PREPARING ROW
|
STA
|
33.500
|
$10,000.000
|
$7,000.000
|
$9,000.000
|
$5,000.000
|
$12,200.000
|
$10,000.000
|
$4,300.000
|
$7,500.000
|
$35,000.000
|
$20,000.000
|
|
|
REMOVING CONC (PAV)
|
SY
|
19,273.000
|
$5.500
|
$1.660
|
$6.000
|
$5.100
|
$2.050
|
$5.000
|
$3.000
|
$2.180
|
$5.000
|
$5.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
1,435.000
|
$6.000
|
$1.520
|
$6.000
|
$9.000
|
$4.900
|
$5.000
|
$6.000
|
$2.180
|
$5.000
|
$5.000
|
|
|
REMOVING CONC (CURB)
|
LF
|
6,102.000
|
$2.250
|
$0.820
|
$3.000
|
$0.300
|
$1.000
|
$1.000
|
$1.000
|
$0.500
|
$3.000
|
$2.000
|
|
|
REMOVING CONC (MISC)
|
SY
|
611.000
|
$7.000
|
$2.180
|
$8.000
|
$18.400
|
$10.000
|
$3.000
|
$2.000
|
$2.180
|
$3.000
|
$10.000
|
|
|
REMOVING STAB BASE & ASPH PAV (8"-10")
|
SY
|
4,476.000
|
$5.400
|
$1.620
|
$4.000
|
$4.300
|
$4.650
|
$4.000
|
$5.000
|
$1.620
|
$5.000
|
$10.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
2,508.000
|
$9.000
|
$8.540
|
$8.000
|
$18.500
|
$21.000
|
$4.000
|
$26.000
|
$10.000
|
$8.000
|
$10.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
15,481.000
|
$6.400
|
$8.990
|
$25.000
|
$21.100
|
$15.250
|
$15.000
|
$24.000
|
$0.500
|
$9.000
|
$30.000
|
|
|
EMBANK(FINAL)(DC)(TY E)(CSBE)
|
CY
|
3,649.000
|
$36.000
|
$50.000
|
$60.000
|
$51.000
|
$49.700
|
$45.000
|
$45.000
|
$5.000
|
$40.000
|
$45.000
|
|
|
BLOCK SODDING
|
SY
|
8,108.000
|
$2.800
|
$2.800
|
$3.250
|
$4.900
|
$4.200
|
$2.800
|
$3.000
|
$3.280
|
$3.800
|
$4.000
|
|
|
STRAW OR HAY MULCH
|
SY
|
28,033.000
|
$0.240
|
$0.240
|
$0.140
|
$0.300
|
$0.300
|
$0.250
|
$0.300
|
$0.200
|
$0.500
|
$0.200
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
12,060.000
|
$0.210
|
$0.160
|
$0.130
|
$0.300
|
$0.250
|
$0.160
|
$0.200
|
$0.350
|
$0.350
|
$0.200
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
12,060.000
|
$0.750
|
$0.160
|
$0.130
|
$0.300
|
$0.200
|
$0.160
|
$0.200
|
$0.350
|
$0.350
|
$0.200
|
|
|
DRILL SEEDING (PERM) (URBAN) (CLAY)
|
SY
|
3,913.000
|
$0.180
|
$0.440
|
$0.200
|
$0.300
|
$0.250
|
$0.440
|
$0.500
|
$0.900
|
$0.850
|
$0.250
|
|
|
FERTILIZER
|
AC
|
7.500
|
$775.000
|
$1,147.500
|
$700.000
|
$763.800
|
$1,400.000
|
$1,150.000
|
$1,300.000
|
$635.000
|
$1,300.000
|
$1,000.000
|
|
|
VEGETATIVE WATERING
|
MG
|
895.600
|
$20.000
|
$20.890
|
$9.000
|
$32.300
|
$32.500
|
$19.000
|
$25.000
|
$30.000
|
$30.000
|
$30.000
|
|
|
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
|
TON
|
518.000
|
$165.000
|
$172.470
|
$152.000
|
$169.500
|
$168.000
|
$160.000
|
$160.000
|
$165.000
|
$180.000
|
$175.000
|
|
|
LIME TRT (EXST MATL)(8")
|
SY
|
24,859.000
|
$3.500
|
$9.750
|
$4.000
|
$4.400
|
$2.650
|
$5.000
|
$4.500
|
$5.000
|
$5.000
|
$5.000
|
|
|
SALV, HAUL & STKPL RCL APH PV (3")
