PREPARING ROW
|
STA
|
9.000
|
$7,500.000
|
$3,500.000
|
$2,618.000
|
$6,500.000
|
$35,000.000
|
$20,000.000
|
$15,000.000
|
$5,600.000
|
|
|
REMOV CONC (DRIVEWAYS)
|
SY
|
65.000
|
$30.000
|
$20.000
|
$44.000
|
$50.000
|
$21.530
|
$30.960
|
$41.000
|
$35.000
|
|
|
RMV (2"-8") TRT/UNTRT BASE & ASPH PAV
|
SY
|
3,939.000
|
$9.000
|
$8.000
|
$2.090
|
$8.000
|
$6.720
|
$8.000
|
$12.000
|
$15.000
|
|
|
EXCAV (ROADWAY)
|
CY
|
276.000
|
$30.000
|
$30.000
|
$42.570
|
$50.000
|
$39.380
|
$65.000
|
$50.000
|
$25.000
|
|
|
EXCAV (CHANNEL)
|
CY
|
352.000
|
$30.000
|
$35.000
|
$126.500
|
$60.000
|
$39.380
|
$51.000
|
$29.000
|
$25.000
|
|
|
EMBANK (FNL)(DC)(TY B)
|
CY
|
6,428.000
|
$50.000
|
$35.000
|
$38.500
|
$25.000
|
$30.190
|
$52.000
|
$30.000
|
$30.000
|
|
|
BLADING
|
HR
|
40.000
|
$160.000
|
$100.000
|
$174.889
|
$125.000
|
$110.250
|
$335.000
|
$300.000
|
$50.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
7,911.000
|
$3.000
|
$3.000
|
$1.672
|
$9.000
|
$4.730
|
$2.000
|
$5.500
|
$2.500
|
|
|
BROADCAST SEED (PERM_URBAN_CLAY)
|
SY
|
7,911.000
|
$1.000
|
$1.000
|
$0.286
|
$0.500
|
$1.050
|
$0.310
|
$0.500
|
$0.750
|
|
|
BROADCAST SEED (TEMP_WARM)
|
SY
|
7,911.000
|
$1.000
|
$1.000
|
$0.198
|
$0.500
|
$2.100
|
$0.750
|
$0.420
|
$0.500
|
|
|
VEGETATIVE WATERING
|
TGL
|
554.000
|
$26.000
|
$50.000
|
$112.211
|
$10.000
|
$73.500
|
$120.000
|
$10.000
|
$1.000
|
|
|
SOIL RET BLKT(SL_MOD_CLAY_SHORT)
|
SY
|
6,337.000
|
$2.000
|
$1.500
|
$2.475
|
$2.000
|
$5.250
|
$2.000
|
$1.100
|
$1.500
|
|
|
PROOF ROLLING
|
HR
|
40.000
|
$456.000
|
$105.000
|
$127.776
|
$150.000
|
$110.250
|
$415.000
|
$100.000
|
$1.000
|
|
|
FL BS (CMP IN PLC)(TY A GR 1-2) (6")
|
SY
|
3,439.000
|
$25.000
|
$25.000
|
$33.000
|
$35.000
|
$84.110
|
$40.000
|
$80.000
|
$30.000
|
|
|
SALV, HAUL & STKPL RCL APH PV(2"-15.6")
|
SY
|
3,939.000
|
$7.000
|
$10.000
|
$5.665
|
$35.000
|
$13.810
|
$22.000
|
$7.500
|
$15.000
|
|
|
PRIME COAT (RC-250)
|
GAL
|
757.000
|
$40.000
|
$25.000
|
$15.400
|
$25.000
|
$21.000
|
$15.000
|
$14.000
|
$20.000
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
1,126.000
|
$150.000
|
$175.000
|
$154.000
|
$150.000
|
$183.750
|
$165.000
|
$140.000
|
$220.000
|
|
|
SP MIXES SP-C SAC-A PG70-28
|
TON
|
365.000
|
$220.000
|
$250.000
|
$206.800
|
$200.000
|
$194.250
|
$220.000
|
$188.000
|
$220.000
|
|
|
TACK COAT
|
GAL
|
636.000
|
$4.500
|
$10.000
|
$2.750
|
$6.000
|
$10.500
|
$3.000
|
$2.500
|
$6.000
|
|
|
CEM STABIL BKFL
|
CY
|
164.000
|
$300.000
|
$220.000
|
$275.000
|
$225.000
|
$137.030
|
$210.000
|
$390.000
|
$300.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
468.000
|
$11.000
|
$15.000
|
$11.000
|
$20.000
|
$26.510
|
$24.000
|
$8.250
|
$10.000
|
|
|
DRILL SHAFT (18 IN)
|
LF
|
136.000
|
$190.000
|
$220.000
