PREPARING ROW
|
STA
|
21.900
|
$2,000.000
|
$2,900.000
|
$9,000.000
|
$2,430.000
|
|
|
REMOVING CONC (PILE ENCASEMENT)
|
CY
|
5.000
|
$800.000
|
$1,575.000
|
$6,842.500
|
$348.000
|
|
|
REMOVING STAB BASE & ASPH PAV (0"-10")
|
SY
|
1,361.000
|
$4.000
|
$16.000
|
$9.130
|
$31.600
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
788.000
|
$15.000
|
$18.000
|
$45.750
|
$63.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
483.000
|
$20.000
|
$45.000
|
$55.130
|
$76.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
10.500
|
$380.000
|
$1,902.000
|
$513.190
|
$2,680.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
1,416.000
|
$20.000
|
$55.000
|
$55.130
|
$70.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
SY
|
1,213.000
|
$1.000
|
$1.050
|
$1.410
|
$3.560
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
3,211.000
|
$0.250
|
$1.050
|
$0.590
|
$0.500
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
3,211.000
|
$0.250
|
$1.050
|
$0.570
|
$0.510
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
5,209.000
|
$2.000
|
$1.050
|
$0.940
|
$3.130
|
|
|
VEGETATIVE WATERING
|
MG
|
54.000
|
$30.000
|
$150.000
|
$87.980
|
$104.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY D)
|
SY
|
3,198.000
|
$3.350
|
$2.000
|
$3.280
|
$5.300
|
|
|
PROOF ROLLING
|
HR
|
50.000
|
$110.000
|
$447.000
|
$117.300
|
$238.000
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
603.000
|
$175.000
|
$162.000
|
$375.360
|
$197.000
|
|
|
PRIME COAT (AE-P)
|
GAL
|
332.000
|
$7.500
|
$16.250
|
$12.900
|
$40.100
|
|
|
CEM STABIL BKFL
|
CY
|
234.000
|
$140.000
|
$265.000
|
$175.950
|
$643.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
220.000
|
$150.000
|
$335.000
|
$233.790
|
$244.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
1,095.000
|
$220.000
|
$369.000
|
$263.120
|
$330.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
330.000
|
$350.000
|
$960.000
|
$321.770
|
$554.000
|
|
|
CL C CONC (ABUT)
|
CY
|
78.000
|
$1,300.000
|
$2,359.000
|
$1,486.570
|
$2,890.000
|
|
|
CL C CONC (CAP)
|
CY
|
13.800
|
$1,900.000
|
$2,228.000
|
$2,548.130
|
$3,760.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
8.300
|
$1,800.000
|
$3,730.000
|
$2,311.580
|
$3,760.000
|
|
|
CL C CONC (RAIL FOUNDATION)
|
CY
|
24.000
|
$600.000
|
$2,575.000
|
$835.550
|
$1,310.000
|
|
|
CL C CONC(PILE ENCASEMENT)
|
LF
|
20.000
|
$1,200.000
|
$1,785.000
|
$2,346.000
|
$1,110.000
|
|
|
CL C CONC(PILE ENCASEMENT)(UNDERWATER)
|
LF
|
40.000
|
$1,200.000
|
$1,575.000
|
$6,451.000
|
$1,110.000
|
|
|
REINF CONC SLAB
|
SF
|
1,560.000
|
$35.000
|
$49.000
|
$30.050
|
$47.800
|
|
|
REINF CONC SLAB (SLAB BEAM)
|
SF
|
3,900.000
|
$20.000
|
$36.240
|
$34.460
|
$47.800
|
|
|
APPROACH SLAB
|
CY
|
135.000
|
$750.000
|
$580.000
|
$794.120
|
$1,340.000
|
|
|
PRESTR CONC SLAB BEAM (5SB12)
|
LF
|
492.420
|
$180.000
|
$244.000
|
$341.140
|
$406.000
|
|
|
PRESTR CONC SLAB BEAM (5SB15)
|
LF
|
247.500
|
$290.000
|
$340.000
|
$341.140
|
$405.000
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
237.690
|
$200.000
|
$279.000
|
$345.920
|
$503.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
492.000
|
$210.000
|
$255.000
|
$260.020
|
$360.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
263.000
|
$225.000
|
$290.000
|
$233.040
|
$414.000
|
|
|
RIPRAP (MOW STRIP)(5 IN)
|
CY
|
101.000
|
$780.000
|
$630.000
|
$643.590
|
$1,000.000
|
|
|
RAIL (TY T223)
|
LF
|
651.000
|
$160.000
|
$195.000
|
$215.760
|
$252.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
162.000
|
$180.000
|
$180.000
|
$117.300
|