|
SY
|
17,056.000
|
$2.500
|
$0.930
|
$5.000
|
$4.200
|
$2.150
|
$3.000
|
$4.000
|
$0.930
|
$10.000
|
$5.000
|
|
|
CONC PAV (JOINT REINF) (10")
|
SY
|
20,877.000
|
$65.000
|
$56.000
|
$62.000
|
$53.000
|
$61.800
|
$60.000
|
$60.000
|
$60.000
|
$62.000
|
$70.000
|
|
|
CONC PVMT (JOINTED-CPCD)(HES)(10")
|
SY
|
358.000
|
$105.000
|
$79.330
|
$95.000
|
$70.200
|
$89.000
|
$90.000
|
$90.000
|
$80.000
|
$85.000
|
$70.000
|
|
|
CEM STABIL BKFL
|
CY
|
3,488.000
|
$46.500
|
$39.320
|
$38.500
|
$56.500
|
$48.500
|
$45.000
|
$47.000
|
$40.000
|
$45.000
|
$100.000
|
|
|
CEMENT STAB BACKFILL (INLET OR MH)
|
CY
|
179.000
|
$41.500
|
$39.320
|
$38.500
|
$43.900
|
$48.500
|
$45.000
|
$38.000
|
$40.000
|
$45.000
|
$100.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
4,919.000
|
$2.150
|
$1.130
|
$1.000
|
$0.100
|
$2.000
|
$3.000
|
$3.000
|
$0.500
|
$1.000
|
$5.000
|
|
|
DRILL SHAFT (24 IN)
|
LF
|
1,350.000
|
$156.000
|
$70.000
|
$80.000
|
$52.600
|
$82.000
|
$50.000
|
$75.000
|
$55.000
|
$155.000
|
$100.000
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
1,008.000
|
$235.000
|
$175.000
|
$180.000
|
$150.000
|
$176.000
|
$220.000
|
$150.000
|
$175.000
|
$200.000
|
$225.000
|
|
|
DRILL SHAFT (48 IN)
|
LF
|
4,445.000
|
$220.000
|
$230.000
|
$220.000
|
$200.000
|
$222.000
|
$290.000
|
$240.000
|
$250.000
|
$300.000
|
$275.000
|
|
|
CL C CONC (ABUT)
|
CY
|
86.800
|
$1,005.000
|
$780.000
|
$950.000
|
$870.300
|
$881.000
|
$850.000
|
$1,200.000
|
$1,000.000
|
$800.000
|
$1,170.000
|
|
|
CL C CONC (BENT)
|
CY
|
693.300
|
$1,140.000
|
$720.000
|
$950.000
|
$950.000
|
$765.000
|
$850.000
|
$650.000
|
$900.000
|
$975.000
|
$1,170.000
|
|
|
CL C CONC (CAP)
|
CY
|
218.400
|
$720.000
|
$320.000
|
$320.000
|
$441.600
|
$456.000
|
$600.000
|
$400.000
|
$250.000
|
$1,000.000
|
$800.000
|
|
|
REINF CONC SLAB
|
SF
|
82,140.000
|
$15.000
|
$16.000
|
$12.000
|
$18.500
|
$16.300
|
$13.000
|
$17.000
|
$17.500
|
$13.500
|
$15.000
|
|
|
BRIDGE MEDIAN
|
SF
|
6,660.000
|
$10.000
|
$6.000
|
$13.000
|
$7.800
|
$9.600
|
$8.000
|
$6.000
|
$10.000
|
$9.000
|
$15.000
|
|
|
BRIDGE SIDEWALK
|
SF
|
15,540.000
|
$10.000
|
$7.500
|
$10.000
|
$8.800
|
$9.800
|
$5.000
|
$4.500
|
$10.000
|
$8.500
|
$15.000
|
|
|
RETAINING WALL (MSE)
|
SF
|
10,362.000
|
$55.000
|
$43.000
|
$55.000
|
$31.900
|
$53.500
|
$45.000
|
$36.000
|
$65.000
|
$35.000
|
$45.000
|
|
|
RETAINING WALL (TEMP WALL)
|
SF
|
3,872.000
|
$15.000
|
$9.350
|
$16.000
|
$13.700
|
$26.000
|
$15.000
|
$20.000
|
$10.000
|
$12.000
|
$25.000
|
|
|
PRESTR CONC GIRDER (TX62)
|
LF
|
11,342.450
|
$130.000
|
$155.000
|
$140.000
|
$153.200
|
$149.000
|
$175.000
|
$160.000
|
$152.500
|
$155.000
|
$165.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