|
$214.500
|
$300.000
|
$329.410
|
$235.000
|
$140.000
|
$180.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
272.000
|
$320.000
|
$270.000
|
$335.500
|
$400.000
|
$440.960
|
$352.000
|
$350.000
|
$330.000
|
|
|
CL C CONC (ABUT)(HPC)
|
CY
|
50.400
|
$1,580.000
|
$1,200.000
|
$1,320.000
|
$2,500.000
|
$1,576.540
|
$2,500.000
|
$1,500.000
|
$2,200.000
|
|
|
REINF CONC SLAB (HPC)
|
SF
|
3,060.000
|
$32.000
|
$28.000
|
$33.000
|
$45.000
|
$25.540
|
$34.000
|
$37.000
|
$45.000
|
|
|
APPROACH SLAB
|
CY
|
51.400
|
$900.000
|
$750.000
|
$1,012.000
|
$900.000
|
$784.470
|
$1,035.000
|
$900.000
|
$1,800.000
|
|
|
RETAINING WALL (TEMP WALL)
|
SF
|
1,958.000
|
$25.000
|
$25.000
|
$38.500
|
$45.000
|
$33.600
|
$49.000
|
$35.000
|
$30.000
|
|
|
PRESTR CONC GIRDER (TX40)
|
LF
|
447.360
|
$205.000
|
$300.000
|
$197.274
|
$395.000
|
$326.300
|
$275.000
|
$325.000
|
$425.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
29.600
|
$725.000
|
$675.000
|
$823.383
|
$800.000
|
$588.000
|
$1,150.000
|
$800.000
|
$750.000
|
|
|
RIPRAP (STONE PROTECTION)(24 IN)
|
CY
|
1,295.000
|
$190.000
|
$190.000
|
$169.576
|
$200.000
|
$194.780
|
$145.000
|
$250.000
|
$200.000
|
|
|
RAIL (TY SSTR)(HPC)
|
LF
|
240.000
|
$120.000
|
$170.000
|
$275.000
|
$200.000
|
$154.730
|
$295.000
|
$225.000
|
$160.000
|
|
|
ARMOR JOINT (SEALED)
|
LF
|
60.000
|
$175.000
|
$150.000
|
$195.184
|
$175.000
|
$118.130
|
$335.000
|
$210.000
|
$200.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
37.000
|
$140.000
|
$130.000
|
$182.468
|
$125.000
|
$170.440
|
$171.000
|
$120.000
|
$150.000
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
54.000
|
$250.000
|
$200.000
|
$256.553
|
$300.000
|
$260.530
|
$295.000
|
$300.000
|
$220.000
|
|
|
RC PIPE (CL III)(48 IN)
|
LF
|
281.000
|
$280.000
|
$300.000
|
$398.211
|
$325.000
|
$288.920
|
$325.000
|
$325.000
|
$300.000
|
|
|
INLET (COMPL)(PAZD)(RC)(5FTX5FT)
|
EA
|
2.000
|
$10,500.000
|
$6,000.000
|
$7,304.000
|
$7,500.000
|
$6,851.250
|
$8,500.000
|
$8,500.000
|
$12,000.000
|
|
|
HEADWALL (CH - PW - S) (DIA= 48 IN)
|
EA
|
1.000
|
$1,600.000
|
$18,000.000
|
$18,645.000
|
$15,000.000
|
$22,050.000
|
$35,000.000
|
$23,000.000
|
$10,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$2,000.000
|
$1,800.000
|
$1,944.250
|
$2,500.000
|
$1,850.630
|
$2,500.000
|
$2,400.000
|
$3,000.000
|
|
|
SET (TY II) (42 IN) (RCP) (6: 1) (P)
|
EA
|
1.000
|
$3,500.000
|
$7,000.000
|
$10,021.000
|
$5,000.000
|
$2,900.630
|
$9,500.000
|
$9,500.000
|
$18,000.000
|
|
|
REMOV STR (SET)
|
EA
|
2.000
|
$900.000
|
$100.000
|
$877.250
|
$2,000.000
|
$220.500
|
$1,200.000
|
$875.000
|
$2,000.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
4.000
|
$1,200.000
|
$500.000
|
$1,705.000
|
$2,500.000
|
$1,378.130
|
$2,100.000