$260.000
|
|
|
CMP (GAL STL 12 IN)
|
LF
|
4.000
|
$65.000
|
$1,330.000
|
$58.650
|
$405.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
172.000
|
$150.000
|
$93.000
|
$108.940
|
$213.000
|
|
|
SET (TY II) (12 IN) (CMP) (4: 1) (C)
|
EA
|
2.000
|
$1,500.000
|
$5,000.000
|
$1,524.900
|
$2,670.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
8.000
|
$2,500.000
|
$3,950.000
|
$2,475.030
|
$3,340.000
|
|
|
SET (TY II) (42 IN) (RCP) (4: 1) (C)
|
EA
|
8.000
|
$5,750.000
|
$7,100.000
|
$9,900.120
|
$12,700.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
3.000
|
$35,000.000
|
$36,000.000
|
$35,190.000
|
$61,000.000
|
|
|
REMOV STR (PIPE)
|
EA
|
9.000
|
$1,000.000
|
$480.000
|
$1,368.500
|
$1,010.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$252,369.890
|
$379,000.000
|
$390,000.000
|
$335,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
16.000
|
$5,600.000
|
$7,000.000
|
$9,806.280
|
$6,930.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
150.000
|
$42.050
|
$49.000
|
$27.370
|
$95.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
287.000
|
$55.000
|
$51.000
|
$82.110
|
$97.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
437.000
|
$15.000
|
$20.000
|
$20.530
|
$24.600
|
|
|
BULLDOZER WORK (EROSION & SEDMT CONT)
|
HR
|
40.000
|
$200.000
|
$230.000
|
$234.600
|
$100.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
3,578.000
|
$4.500
|
$3.150
|
$4.690
|
$9.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
3,578.000
|
$2.000
|
$1.050
|
$1.760
|
$2.140
|
|
|
DRIVEWAYS (ACP)
|
SY
|
469.000
|
$55.000
|
$40.500
|
$75.070
|
$175.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,300.000
|
$28.000
|
$27.500
|
$29.330
|
$36.900
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
9.000
|
$2,300.000
|
$1,900.000
|
$2,111.400
|
$2,600.000
|
|
|
MTL BEAM GD FEN TRANS (TL2)
|
EA
|
9.000
|
$1,420.000
|
$1,365.000
|
$1,243.380
|
$1,880.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
1.000
|
$2,140.000
|
$1,470.000
|
$1,700.850
|
$2,160.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
16.000
|
$3,280.000
|
$3,045.000
|
$3,753.600
|
$4,020.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL2)
|
EA
|
3.000
|
$44,000.000
|
$26,775.000
|
$30,110.910
|
$37,600.000
|
|
|
GATE (TY 1)
|
EA
|
1.000
|
$750.000
|
$3,465.000
|
$1,407.600
|
$5,880.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
6.000
|
$315.000
|
$309.750
|
$504.390
|
$640.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
5.000
|
$650.000
|
$735.000
|
$839.870
|
$1,770.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
12.000
|
$110.000
|
$210.000
|
$99.710
|
$275.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
25.000
|
$30.000
|
$26.250
|
$21.110
|
$84.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
80.000
|
$40.000
|
$52.500
|
$32.840
|
$63.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
1,666.000
|
$1.000
|
$2.100
|
$4.690
|
$5.800
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
1,514.000
|
$3.600
|
$2.100
|
$4.690
|
$27.800
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
28.000
|
$6.000
|
$15.750
|
$10.560
|
$27.800
|
|
|
TACK COAT
|
GAL
|
98.000
|
$7.500
|
$44.350
|
$20.810
|
$33.200
|
|
|
D-GR HMA TY-D PG 64-22 (EXEMPT)
|
TON
|
181.000
|
$200.000
|
$275.750
|
$479.190
|
$529.000
|
|
|
THERMOPLASTIC PIPE (PP) (42")
|
LF
|
144.000
|
$210.000
|
$144.000
|
$504.390
|
$278.000
|
|
|
TMA (STATIONARY)
|
DAY
|
360.000
|
$320.000
|
$303.000
|
$504.390
|
$214.000
|
|
Totals: |
$2,807,681.190
|
$3,831,475.490
|
$4,152,670.737
|
$4,665,503.970
|