24.000
|
$445.000
|
$519.440
|
$400.000
|
$359.600
|
$448.000
|
$800.000
|
$450.000
|
$500.000
|
$325.000
|
$500.000
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
3.710
|
$420.000
|
$883.520
|
$550.000
|
$752.600
|
$770.000
|
$800.000
|
$750.000
|
$500.000
|
$450.000
|
$500.000
|
|
|
RIPRAP (CONC)(6 IN)
|
CY
|
65.000
|
$432.250
|
$362.990
|
$450.000
|
$506.800
|
$453.000
|
$800.000
|
$550.000
|
$600.000
|
$375.000
|
$550.000
|
|
|
RIPRAP CONC (8 IN)
|
CY
|
1.200
|
$452.000
|
$601.830
|
$650.000
|
$977.900
|
$770.000
|
$800.000
|
$430.000
|
$500.000
|
$550.000
|
$600.000
|
|
|
STR STEEL (MISC NON - BRIDGE)
|
LB
|
3,795.000
|
$10.000
|
$6.770
|
$13.000
|
$14.600
|
$7.500
|
$9.000
|
$15.000
|
$17.720
|
$10.000
|
$10.000
|
|
|
RAIL (TY C221)
|
LF
|
3,400.000
|
$65.000
|
$51.000
|
$65.000
|
$82.700
|
$94.000
|
$60.000
|
$72.000
|
$120.000
|
$95.000
|
$120.000
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
|
LF
|
320.000
|
$90.000
|
$73.310
|
$80.000
|
$67.600
|
$95.000
|
$75.000
|
$80.000
|
$110.000
|
$100.000
|
$100.000
|
|
|
CONC BOX CULV (5 FT X 3 FT)
|
LF
|
1,235.000
|
$180.000
|
$220.000
|
$170.000
|
$155.000
|
$187.000
|
$205.000
|
$192.000
|
$275.000
|
$200.000
|
$225.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
1,039.000
|
$52.000
|
$60.000
|
$40.000
|
$48.300
|
$50.000
|
$50.000
|
$48.000
|
$80.000
|
$40.000
|
$50.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
1,034.000
|
$54.000
|
$65.000
|
$50.000
|
$51.200
|
$59.000
|
$55.000
|
$50.000
|
$90.000
|
$45.000
|
$60.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
362.000
|
$74.600
|
$70.000
|
$55.000
|
$78.500
|
$80.000
|
$60.000
|
$91.000
|
$105.000
|
$60.000
|
$70.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
322.000
|
$81.000
|
$80.000
|
$70.000
|
$96.300
|
$87.000
|
$75.000
|
$95.000
|
$140.000
|
$72.000
|
$90.000
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
373.000
|
$105.000
|
$90.000
|
$80.000
|
$104.600
|
$116.000
|
$85.000
|
$134.000
|
$145.000
|
$95.000
|
$120.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
554.000
|
$125.000
|
$130.000
|
$95.000
|
$125.900
|
$131.000
|
$100.000
|
$112.000
|
$175.000
|
$105.000
|
$180.000
|
|
|
INLET (COMPL)(TY AAD)
|
EA
|
4.000
|
$4,250.000
|
$5,001.610
|
$4,000.000
|
$2,974.800
|
$3,935.000
|
$4,000.000
|
$3,700.000
|
$4,500.000
|
$3,850.000
|
$5,000.000
|
|
|
INLET (COMPL)(TY AD)
|
EA
|
17.000
|
$3,280.000
|
$3,674.050
|
$3,000.000
|
$2,294.700
|
$2,365.000
|
$3,000.000
|
$2,900.000
|
$3,500.000
|
$2,550.000
|
$5,000.000
|
|
|
MANH (COMPL)(TY A)
|
EA
|
11.000
|
$3,100.000
|
$5,116.610
|
$4,000.000
|
$3,748.600
|
$3,435.000
|
$4,000.000
|
$6,300.000
|
$5,000.000
|