|
$1,600.000
|
$2,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
157.000
|
$30.000
|
$10.000
|
$46.750
|
$20.000
|
$22.050
|
$36.000
|
$26.000
|
$30.000
|
|
|
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
|
EA
|
1.000
|
$50,000.000
|
$25,000.000
|
$28,050.000
|
$48,000.000
|
$31,500.000
|
$115,000.000
|
$100,000.000
|
$235,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$234,827.000
|
$180,000.000
|
$395,377.500
|
$309,000.000
|
$280,000.000
|
$142,358.950
|
$300,000.000
|
$275,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
9.000
|
$10,000.000
|
$3,000.000
|
$10,450.000
|
$4,500.000
|
$3,029.250
|
$10,000.000
|
$14,000.000
|
$7,300.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$7,500.000
|
$13,286.603
|
$20,000.000
|
$21,000.000
|
$20,000.000
|
$15,000.000
|
$22,500.000
|
|
|
TMA (STATIONARY)
|
DAY
|
2.000
|
$210.000
|
$400.000
|
$410.674
|
$300.000
|
$1,050.000
|
$1,000.000
|
$300.000
|
$300.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
16.000
|
$100.000
|
$200.000
|
$165.000
|
$50.000
|
$262.500
|
$1,200.000
|
$250.000
|
$200.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
24.000
|
$50.000
|
$109.000
|
$50.237
|
$50.000
|
$105.000
|
$115.000
|
$50.000
|
$1.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
24.000
|
$20.000
|
$25.000
|
$20.911
|
$30.000
|
$52.500
|
$58.000
|
$25.000
|
$1.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
78.000
|
$40.000
|
$30.000
|
$49.566
|
$55.000
|
$31.500
|
$45.000
|
$45.000
|
$1.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
78.000
|
$15.000
|
$10.000
|
$21.098
|
$25.000
|
$10.500
|
$15.000
|
$15.000
|
$1.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
893.000
|
$5.000
|
$4.000
|
$4.543
|
$5.000
|
$5.250
|
$5.000
|
$4.000
|
$1.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
893.000
|
$1.000
|
$2.000
|
$1.254
|
$2.000
|
$2.100
|
$1.000
|
$1.500
|
$1.000
|
|
|
CONSTRUCTING DETOURS
|
SY
|
357.000
|
$130.000
|
$200.000
|
$237.050
|
$200.000
|
$170.260
|
$155.000
|
$230.000
|
$200.000
|
|
|
ONE-WAY TRAF CONT (FLAGGER CONT)
|
HR
|
24.000
|
$70.000
|
$65.000
|
$38.500
|
$150.000
|
$157.500
|
$405.000
|
$250.000
|
$170.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
8.000
|
$7,000.000
|
$4,000.000
|
$7,988.750
|
$9,000.000
|
$7,875.000
|
$5,225.000
|
$7,500.000
|
$5,000.000
|
|
|
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
|
LF
|
90.000
|
$52.000
|
$65.000
|
$88.000
|
$90.000
|
$72.710
|
$85.000
|
$80.000
|
$100.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
860.000
|
$60.000
|
$45.000
|
$88.000
|
$90.000
|
$82.160
|
$85.000
|
$80.000
|
$110.000
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$65.000
|
$10.000
|
$88.000
|
$90.000
|
$80.060
|
$85.000
|
$80.000
