TY I) (72 IN) (4: 1) (C)
|
EA
|
2.000
|
$8,000.000
|
$18,037.070
|
$15,000.000
|
$26,600.000
|
$30,000.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
1.000
|
$1,050.000
|
$1,100.000
|
$500.000
|
$2,300.000
|
$5,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
12.000
|
$18.000
|
$15.000
|
$20.000
|
$82.000
|
$401.000
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
2.000
|
$70,000.000
|
$88,550.000
|
$75,000.000
|
$80,000.000
|
$150,000.000
|
|
|
REMOV STR (SMALL FENCE)
|
LF
|
2,433.000
|
$5.000
|
$4.000
|
$5.000
|
$2.300
|
$3.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$250,000.000
|
$419,155.190
|
$400,000.000
|
$416,000.000
|
$430,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
9.000
|
$12,000.000
|
$1,989.380
|
$5,000.000
|
$17,000.000
|
$15,000.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
440.000
|
$4.000
|
$3.920
|
$5.000
|
$7.500
|
$12.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
440.000
|
$1.250
|
$1.120
|
$1.000
|
$3.000
|
$3.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
350.000
|
$5.000
|
$3.920
|
$5.000
|
$9.900
|
$12.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
350.000
|
$1.750
|
$1.120
|
$1.000
|
$3.800
|
$3.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
900.000
|
$26.000
|
$29.150
|
$30.000
|
$36.150
|
$37.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
8.000
|
$2,000.000
|
$1,925.000
|
$2,000.000
|
$2,615.000
|
$2,085.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,000.000
|
$3.600
|
$2.000
|
$5.000
|
$3.150
|
$1.600
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
8.000
|
$360.000
|
$250.000
|
$500.000
|
$317.000
|
$300.000
|
|
|
RM MTL BM GD FEN TRANS (T101)
|
EA
|
8.000
|
$250.000
|
$275.000
|
$500.000
|
$317.000
|
$250.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
8.000
|
$2,700.000
|
$3,135.000
|
$3,000.000
|
$3,455.000
|
$2,980.000
|
|
|
WIRE FENCE (TY C)
|
LF
|
2,332.000
|
$15.000
|
$22.400
|
$15.000
|
$21.100
|
$17.000
|
|
|
WIRE FENCE (WATER GAP)
|
LF
|
150.000
|
$60.000
|
$33.600
|
$30.000
|
$31.620
|
$100.000
|
|
|
CORNER OR PULL POST AM(REM/REP)(METAL)
|
EA
|
21.000
|
$250.000
|
$1,120.000
|
$500.000
|
$1,055.000
|
$250.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
2.000
|
$725.000
|
$980.000
|
$1,000.000
|
$925.000
|
$610.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
6.000
|
$900.000
|
$1,120.000
|
$1,500.000
|
$1,055.000
|
$640.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
6.000
|
$115.000
|
$112.000
|
$100.000
|
$125.000
|
$75.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
16.000
|
$27.000
|
$44.800
|
$50.000
|
$19.000
|
$12.750
|
|
|
REMOVE DELIN & OBJECT MARKER ASSMS
|
EA
|
32.000
|
$17.500
|
$16.800
|
$10.000
|
$105.000
|
$10.500
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
25.000
|
$38.000
|
$140.000
|
$50.000
|
$40.000
|
$35.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND
|
EA
|
2.000
|
$140.000
|
$26.000
|
$200.000
|
$153.000
|
$65.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
2,480.000
|
$0.260
|
$0.840
|
$1.000
|
$0.790
|
$0.750
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
3,852.000
|
$0.400
|
$1.400
|
$1.500
|
$1.320
|
$1.250
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
3,852.000
|
$0.390
|
$1.400
|
$1.500
|
$1.320
|
$1.250
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
2,480.000
|
$1.000
|
$0.560
|
$1.000
|
$0.530
|
$0.500
|
|
|
SP MIXES SP-D SAC-A PG70-22
|
TON
|
957.000
|
$180.000
|
$296.800
|
$275.000
|
$160.000
|
$195.000
|
|
|
TACK COAT
|
GAL
|
565.000
|
$5.000
|
$20.720
|
$20.000
|
$4.650
|
$4.000
|
|
|
INSTALL BRIDGE IDENTIFICATION NUMBERS
|
EA
|
4.000
|
$250.000
|
$250.000
|
$2,000.000
|
$335.000
|
$500.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$12,000.000
|
$15,750.000
|
$15,000.000
|
$21,700.000
|
$15,000.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
20.000
|
$80.000
|
$90.000
|
$400.000
|
$78.000
|
$95.000
|
|
Totals: |
$3,527,838.490
|
$3,478,339.720
|
$3,927,759.500
|
$4,162,986.230
|
$4,327,644.500
|