$4,200.000
|
$5,000.000
|
|
|
INLET (COMPL)(CURB)(TY C)
|
EA
|
9.000
|
$3,165.000
|
$2,720.930
|
$3,000.000
|
$2,728.400
|
$2,290.000
|
$3,000.000
|
$5,000.000
|
$4,000.000
|
$2,200.000
|
$5,000.000
|
|
|
INLET (COMPL)(CURB)(TY C1)
|
EA
|
13.000
|
$4,600.000
|
$2,874.110
|
$3,500.000
|
$2,803.100
|
$2,800.000
|
$4,000.000
|
$3,800.000
|
$4,500.000
|
$3,150.000
|
$5,000.000
|
|
|
INLET (COMPL)(EXT TY C)
|
EA
|
8.000
|
$1,150.000
|
$2,193.320
|
$1,500.000
|
$845.700
|
$1,860.000
|
$1,000.000
|
$800.000
|
$700.000
|
$600.000
|
$2,000.000
|
|
|
SET (TY I)(S= 5 FT)(HW= 3 FT)(3:1) (C)
|
EA
|
1.000
|
$6,800.000
|
$10,089.640
|
$5,000.000
|
$3,462.100
|
$3,075.000
|
$4,000.000
|
$5,700.000
|
$5,000.000
|
$6,500.000
|
$3,000.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$4,150.000
|
$3,626.300
|
$4,000.000
|
$3,740.800
|
$3,350.000
|
$4,000.000
|
$4,500.000
|
$4,000.000
|
$3,800.000
|
$4,000.000
|
|
|
GRATE AND FRAME (BRIDGE DRAIN)
|
EA
|
20.000
|
$4,000.000
|
$1,824.300
|
$3,500.000
|
$2,076.700
|
$1,250.000
|
$3,500.000
|
$2,200.000
|
$2,250.000
|
$1,250.000
|
$2,500.000
|
|
|
PIPE (PVC) (SCH 40) (8 IN)
|
LF
|
510.000
|
$50.000
|
$35.470
|
$25.000
|
$44.200
|
$58.000
|
$75.000
|
$140.000
|
$75.000
|
$15.000
|
$20.000
|
|
|
REMOV STR (INLET)
|
EA
|
4.000
|
$375.000
|
$863.410
|
$500.000
|
$429.300
|
$400.000
|
$500.000
|
$600.000
|
$1,100.000
|
$450.000
|
$500.000
|
|
|
REMOV STR (SET)
|
EA
|
2.000
|
$550.000
|
$863.410
|
$600.000
|
$591.000
|
$350.000
|
$500.000
|
$530.000
|
$1,100.000
|
$250.000
|
$500.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
2.000
|
$1,210.000
|
$2,210.640
|
$700.000
|
$591.000
|
$500.000
|
$2,500.000
|
$800.000
|
$1,100.000
|
$1,250.000
|
$500.000
|
|
|
REMOV STR (PIPE)
|
LF
|
627.000
|
$35.000
|
$24.840
|
$14.000
|
$21.500
|
$15.000
|
$20.000
|
$26.000
|
$30.000
|
$10.000
|
$5.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
98.000
|
$42.500
|
$39.740
|
$50.000
|
$34.100
|
$20.000
|
$50.000
|
$143.000
|
$85.000
|
$30.000
|
$5.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$715,000.000
|
$1,100,000.000
|
$1,100,000.000
|
$1,100,000.000
|
$1,150,000.000
|
$1,200,000.000
|
$1,100,000.000
|
$1,250,000.000
|
$1,200,000.000
|
$1,400,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
22.000
|
$6,800.000
|
$3,581.200
|
$3,500.000
|
$6,986.500
|
$2,000.000
|
$3,500.000
|
$6,000.000
|
$9,500.000
|
$2,850.000
|
$5,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
480.000
|
$34.500
|
$20.110
|
$22.000
|
$33.500
|
$28.000
|
$26.000
|
$23.000
|
$22.330
|
$35.000
|
$25.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
480.000
|
$10.500
|
$9.450
|
$10.000
|
$8.900
|
$11.000
|
$10.000
|
$10.000
|
$6.000
|
$10.000