|
$120.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
760.000
|
$22.000
|
$15.000
|
$11.000
|
$30.000
|
$10.760
|
$10.000
|
$10.000
|
$40.000
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$25.000
|
$15.000
|
$11.000
|
$30.000
|
$10.760
|
$30.000
|
$10.000
|
$40.000
|
|
|
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
|
LF
|
90.000
|
$18.000
|
$15.000
|
$44.000
|
$30.000
|
$10.760
|
$15.000
|
$40.000
|
$50.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
860.000
|
$22.000
|
$15.000
|
$19.800
|
$30.000
|
$10.760
|
$22.000
|
$18.000
|
$50.000
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
40.000
|
$25.000
|
$15.000
|
$19.800
|
$30.000
|
$10.760
|
$22.000
|
$18.000
|
$50.000
|
|
|
PORT CTB(FUR & INSTL)(F-SHAPE)(TY T)
|
LF
|
20.000
|
$120.000
|
$25.000
|
$198.000
|
$90.000
|
$170.360
|
$85.000
|
$180.000
|
$130.000
|
|
|
PORT CTB(REMOVE)(F-SHAPE)(TY T)
|
LF
|
20.000
|
$56.000
|
$15.000
|
$55.000
|
$30.000
|
$10.760
|
$13.000
|
$50.000
|
$130.000
|
|
|
DRIVEWAYS (CONC)
|
SY
|
59.000
|
$126.000
|
$120.000
|
$99.000
|
$120.000
|
$120.230
|
$140.000
|
$110.000
|
$120.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
927.000
|
$80.000
|
$65.000
|
$58.300
|
$60.000
|
$29.400
|
$45.000
|
$40.000
|
$80.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
175.000
|
$28.000
|
$25.000
|
$27.500
|
$35.000
|
$36.750
|
$30.000
|
$25.000
|
$26.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$2,000.000
|
$2,100.000
|
$2,090.000
|
$2,350.000
|
$2,625.000
|
$2,235.000
|
$1,900.000
|
$1,800.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
500.000
|
$4.500
|
$2.000
|
$3.025
|
$5.000
|
$5.250
|
$3.000
|
$2.750
|
$2.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
3.000
|
$300.000
|
$400.000
|
$165.000
|
$300.000
|
$262.500
|
$175.000
|
$150.000
|
$500.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$3,200.000
|
$3,500.000
|
$3,165.250
|
$3,500.000
|
$3,675.000
|
$3,500.000
|
$2,900.000
|
$4,000.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
1.000
|
$300.000
|
$350.000
|
$275.000
|
$350.000
|
$262.500
|
$295.000
|
$250.000
|
$500.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
11.000
|
$900.000
|
$840.000
|
$797.500
|
$900.000
|
$813.750
|
$1,000.000
|
$630.000
|
$1,200.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
|
EA
|
1.000
|
$900.000
|
$1,050.000
|
$830.500
|
$1,000.000
|
$1,018.500
|
$1,000.000
|
$935.000
|
$1,500.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
1.000
|
$1,200.000
|
$1,060.000
|
$1,358.500
|
$1,150.000
|
$1,123.500
|
$1,000.000
|
$855.000
|
$1,500.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
|
EA
|
1.000
|
$1,200.000
|
$1,550.000
|
$1,952.500
|
$1,500.000
|
$1,501.500
|
$1,000.000
|
$1,255.000
|
