HALL SH 256 (0541-02-033)

Items: 81

County: HALL
Length: 0.0000 MILES (0.9024 MILES)
Highway: SH 256
District: CHILDRESS
Control Number: 0541-02-033
DBE Goal: 0.0%
Project: C 541-2-33
Guaranty: $100,000.00
Time: 264 WORKING DAYS
Engineer's Estimate: $8,833,129.70
Date: 08/06/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263214
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00128671
Project Description: REHABILITATION OF EXISTING ROADWAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$8,833,129.70
$9,477,780.50
Over/Under Est: 7.3% $644,650.80
$13,244,546.40
Over/Under Est: 49.94% $4,411,416.70
Amt Left: 39.74% $3,766,765.90
$14,271,374.62
Over/Under Est: 61.57% $5,438,244.92
Amt Left: 50.58% $4,793,594.12
Delta: -7.75% -$1,026,828.22

Bid Items & Bid Tabulations

81 Total 0 of 81
HALL  |  SH 256  |  CHILDRESS  |  0541-02-033  |  08/06/2026 1:00 PM CDT  |  $8,833,129.70  |  C 541-2-33  |  REHAB EXIST ROADWAY  |  264 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J. LEE MILLIGAN, INC.
EARTH BUILDERS, L.P.
A. L. HELMCAMP, INC.
PREPARING ROW
STA 48.000 $4,000.000 $7,000.000 $18,000.000 $300.000
REMOV CONC (PAV)
SY 1,410.000 $25.000 $25.000 $20.000 $36.000
REMOV CONC (RIPRAP)
SY 88.000 $45.000 $60.000 $20.000 $66.000
REMOV CONC (DRIVEWAYS)
SY 2,947.000 $30.000 $26.000 $20.000 $55.000
REMOV CONC (SIDEWALK, RAMP OR SUP)
SY 2,583.000 $28.000 $20.000 $20.000 $45.000
REMOV CONC (CURB OR CURB & GUTTER)
LF 7,568.000 $27.600 $8.000 $20.000 $29.000
REMOV CONC (RETAINING WALLS)
SY 3.000 $100.000 $245.000 $50.000 $2,300.000
RMV (7"-11") TRT/UNTRT BASE & ASPH PAV
SY 1,410.000 $12.000 $22.600 $22.000 $36.000
RMV (12"-30") TRT/UNTRT BASE & ASPH PAV
SY 11,540.000 $15.000 $20.500 $30.000 $55.000
RMV, CLN, PALLETZ, & STORE STREET BRICK
SY 13,369.000 $30.000 $28.500 $120.000 $19.000
EXCAV (ROADWAY)
CY 10,217.000 $25.000 $9.600 $30.000 $68.000
EMBANK (FNL)(OC)(TY A)
CY 573.000 $100.000 $31.000 $45.000 $30.000
BLOCK SODDING
SY 2,354.000 $12.000 $8.400 $9.000 $8.000
BROADCAST SEED (TEMP_WARM_COOL)
SY 2,354.000 $0.600 $1.100 $2.000 $1.500
FL BS (CMP IN PLC)(TY A GR 1-2) (10")
SY 24,249.000 $20.000 $37.000 $50.000 $49.000
CEMENT
TON 341.000 $270.000 $290.000 $450.000 $360.000
CEMENT TRT (SUBGRADE) (8")
SY 24,349.000 $7.000 $6.000 $18.000 $14.000
PRIME COAT (MC-30)
GAL 4,855.000 $6.450 $5.100 $10.000 $12.000
D-GR HMA TY-D SAC-A PG70-28
TON 6,695.000 $115.000 $175.000 $250.000 $261.000
TACK COAT
GAL 15,166.000 $5.000 $6.500 $10.000 $5.000
CONC PVMT (CRCP) (9")
SY 3,787.000 $100.000 $150.000 $125.000 $225.000
CONC PVMT (CRCP) (13")
SY 4,028.000 $135.000 $230.000 $155.000 $310.000
CL A CONC (MISC)
CY 1,916.000 $600.000 $360.000 $650.000 $950.000
RETAINING WALL (SPREAD FOOTING)
SF 838.000 $250.000 $91.500 $100.000 $200.000
RAIL (HANDRAIL)(TY A)
LF 308.000 $256.750 $215.000 $95.000 $165.000
RC PIPE (CL III)(24 IN)
LF 55.000 $136.000 $160.000 $150.000 $200.000
RC PIPE (ARCH)(CL III)(DES 5)
LF 48.000 $451.000 $385.000 $320.000 $380.000
INLET (COMPL)(PCU)(5FT)(NONE)
EA 4.000 $17,000.000 $8,800.000 $7,000.000 $12,000.000
REMOV STR (INLET)
EA 4.000 $1,500.000 $1,800.000 $1,200.000 $2,000.000
REMOV STR (PIPE)
LF 109.000 $35.000 $65.000 $25.000 $65.000
MOBILIZATION
LS 1.000 $800,000.000 $1,042,500.000 $1,400,000.000 $1,400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $18,000.000 $32,800.000 $7,500.000 $50,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 264.000 $100.000 $250.000 $140.000 $200.000
TMA (STATIONARY)
DAY 65.000 $330.000 $400.000 $250.000 $150.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 1,326.000 $35.000 $15.000 $50.000 $25.000
CONSTRUCTION EXITS (REMOVE)
