HARRISON SH 43 (0208-01-026)
Items: 84
County: HARRISON
Length: 2.6380 MILES
Highway: SH 43
District: ATLANTA
Control Number: 0208-01-026
DBE Goal: 0.0%
Project: F 2026(875)
Guaranty: $70,000.00
Time: 65 WORKING DAYS
Engineer's Estimate: $3,307,700.41
Date: 08/06/2026 1:00 PM CDT (6 weeks ago)
Contract Number: 8263222
Type: RESURFACE ROADWAY
Project ID: A00196275
Contract Type: FEDERAL
Project Description: RESURFACE EXISTING 4-LANE ROADWAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JACOB VISE
RYAN GRIFFIN
HARRISON SH 43 (0208-01-026)
Project Name: N/A
Project: F 2026(875)
Engineer's Estimate: $3,307,700.41
Length: 2.6380 MILES
Project Class: OVERLAY
Limits From: US 59
Limits To: SL 390
Project Description: RESURFACE EXISTING 4-LANE ROADWAY
Bidders (5)
E
Engineer's Estimate
$3,307,700.41
1
Awarded
$3,320,427.62
Over/Under Est:
0.38%
$12,727.21
$3,390,830.98
Over/Under Est:
2.51%
$83,130.57
Amt Left:
2.12%
$70,403.36
$3,442,164.84
Over/Under Est:
4.07%
$134,464.43
Amt Left:
3.67%
$121,737.22
Delta:
-1.51%
-$51,333.86
$4,052,653.69
Over/Under Est:
22.52%
$744,953.28
Amt Left:
22.05%
$732,226.07
Delta:
-17.74%
-$610,488.85
$4,232,999.00
Over/Under Est:
27.97%
$925,298.59
Amt Left:
27.48%
$912,571.38
Delta:
-4.45%
-$180,345.31
Bid Items & Bid Tabulations
84
Total
0 of 84
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $34,498.67 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $17,249.33 |
| Total: | $51,748.00 |