$2,000.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
15.000
|
$175.000
|
$140.000
|
$108.900
|
$150.000
|
$141.750
|
$295.000
|
$115.000
|
$50.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB (BI)
|
EA
|
6.000
|
$33.000
|
$25.000
|
$17.600
|
$50.000
|
$23.630
|
$17.000
|
$33.000
|
$30.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
6.000
|
$33.000
|
$28.000
|
$27.500
|
$50.000
|
$27.830
|
$17.000
|
$38.000
|
$30.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
4.000
|
$75.000
|
$119.000
|
$55.000
|
$150.000
|
$110.250
|
$55.000
|
$130.000
|
$500.000
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
2.000
|
$50.000
|
$124.000
|
$49.500
|
$150.000
|
$120.750
|
$53.000
|
$130.000
|
$500.000
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
20.000
|
$5.100
|
$6.000
|
$5.500
|
$10.000
|
$4.840
|
$8.000
|
$7.500
|
$5.000
|
|
|
WK ZN PAV MRK REMOV (W)6"(SLD)
|
LF
|
4,737.000
|
$1.600
|
$1.500
|
$2.145
|
$2.000
|
$1.580
|
$1.750
|
$1.500
|
$2.000
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
34.000
|
$12.000
|
$15.000
|
$7.700
|
$15.000
|
$27.300
|
$15.000
|
$13.000
|
$10.000
|
|
|
WK ZN PAV MRK REMOV (Y)6"(SLD)
|
LF
|
800.000
|
$1.600
|
$1.250
|
$2.145
|
$2.000
|
$2.000
|
$1.750
|
$1.500
|
$2.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
32.000
|
$10.000
|
$10.000
|
$9.900
|
$15.000
|
$3.000
|
$15.000
|
$13.000
|
$10.000
|
|
|
PAVEMENT SLER 6"
|
LF
|
2,744.000
|
$0.500
|
$0.500
|
$0.550
|
$1.000
|
$4.000
|
$0.600
|
$0.500
|
$1.000
|
|
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
|
LF
|
1,084.000
|
$1.000
|
$1.000
|
$1.705
|
$2.000
|
$1.000
|
$1.750
|
$1.500
|
$2.000
|
|
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
|
LF
|
1,974.000
|
$1.000
|
$1.100
|
$1.705
|
$2.000
|
$1.000
|
$1.750
|
$1.500
|
$2.000
|
|
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
|
LF
|
1,084.000
|
$1.000
|
$1.000
|
$1.705
|
$2.000
|
$1.000
|
$1.750
|
$1.500
|
$2.000
|
|
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
|
LF
|
1,822.000
|
$1.000
|
$1.150
|
$1.705
|
$2.000
|
$1.000
|
$1.770
|
$1.500
|
$2.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
29.000
|
$6.000
|
$6.000
|
$7.205
|
$12.000
|
$20.000
|
$10.000
|
$10.000
|
$8.000
|
|
|
ELIM EXT PM & MRKS (4")
|
LF
|
2,006.000
|
$1.000
|
$1.250
|
$1.980
|
$2.000
|
$1.000
|
$2.000
|
$1.750
|
$2.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
5,964.000
|
$0.500
|
$0.250
|
$0.275
|
$0.500
|
$1.000
|
$0.350
|
$0.300
|
$0.250
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
32.000
|
$1.000
|
$2.000
|
$0.935
|
$20.000
|
$1.000
|
$3.500
|
$3.000
|
$1.000
|
|
Totals: |
$2,673,092.000
|
$2,382,295.200
|
$2,879,976.661
|
$3,094,888.200
|
$3,179,978.412
|
$3,180,000.000
|
$3,186,925.520
|
$3,241,067.750
|