|
$10.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
296.000
|
$30.500
|
$30.540
|
$32.000
|
$32.600
|
$15.000
|
$45.000
|
$33.000
|
$25.660
|
$30.000
|
$40.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
296.000
|
$11.000
|
$7.270
|
$8.000
|
$7.300
|
$15.000
|
$5.000
|
$8.000
|
$8.500
|
$8.000
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
14,278.000
|
$2.350
|
$1.600
|
$2.000
|
$2.200
|
$2.250
|
$2.000
|
$2.000
|
$2.000
|
$4.000
|
$2.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
14,278.000
|
$0.750
|
$0.550
|
$0.550
|
$1.100
|
$0.550
|
$0.400
|
$0.600
|
$0.380
|
$1.000
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
1,052.000
|
$4.950
|
$3.060
|
$3.500
|
$5.000
|
$3.900
|
$3.500
|
$3.400
|
$3.600
|
$7.000
|
$5.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
756.000
|
$7.250
|
$1.090
|
$1.500
|
$7.800
|
$4.400
|
$5.000
|
$1.200
|
$4.600
|
$8.000
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,808.000
|
$1.050
|
$0.380
|
$0.500
|
$1.600
|
$0.850
|
$0.400
|
$0.420
|
$0.650
|
$1.000
|
$1.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
3,820.000
|
$98.000
|
$12.400
|
$25.000
|
$59.200
|
$15.000
|
$40.000
|
$22.000
|
$12.000
|
$60.000
|
$35.000
|
|
|
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
|
LF
|
1,900.000
|
$35.000
|
$28.000
|
$40.000
|
$50.800
|
$14.150
|
$60.000
|
$65.000
|
$60.000
|
$55.000
|
$65.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
8,595.000
|
$29.500
|
$20.000
|
$40.000
|
$18.500
|
$16.750
|
$20.000
|
$67.000
|
$60.000
|
$55.000
|
$65.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
660.000
|
$25.000
|
$46.000
|
$40.000
|
$17.300
|
$18.100
|
$35.000
|
$92.000
|
$60.000
|
$55.000
|
$65.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
1,980.000
|
$3.900
|
$9.620
|
$6.000
|
$7.000
|
$5.400
|
$15.000
|
$15.000
|
$10.000
|
$10.000
|
$10.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
80.000
|
$13.100
|
$14.320
|
$11.000
|
$7.000
|
$9.000
|
$15.000
|
$20.000
|
$10.000
|
$10.000
|
$10.000
|
|
|
PORT CTB (REMOVE)(SGL SLP)(TY 1)
|
LF
|
1,900.000
|
$12.200
|
$8.000
|
$8.000
|
$9.200
|
$7.600
|
$15.000
|
$10.000
|
$7.000
|
$15.000
|
$10.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
8,595.000
|
$9.250
|
$7.000
|
$8.000
|
$9.200
|
$7.000
|
$15.000
|
$7.200
|
$5.000
|
$15.000
|
$10.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
660.000
|
$12.600
|
$9.360
|
$8.000
|
$10.200
|
$8.250
|
$15.000
|
$16.000
|
$5.000
|
$15.000
|
$10.000
|
|
|
CONC CURB (DOWEL)
|
LF
|
13,695.000
|
$9.300
|
$6.400
|
$4.000
|
$6.300
|
$10.000
|
$5.000
|
$8.000
|
$4.000
|
$7.000
|
$10.000
|
|
|
CONC CURB & GUTTER (ARMOR CURB)
|
LF
|
10.000
|
$105.000
|
$111.860
|
$250.000
