HARRISON CS (0919-03-062)
Items: 47
County: HARRISON
Length: N/A
Highway: CS
District: ATLANTA
Control Number: 0919-03-062
DBE Goal: N/A
Project: STP 2020(163)TAPS
Guaranty: N/A
Time: 176 WORKING DAYS
Engineer's Estimate: $546,582.00
Date: 05/06/2021 (5 years ago)
Contract Number: N/A
Type: CONSTRUCT SIDEWALKS AND CURB RAMPS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Pay Estimates:
Documents
1 files available
Bidders (6)
E
Engineer's Estimate
$546,582.00
1
$477,174.00
Over/Under Est:
-12.7%
-$69,408.00
$537,938.00
Over/Under Est:
-1.58%
-$8,644.00
Amt Left:
12.73%
$60,764.00
$579,967.50
Over/Under Est:
6.11%
$33,385.50
Amt Left:
21.54%
$102,793.50
Delta:
-7.81%
-$42,029.50
$589,393.10
Over/Under Est:
7.83%
$42,811.10
Amt Left:
23.52%
$112,219.10
Delta:
-1.63%
-$9,425.60
$613,656.40
Over/Under Est:
12.27%
$67,074.40
Amt Left:
28.6%
$136,482.40
Delta:
-4.12%
-$24,263.30
$1,092,025.70
Over/Under Est:
99.79%
$545,443.70
Amt Left:
128.85%
$614,851.70
Delta:
-77.95%
-$478,369.30
Bid Items & Bid Tabulations
47
Total
0 of 47
