Show Job Controls
Bid Cobra

HARRIS US 290 (0050-06-108)

Items: 30

County: HARRIS
Length: 0.0000 MILES (0.4034 MILES)
Highway: US 290
District: HOUSTON
Control Number: 0050-06-108
DBE Goal: 0.0%
Project: F 2026(851)
Guaranty: $28,000.00
Time: 80 WORKING DAYS
Engineer's Estimate: $1,357,254.35
Date: 08/05/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263022
Type: DRAINAGE IMPROVEMENTS
Project ID: A00209716
Contract Type: FEDERAL
Project Description: EROSION REPAIR UNDERNEATH EXISTING US 290 MAINLANE AND FRONTAGE ROAD BRIDGES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$1,357,254.35
$1,422,408.75
Over/Under Est: 4.8% $65,154.40
Over/Under Est: 8.94% $121,292.05
Amt Left: 3.95% $56,137.65
$1,597,610.40
Over/Under Est: 17.71% $240,356.05
Amt Left: 12.32% $175,201.65
Delta: -8.05% -$119,064.00
Over/Under Est: 34.06% $462,268.65
Amt Left: 27.92% $397,114.25
Delta: -13.89% -$221,912.60
$1,980,373.00
Over/Under Est: 45.91% $623,118.65
Amt Left: 39.23% $557,964.25
Delta: -8.84% -$160,850.00
Over/Under Est: 85.15% $1,155,692.15
Amt Left: 76.67% $1,090,537.75
Delta: -26.89% -$532,573.50
$2,657,330.20
Over/Under Est: 95.79% $1,300,075.85
Amt Left: 86.82% $1,234,921.45
Delta: -5.75% -$144,383.70

Bid Items & Bid Tabulations

30 Total 0 of 30
HARRIS  |  US 290  |  HOUSTON  |  0050-06-108  |  08/05/2026 1:00 PM CDT  |  $1,357,254.35  |  F 2026(851)  |  DRAINAGE IMPRVS  |  80 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DIGG COMMERCIAL, LLC
GARRET SHIELDS INFRASTRUCTURE
ISI CONTRACTING, INC.
STRUCTURAL INTEGRITY GROUP LLC
JFO SERVICES, LLC
FORDE CONSTRUCTION COMPANY, INC.
MC2 CIVIL, LLC
PREPARING ROW
AC 2.650 $9,811.350 $17,875.000 $5,000.000 $16,500.000 $3,500.000 $20,511.650 $58,000.000 $80,000.000
EXCAV (CHANNEL)
CY 2,900.000 $25.230 $15.000 $30.000 $15.000 $22.750 $79.430 $32.000 $30.000
EMBANK (FNL)(DC)(TY C)
CY 2,900.000 $13.470 $15.000 $40.000 $35.000 $27.250 $73.040 $32.000 $30.000
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 660.000 $99.380 $120.000 $150.000 $152.000 $112.000 $114.870 $190.000 $85.000
RIPRAP (CONC)(4 IN)
CY 166.000 $567.130 $600.000 $600.000 $365.000 $675.000 $656.020 $858.000 $1,000.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 2,240.000 $216.550 $150.000 $200.000 $160.000 $205.000 $196.860 $213.000 $260.000
WINGWALL (PW - 1) (HW=7 FT)
EA 6.000 $19,011.670 $25,344.000 $15,000.000 $10,000.000 $53,500.000 $14,396.570 $78,000.000 $50,000.000
MOBILIZATION
LS 1.000 $125,524.550 $115,000.000 $100,000.000 $100,000.000 $125,000.000 $188,956.140 $248,000.000 $260,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,000.000 $3,000.000 $5,000.000 $6,000.000 $13,275.000 $3,672.960 $19,000.000 $32,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 112.000 $81.350 $300.000 $100.000 $187.000 $50.000 $120.320 $200.000 $70.000
TMA (STATIONARY)
DAY 24.000 $254.170 $2,800.000 $300.000 $3,250.000 $1,375.000 $633.270 $200.000 $750.000
TMA (MOBILE OPERATION)
DAY 20.000 $101.670 $100.000 $300.000 $512.000 $10.000 $633.270 $165.000 $1,700.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 120.000 $64.300 $54.000 $20.000 $38.000 $54.000 $44.330 $85.000 $65.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $10.000 $10.000 $5.000 $16.000 $12.000 $19.000 $20.000 $13.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 224.000 $35.580 $31.000 $20.000 $27.000 $29.000 $31.660 $60.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 224.000 $14.230 $8.000 $5.000 $11.000 $15.500 $12.670 $16.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 700.000 $4.450 $4.000 $5.000 $2.440 $3.000 $2.850 $4.000 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 700.000 $0.760 $1.000 $1.000 $0.810 $1.000 $0.950 $2.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (6")
LF 700.000 $1.020 $20.000 $5.000 $7.580 $5.000 $8.870 $3.000 $6.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 700.000 $1.530 $1.000 $1.000 $2.160 $1.000 $2.530 $1.000 $1.430
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 80.000 $1.500 $20.000 $1.250 $2.160 $23.000 $2.530 $3.000 $2.300
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 80.000 $1.500 $20.000 $1.880 $2.160 $23.000 $2.530 $3.000 $2.300
RE PM TY II (W) 6" (BRK)
LF 30.000 $0.500 $30.000 $2.200 $1.730 $23.000 $2.030 $2.000 $1.850
RE PM TY II (W) 6" (SLD)
LF 80.000 $0.500 $20.000 $1.000 $1.620 $23.000 $1.900 $2.000 $1.700
RE PM TY II (Y) 6" (SLD)
LF 80.000 $1.500 $20.000 $1.000 $1.620 $23.000 $1.900 $2.000 $1.700
REFL PAV MRK TY I (W)6"(BRK)(100MIL)
LF 30.000 $1.500 $25.000 $2.000 $1.950 $23.000 $2.280 $2.000 $2.100
ELIM EXT PM & MRKS (6")
LF 190.000 $1.000 $10.000 $3.000 $0.320 $30.000 $0.380 $0.350 $0.350
PAV SURF PREP FOR MRK (6")
LF 190.000 $0.250 $10.000 $1.000 $0.160 $30.000 $0.190 $0.200 $0.180
BRIDGE JOINT REPLACEMENT (SEJ)
LF 570.000 $302.460 $463.000 $400.000 $850.000 $580.000 $629.460 $615.000 $875.000
REPLACING ELASTOMERIC BEARING PADS
EA 5.000 $11,754.700 $15,000.000 $25,000.000 $15,000.000 $16,000.000 $26,310.610 $36,000.000 $25,000.000
Totals: $1,357,254.348 $1,422,408.750 $1,478,546.400 $1,597,610.400 $1,819,523.000 $1,980,373.002 $2,512,946.500 $2,657,330.200
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $6,900.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,600.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $3,000.00
Total: $11,500.00