|
$55.800
|
$240.000
|
$200.000
|
$270.000
|
$20.000
|
$20.000
|
$10.000
|
|
|
DRIVEWAYS (CONC) (FAST TRACK)
|
SY
|
928.000
|
$74.000
|
$57.730
|
$90.000
|
$62.500
|
$87.000
|
$75.000
|
$88.000
|
$95.000
|
$75.000
|
$100.000
|
|
|
CONC MEDIAN
|
SY
|
1,364.000
|
$85.000
|
$55.070
|
$60.000
|
$52.700
|
$55.000
|
$40.000
|
$70.000
|
$70.000
|
$40.000
|
$50.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
98.000
|
$3.850
|
$5.000
|
$2.000
|
$5.400
|
$5.600
|
$5.000
|
$3.000
|
$5.000
|
$10.000
|
$5.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
2.000
|
$157.000
|
$350.000
|
$1,850.000
|
$270.400
|
$390.000
|
$350.000
|
$100.000
|
$350.000
|
$300.000
|
$250.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$185.000
|
$350.000
|
$400.000
|
$270.400
|
$390.000
|
$350.000
|
$380.000
|
$350.000
|
$1,500.000
|
$300.000
|
|
|
CHAIN LINK FENCE (INSTALL) (8')
|
LF
|
280.000
|
$75.000
|
$106.430
|
$61.000
|
$55.800
|
$75.000
|
$25.000
|
$52.000
|
$59.460
|
$20.000
|
$100.000
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
145.250
|
$40.500
|
$27.000
|
$11.000
|
$32.300
|
$30.250
|
$16.000
|
$18.000
|
$27.000
|
$30.000
|
$20.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
18.000
|
$430.000
|
$315.000
|
$11.000
|
$568.700
|
$350.000
|
$300.000
|
$450.000
|
$315.000
|
$550.000
|
$500.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
|
EA
|
2.000
|
$1,162.000
|
$1,150.000
|
$33.000
|
$747.100
|
$1,290.000
|
$520.000
|
$600.000
|
$1,150.000
|
$680.000
|
$750.000
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
|
EA
|
2.000
|
$1,850.000
|
$1,560.000
|
$544.000
|
$2,564.500
|
$2,800.000
|
$2,500.000
|
$3,000.000
|
$1,550.000
|
$2,500.000
|
$3,000.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(BRK)
|
LF
|
2,008.000
|
$0.740
|
$0.600
|
$0.650
|
$0.700
|
$0.750
|
$0.700
|
$0.700
|
$0.650
|
$1.000
|
$0.750
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
34,748.000
|
$0.660
|
$0.550
|
$0.550
|
$0.600
|
$0.600
|
$0.650
|
$0.650
|
$0.550
|
$1.000
|
$0.750
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
80.000
|
$11.950
|
$3.000
|
$3.000
|
$7.500
|
$3.350
|
$4.000
|
$3.300
|
$3.000
|
$7.000
|
$4.000
|
|
|
WK ZN PAV MRK REMOV (W)(ARROW)
|
EA
|
7.000
|
$170.000
|
$85.000
|
$60.000
|
$99.200
|
$67.000
|
$100.000
|
$95.000
|
$60.000
|
$105.000
|
$100.000
|
|
|
WK ZN PAV MRK REMOV (W)(DBL ARROW)
|
EA
|
1.000
|
$268.000
|
$100.000
|
$80.000
|
$133.800
|
$90.000
|
$125.000
|
$115.000
|
$80.000
|
$150.000
|
$150.000
|
|
|
WK ZN PAV MRK REMOV (W)(WORD)
|
EA
|
2.000
|
$168.000
|
$100.000
|
$60.000
|
$122.700
|
$67.000
|
$120.000
|
$110.000
|
$60.000
|
$185.000
|
$150.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(BRK)
|
LF
|
