PREPARING ROW
|
STA
|
64.130
|
$2,000.000
|
$4,200.000
|
$3,000.000
|
$4,200.000
|
|
|
REMOVING STAB BASE & ASPH PAV (9")
|
SY
|
66,489.000
|
$6.500
|
$6.250
|
$6.500
|
$7.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
87.000
|
$25.000
|
$40.000
|
$40.000
|
$40.000
|
|
|
BACKFILL (TY A)
|
STA
|
136.600
|
$300.000
|
$210.000
|
$375.000
|
$210.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
SY
|
29,070.000
|
$0.200
|
$0.120
|
$0.140
|
$0.120
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
14,536.000
|
$0.200
|
$0.100
|
$0.100
|
$1.100
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
14,536.000
|
$0.200
|
$0.070
|
$0.100
|
$0.750
|
|
|
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
|
SY
|
14,535.000
|
$0.650
|
$0.800
|
$0.750
|
$0.900
|
|
|
VEGETATIVE WATERING
|
MG
|
930.000
|
$10.000
|
$10.000
|
$8.000
|
$2.000
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
400.000
|
$1.750
|
$1.620
|
$1.650
|
$1.800
|
|
|
CEM TRT(PLNT MX)(CL M)(TY A)(GR1-2)(8")
|
SY
|
64,133.000
|
$15.000
|
$32.000
|
$35.000
|
$32.000
|
|
|
PRIME COAT & BLOTTER (MC-30)
|
GAL
|
16,033.000
|
$5.000
|
$4.200
|
$5.000
|
$4.200
|
|
|
ASPH (TIER II)
|
GAL
|
22,447.000
|
$4.000
|
$4.100
|
$4.500
|
$4.100
|
|
|
AGGR(TY-PB GR-3 SAC-B)
|
CY
|
582.000
|
$110.000
|
$170.000
|
$175.000
|
$170.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
88.000
|
$450.000
|
$510.000
|
$450.000
|
$510.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
60.000
|
$40.000
|
$60.000
|
$50.000
|
$60.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
16.000
|
$530.000
|
$690.000
|
$700.000
|
$690.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$415,000.000
|
$481,000.000
|
$400,000.000
|
$580,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
4.000
|
$10,000.000
|
$5,000.000
|
$15,000.000
|
$16,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
130.000
|
$45.000
|
$55.000
|
$50.000
|
$60.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
130.000
|
$10.000
|
$11.000
|
$11.000
|
$12.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,360.000
|
$2.750
|
$2.350
|
$2.750
|
$2.600
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,360.000
|
$1.000
|
$0.900
|
$0.750
|
$1.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
56.000
|
$100.000
|
$120.000
|
$140.000
|
$120.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,168.000
|
$50.000
|
$43.000
|
$40.000
|
$48.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
26,516.000
|
$0.200
|
$0.290
|
$0.250
|
$0.250
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
700.000
|
$22.000
|
$21.000
|
$23.000
|
$20.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
525.000
|
$4.500
|
$2.000
|
$2.200
|
$4.400
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
2.000
|
$250.000
|
$200.000
|
$220.000
|
$440.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,700.000
|
$2,500.000
|
$2,750.000
|
$2,900.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
2.000
|
$300.000
|
$200.000
|
$220.000
|
$330.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
1.000
|
$300.000
|
$350.000
|
$385.000
|
$380.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
2.000
|
$610.000
|
$710.000
|
$780.000
|
$775.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
9.000
|
$700.000
|
$835.000
|
$925.000
|
$975.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
9.000
|
$550.000
|
$425.000
|
$475.000
|
$465.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
2.000
|
$430.000
|
$505.000
|
$565.000
|
$555.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
14.000
|
$100.000
|
$140.000
|
$100.000
|
$150.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
4.000
|
$40.000
|
$35.000
|
$40.000
|
$38.000
|
|
|
INSTL DEL ASSM (D-DY)SZ 1(BRF)GF2
|
EA
|
4.000
|
$30.000
|
$35.000
|
$40.000
|
$42.000
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
802.000
|
$3.000
|
$1.150
|
$1.100
|
$1.100
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
64.000
|
$15.000
|
$15.000
|
$16.500
|
$16.500
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
1.000
|
$210.000
|
$220.000
|
$220.000
|
$220.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
1.000
|
$325.000
|
$320.000
|
$330.000
|
$330.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
80.000
|
$3.500
|
$3.000
|
$4.400
|
$4.400
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
729.000
|
$3.500
|
$3.000
|
$3.850
|
$3.850
|
|
|
NO. OF WORKING DAYS
|
$/D
|
8,000.000
|
$55.000
|
$55.000
|
$55.000
|
$55.000
|
|
|
SP MIXES SP-C SAC-A PG76-22
|
TON
|
14,864.000
|
$110.000
|
$114.850
|
$114.000
|
$107.880
|
|
|
TACK COAT
|
GAL
|
13,381.000
|
$3.000
|
$1.000
|
$0.250
|
$1.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
8.000
|
$8,000.000
|
$4,000.000
|
$10,000.000
|
$30,000.000
|
|
|
PREFORMED CENTERLINE RUMBLE STRIP
|
LF
|
2,473.000
|
$3.250
|
$5.350
|
$5.500
|
$5.500
|
|
|
REFL PAV MRK AWT (W) 4" (SLD) (100MIL)
|
LF
|
26,966.000
|
$0.500
|
$0.450
|
$0.550
|
$0.550
|
|
|
REFL PAV MRK AWT (Y) 4" (SLD) (100MIL)
|
LF
|
17,264.000
|
$0.500
|
$0.450
|
$0.600
|
$0.600
|
|
|
REFL PAV MRK AWT (Y) 4" (BRK) (100MIL)
|
LF
|
3,102.000
|
$0.500
|
$0.550
|
$0.550
|
$0.550
|
|
|
TMA (STATIONARY)
|
DAY
|
65.000
|
$225.000
|
$150.000
|
$300.000
|
$125.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
6.000
|
$250.000
|
$1.000
|
$300.000
|
$275.000
|
|
Totals: |
$4,700,137.100
|
$5,981,441.560
|
$6,155,927.650
|
$6,315,031.270
|