Show Job Controls
Bid Cobra

HARRIS SS 261 (0110-06-151)

Items: 30

County: HARRIS
Length: 0.0000 MILES (4.4520 MILES)
Highway: SS 261
District: HOUSTON
Control Number: 0110-06-151
DBE Goal: 0.0%
Project: F 2B26(023)
Guaranty: $26,000.00
Time: 89 WORKING DAYS
Engineer's Estimate: $1,284,248.10
Date: 09/02/2026 1:00 PM CDT (17 days ago) Changed
Contract Number: 9263224
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00140552
Contract Type: FEDERAL
Project Description: FULL DEPTH REPAIR, REPLACE EXISTING ACP PATCHES WITH EPOXY (SPALL REPAIR), DIAMOND GRINDING OUTSIDE LANE, UPGRADE GUARD RAIL, PAVEMENT MARKINGS, AND MEDIAN PAINT
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$1,284,248.10
$1,196,117.63
Over/Under Est: -6.86% -$88,130.47
Over/Under Est: -1.02% -$13,159.33
Amt Left: 6.27% $74,971.14
$1,463,129.62
Over/Under Est: 13.93% $178,881.52
Amt Left: 22.32% $267,011.99
Delta: -15.11% -$192,040.85
$1,499,485.41
Over/Under Est: 16.76% $215,237.31
Amt Left: 25.36% $303,367.78
Delta: -2.48% -$36,355.79
Over/Under Est: 73.44% $943,199.21
Amt Left: 86.22% $1,031,329.68
Delta: -48.55% -$727,961.90
Over/Under Est: 109.49% $1,406,148.55
Amt Left: 124.93% $1,494,279.02
Delta: -20.78% -$462,949.34

Bid Items & Bid Tabulations

30 Total 0 of 30
HARRIS  |  SS 261  |  HOUSTON  |  0110-06-151  |  09/02/2026 1:00 PM CDT  |  $1,284,248.10  |  F 2B26(023)  |  SURF/ROADWAY RESTOR  |  89 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
STRUCTURAL INTEGRITY GROUP LLC
DIGG COMMERCIAL, LLC
MC2 CIVIL, LLC
SELECT MAINTENANCE, L.L.C.
EMERY SAPP & SON'S INC.
FULL - DEPTH REPAIR CRCP (9")
CY 700.000 $854.660 $565.000 $849.000 $900.000 $1,220.000 $1,650.000 $2,050.000
MOBILIZATION
LS 1.000 $116,750.000 $50,000.000 $90,000.000 $125,000.000 $60,000.000 $220,000.000 $400,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $8,000.000 $3,250.000 $1.000 $10,000.000 $4,000.000 $42,000.000 $38,000.000
TMA (STATIONARY)
DAY 75.000 $225.000 $4,150.000 $200.000 $500.000 $500.000 $300.000 $285.000
TMA (MOBILE OPERATION)
DAY 46.000 $267.150 $550.000 $1.000 $1,650.000 $500.000 $300.000 $300.000
RE PM TY II (Y)(CURB)
LF 37,430.000 $2.300 $2.100 $2.880 $3.230 $2.880 $2.880 $2.200
RE PM TY III (W)(6")(SLD)
LF 2,578.000 $0.600 $0.810 $0.850 $0.960 $0.850 $0.850 $0.800
RE PM TY III (W)(6")(BRK)
LF 20,730.000 $0.650 $0.790 $0.850 $0.960 $0.850 $0.850 $1.200
RE PM TY III (W)(6")(DOT)
LF 48.000 $1.500 $3.160 $0.850 $0.960 $0.850 $0.850 $2.300
RE PM TY III (W)(8")(SLD)
LF 9,636.000 $0.900 $1.420 $1.100 $1.240 $1.100 $1.100 $2.350
RE PM TY III (W)(8")(DOT)
LF 1,928.000 $1.100 $1.580 $1.100 $1.240 $1.100 $1.100 $2.500
RE PM TY III (W)(12")(SLD)
LF 112.000 $2.600 $4.210 $5.000 $5.600 $5.000 $5.000 $6.000
RE PM TY III (Y)(6")(SLD)
LF 558.000 $0.600 $1.580 $0.850 $0.960 $0.850 $0.850 $0.900
RE PM TY III (Y)(8")(SLD)
LF 1,011.000 $1.300 $1.420 $1.100 $1.240 $1.100 $1.100 $2.100
RE PM TY III (Y)(12")(SLD)
LF 607.000 $3.100 $3.840 $5.000 $5.600 $5.000 $5.000 $6.000
RE PM TY III (BLK)(6")(SHADOW)
LF 20,730.000 $0.700 $0.950 $0.850 $0.960 $0.850 $0.850 $0.850
PREFAB PM TY C (W)(24")(SLD)
LF 7,769.000 $14.000 $13.680 $15.000 $16.800 $15.000 $15.000 $20.000
PREFAB PM TY C (W)(ARROW)
EA 101.000 $195.000 $231.450 $195.000 $218.400 $195.000 $195.000 $300.000
PREFAB PM TY C (W)(DBL ARROW)
EA 2.000 $330.000 $341.910 $225.000 $252.000 $225.000 $225.000 $540.000
PREFAB PM TY C (W)(WORD)
EA 101.000 $254.160 $299.830 $195.000 $218.400 $195.000 $195.000 $360.000
REFL PAV MRKR TY II-C-R
EA 1,771.000 $4.330 $6.310 $5.000 $5.600 $5.000 $5.000 $7.200
PAV SURF PREP FOR MRK (6")
LF 31,698.000 $0.020 $0.050 $0.010 $0.020 $0.010 $0.010 $0.100
PAV SURF PREP FOR MRK (8")
LF 9,751.000 $0.060 $0.080 $0.030 $0.040 $0.030 $0.030 $0.150
PAV SURF PREP FOR MRK (12")
LF 395.000 $0.170 $0.260 $0.100 $0.120 $0.100 $0.100 $0.600
PAV SURF PREP FOR MRK (24")
LF 5,084.000 $0.500 $0.530 $0.150 $0.170 $0.150 $0.150 $1.200
PAV SURF PREP FOR MRK (ARROW)
EA 101.000 $6.500 $15.780 $10.000 $11.200 $10.000 $10.000 $12.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 2.000 $12.000 $26.300 $10.000 $11.200 $10.000 $10.000 $24.000
PAV SURF PREP FOR MRK (WORD)
EA 101.000 $11.000 $18.940 $10.000 $11.200 $10.000 $10.000 $12.000
SPALLING REPAIR (POLYMERIC) (SEMIRIGID)
GAL 286.000 $72.690 $25.000 $345.000 $120.000 $100.000 $300.000 $307.000
CONTINUOUS GRINDING-CONCRETE PAVEMENT
SY 17,034.000 $10.150 $4.000 $8.290 $7.500 $8.250 $8.600 $5.500
Totals: $1,284,248.100 $1,196,117.630 $1,271,088.770 $1,463,129.620 $1,499,485.410 $2,227,447.310 $2,690,396.650
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $6,500.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $2,500.00
Total: $11,000.00