714.000
|
$0.750
|
$0.700
|
$0.650
|
$0.700
|
$0.750
|
$0.800
|
$0.800
|
$0.650
|
$1.200
|
$1.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
21,731.000
|
$0.690
|
$0.550
|
$0.550
|
$0.600
|
$0.600
|
$0.600
|
$0.600
|
$0.550
|
$1.000
|
$0.750
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
741.000
|
$4.960
|
$4.500
|
$6.000
|
$5.900
|
$6.700
|
$4.500
|
$5.000
|
$6.000
|
$6.000
|
$5.000
|
|
REFL PAV MRK TY I (W)(ARROW)(100MIL)
|
EA
|
10.000
|
$96.000
|
$125.000
|
$100.000
|
$133.800
|
$112.000
|
$125.000
|
$130.000
|
$100.000
|
$135.000
|
$150.000
|
|
REFL PAV MRK TY I (W)(WORD)(100MIL)
|
EA
|
2.000
|
$115.000
|
$150.000
|
$125.000
|
$200.700
|
$140.000
|
$150.000
|
$167.000
|
$125.000
|
$195.000
|
$200.000
|
|
|
PAVEMENT SEALER 4"
|
LF
|
3,572.000
|
$0.150
|
$0.150
|
$0.100
|
$0.100
|
$0.100
|
$0.150
|
$0.170
|
$0.100
|
$0.100
|
$0.250
|
|
|
PAVEMENT SEALER 24"
|
LF
|
741.000
|
$0.970
|
$1.750
|
$0.500
|
$0.700
|
$0.550
|
$1.800
|
$2.000
|
$0.500
|
$0.750
|
$2.000
|
|
|
PAVEMENT SEALER (ARROW)
|
EA
|
10.000
|
$24.000
|
$25.000
|
$10.000
|
$52.400
|
$11.000
|
$25.000
|
$28.000
|
$10.000
|
$55.000
|
$50.000
|
|
|
PAVEMENT SEALER (WORD)
|
EA
|
2.000
|
$39.000
|
$25.000
|
$10.000
|
$52.400
|
$11.000
|
$25.000
|
$28.000
|
$10.000
|
$55.000
|
$50.000
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
1,480.000
|
$0.830
|
$1.000
|
$0.400
|
$0.900
|
$0.450
|
$1.000
|
$1.100
|
$0.400
|
$1.000
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
2,092.000
|
$0.310
|
$1.000
|
$0.400
|
$0.900
|
$0.450
|
$1.000
|
$1.100
|
$0.400
|
$1.000
|
$1.000
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
83.000
|
$3.500
|
$4.000
|
$4.000
|
$4.500
|
$4.500
|
$4.000
|
$4.400
|
$4.000
|
$5.000
|
$5.000
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
3,572.000
|
$0.030
|
$0.010
|
$0.040
|
$0.100
|
$0.050
|
$0.010
|
$0.020
|
$0.040
|
$0.050
|
$0.100
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
741.000
|
$0.900
|
$0.010
|
$0.250
|
$0.100
|
$0.300
|
$0.010
|
$0.050
|
$0.250
|
$0.250
|
$0.100
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
10.000
|
$14.000
|
$2.500
|
$10.000
|
$8.800
|
$11.200
|
$2.500
|
$3.000
|
$10.000
|
$10.000
|
$5.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
2.000
|
$17.000
|
$2.500
|
$10.000
|
$8.800
|
$11.200
|
$2.500
|
$3.000
|
$10.000
|
$10.000
|
$5.000
|
|
|
WIDE FLANGE PAVEMENT TERMINALS
|
LF
|
144.000
|
$214.000
|
$546.230
|
$400.000
|
$530.000
|
$334.000
|
$600.000
|
$400.000
|
$125.000
|
$200.000
|
$300.000
|
|
Totals: |
$12,019,165.135
|
$11,194,639.229
|
$11,716,805.250
|
$11,799,794.901
|
$11,845,430.462
|
$12,276,459.950
|
$12,371,163.790
|
$12,651,273.015
|
$13,674,581.800
|
$14,937,894.650
|