SY 1,326.000 $12.000 $1.500 $8.000 $5.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 8,902.000 $8.000 $7.000 $5.000 $5.100
BIODEG EROSN CONT LOGS (REMOVE)
LF 8,902.000 $3.000 $2.000 $1.000 $1.000
CONSTRUCTING DETOURS
SY 310.000 $117.500 $130.000 $150.000 $220.000
REMOVE AND RELAY PAVERS
SY 3,823.000 $100.000 $40.150 $175.000 $45.000
CONC CURB (MONO) (TY II)
LF 1,385.000 $25.000 $13.000 $15.000 $50.000
CONC CURB & GUTTER (TY II)
LF 5,768.000 $45.000 $42.500 $45.000 $50.000
DRIVEWAYS (CONC)
SY 2,404.000 $130.000 $150.000 $100.000 $220.000
CONC SIDEWALKS (4")
SY 3,725.000 $160.000 $110.000 $85.000 $150.000
CONC SIDEWALK (STEPS)
SY 239.000 $250.000 $300.000 $150.000 $190.000
CURB RAMPS (TY 1)
EA 1.000 $3,000.000 $2,000.000 $1,500.000 $3,900.000
CURB RAMPS (TY 7)
EA 40.000 $3,200.000 $2,000.000 $1,500.000 $2,600.000
CURB RAMPS (TY 10)
EA 2.000 $2,200.000 $2,000.000 $1,500.000 $3,900.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 13.000 $345.000 $670.000 $250.000 $230.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 1.000 $710.000 $1,100.000 $600.000 $580.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 48.000 $900.000 $850.000 $1,400.000 $1,200.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,200.000 $1,385.000 $1,400.000 $1,200.000
REMOVE SM RD SN SUP&AM
EA 4.000 $200.000 $200.000 $150.000 $110.000
INSTL OM ASSM (OM-2X)(WC)GND
EA 14.000 $70.000 $275.000 $85.000 $85.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 5,782.000 $0.500 $1.300 $2.000 $0.360
WK ZN PAV MRK REMOV (W)6"(SLD)
LF 1,326.000 $1.100 $1.650 $2.000 $0.900
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 10.000 $18.000 $21.900 $22.000 $7.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 9,004.000 $1.250 $1.650 $2.000 $0.900
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 1,492.000 $4.000 $7.400 $8.000 $3.500
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 341.000 $11.000 $13.150 $15.000 $8.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 1.000 $210.000 $330.000 $350.000 $170.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $260.000 $440.000 $500.000 $180.000
REFL PAV MRK TY I (W)(SYMBOL)(100MIL)
EA 5.000 $325.000 $440.000 $500.000 $190.000
PAVEMENT SLER 6"
LF 8,917.000 $0.650 $0.950 $1.000 $0.250
PAVEMENT SLER 12"
LF 1,492.000 $1.200 $3.250 $3.500 $0.400
PAVEMENT SLER 24"
LF 341.000 $3.800 $5.500 $6.000 $0.600
PAVEMENT SLER (ARROW)
EA 1.000 $80.000 $110.000 $120.000 $10.000
PAVEMENT SLER (WORD)
EA 1.000 $150.000 $165.000 $180.000 $10.000
PAVEMENT SLER (SYMBOL)
EA 5.000 $105.280 $165.000 $180.000 $16.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 1,606.000 $0.700 $5.500 $6.000 $1.100
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 7,311.000 $1.000 $2.200 $2.500 $0.750
REFL PAV MRKR TY I-C
EA 367.000 $5.000 $8.200 $9.000 $4.200
ELIM EXT PM & MRKS (4")
LF 3,064.000 $1.300 $2.500 $3.000 $1.000
ELIM EXT PM & MRKS (8")
LF 70.000 $1.700 $3.300 $4.000 $1.000
ELIM EXT PM & MRKS (18")
LF 24.000 $4.600 $5.500 $6.000 $2.000
PAV SURF PREP FOR MRK (6")
LF 8,917.000 $0.500 $0.850 $1.200 $0.200
PAV SURF PREP FOR MRK (12")
LF 1,492.000 $0.850 $3.300 $3.500 $0.250
PAV SURF PREP FOR MRK (24")
LF 341.000 $3.000 $5.500 $5.500 $0.600
PAV SURF PREP FOR MRK (ARROW)
EA 1.000 $70.000 $110.000 $110.000 $11.000
PAV SURF PREP FOR MRK (WORD)
EA 1.000 $70.000 $165.000 $160.000 $11.000
PAV SURF PREP FOR MRK (SYMBOL)
EA 5.000 $50.000 $165.000 $160.000 $16.000
Totals: $8,833,129.700 $9,477,780.500 $13,244,546.400 $14,271,374.620
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $9,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
Total: $10,000.00