PREPARING ROW
|
STA
|
30.000
|
$2,500.000
|
$1,729.000
|
$1,440.000
|
|
|
REMOVING CONC (DRIVEWAYS)
|
SY
|
123.000
|
$27.880
|
$39.000
|
$22.300
|
|
|
REMOVING STAB BASE & ASPH PAV (0"-10")
|
SY
|
717.000
|
$15.000
|
$15.250
|
$33.500
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,576.000
|
$22.000
|
$29.000
|
$21.900
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
130.000
|
$50.000
|
$45.000
|
$14.600
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
11,516.000
|
$2.840
|
$2.340
|
$2.100
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
SY
|
11,516.000
|
$0.570
|
$0.220
|
$0.230
|
|
|
DRILL SEED (TEMP)(WARM OR COOL)
|
SY
|
11,516.000
|
$0.250
|
$0.150
|
$0.160
|
|
|
VEGETATIVE WATERING
|
MG
|
186.000
|
$38.700
|
$25.000
|
$38.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
11,516.000
|
$2.000
|
$0.950
|
$1.000
|
|
|
PROOF ROLLING
|
HR
|
5.000
|
$148.740
|
$139.000
|
$92.100
|
|
|
FL BS (CIP)(TY D GR 1-2, OR 5)FINAL POS
|
CY
|
2,387.000
|
$50.000
|
$73.250
|
$61.700
|
|
|
PRIME COAT(MC-30 OR AE-P)
|
GAL
|
1,078.000
|
$12.130
|
$8.000
|
$4.250
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
5,101.000
|
$50.000
|
$40.250
|
$47.700
|
|
|
PLANE ASPH CONC PAV (2")
|
SY
|
11,617.000
|
$3.000
|
$1.400
|
$3.000
|
|
|
PLANE ASPH CONC PAV (6")
|
SY
|
1,489.000
|
$5.830
|
$5.500
|
$7.700
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$136,860.440
|
$137,000.000
|
$112,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
6.000
|
$10,000.000
|
$12,000.000
|
$4,520.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
50.000
|
$42.070
|
$40.000
|
$42.300
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
50.000
|
$12.000
|
$10.000
|
$25.400
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
156.000
|
$33.990
|
$24.000
|
$25.400
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
156.000
|
$12.630
|
$5.000
|
$2.100
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
5,084.000
|
$4.000
|
$1.950
|
$2.050
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
5,084.000
|
$1.000
|
$0.500
|
$0.530
|
|
|
DRIVEWAYS (CONC)
|
SY
|
123.000
|
$122.180
|
$131.000
|
$140.000
|
|
|
DRIVEWAYS (ACP)(TYPE 1)
|
SY
|
717.000
|
$64.110
|
$58.000
|
$90.700
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 1
|
EA
|
12.000
|
$271.420
|
$360.000
|
$311.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
8.000
|
$793.060
|
$808.000
|
$865.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
2.000
|
$910.450
|
$975.000
|
$1,070.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SB(U)
|
EA
|
2.000
|
$1,233.990
|
$1,450.000
|
$1,750.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
8.000
|
$147.860
|
$140.000
|
$130.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
12,400.000
|
$1.240
|
$0.690
|
$1.300
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
12,400.000
|
$1.120
|
$0.690
|
$1.300
|
|
REFL PAV MRK TY I(Y)(MED NOSE)(100MIL)
|
EA
|
2.000
|
$490.810
|
$449.000
|
$476.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
5,563.000
|
$0.380
|
$0.310
|
$0.530
|
|
|
PAVEMENT SEALER 6"
|
LF
|
6,313.000
|
$2.100
|
$0.470
|
$0.630
|
|
|
PAVEMENT SEALER (MED NOSE)
|
EA
|
2.000
|
$163.920
|
$147.000
|
$159.000
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
6,313.000
|
$0.740
|
$0.790
|
$1.300
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
860.000
|
$0.870
|
$0.510
|
$1.050
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
4,703.000
|
$0.960
|
$0.480
|
$1.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
46.000
|
$6.100
|
$4.440
|
$10.600
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
87.000
|
$7.080
|
$4.440
|
$10.600
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
1,000.000
|
$0.950
|
$0.870
|
$2.650
|
|
|
TACK COAT
|
GAL
|
720.000
|
$5.000
|
$3.500
|
$3.500
|
|
|
D-GR HMA TY-C PG64-22
|
TON
|
2,316.000
|
$90.000
|
$97.000
|
$106.000
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
1,357.000
|
$125.000
|
$105.000
|
$111.000
|
|
|
BONDING COURSE
|
GAL
|
1,435.000
|
$6.170
|
$3.500
|
$4.200
|
|
|
UNDERSEAL COURSE
|
GAL
|
1,238.000
|
$4.100
|
$3.500
|
$4.750
|
|
|
GEOGRID BASE REINFORCEMENT (TY II)
|
SY
|
7,219.000
|
$3.270
|
$1.300
|
$3.300
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$13,646.790
|
$6,000.000
|
$11,500.000
|
|
|
TMA (STATIONARY)
|
DAY
|
76.000
|
$335.380
|
$250.000
|
$128.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
104.000
|
$105.230
|
$80.000
|
$106.000
|
|
Totals: |
$1,505,464.880
|
$1,371,678.580
|
$1,413,416.640
|