PREPARING ROW
|
STA
|
214.576
|
$300.000
|
$275.000
|
$160.000
|
$450.000
|
$3,000.000
|
|
|
REMOVING STAB BASE & ASPH PAV (7"-12")
|
SY
|
81,074.000
|
$6.000
|
$1.050
|
$7.800
|
$6.150
|
$4.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
50.000
|
$8.000
|
$42.000
|
$145.000
|
$75.000
|
$25.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY D)
|
CY
|
50.000
|
$10.000
|
$42.000
|
$96.000
|
$75.000
|
$28.000
|
|
|
BACKFILL (TY B)
|
STA
|
214.800
|
$165.000
|
$210.000
|
$390.000
|
$225.000
|
$250.000
|
|
|
BLADING
|
HR
|
219.000
|
$150.000
|
$210.000
|
$38.000
|
$150.000
|
$150.000
|
|
|
COMPOST MANUF TOPSOIL (4")
|
SY
|
24,732.400
|
$1.400
|
$1.210
|
$1.350
|
$1.350
|
$2.000
|
|
|
BROADCAST SEED (PERM) (RURAL) (SANDY)
|
AC
|
5.110
|
$800.000
|
$1,150.000
|
$1,050.000
|
$1,500.000
|
$700.000
|
|
|
VEGETATIVE WATERING
|
MG
|
1,048.000
|
$20.000
|
$42.000
|
$0.010
|
$40.000
|
$10.000
|
|
|
FL BS(RDWY DEL)(TY D GR 1-2)(FNAL POS)
|
CY
|
10,970.000
|
$48.000
|
$55.000
|
$53.850
|
$38.500
|
$75.000
|
|
|
LIME (HYD, COM OR QK)(SLURRY)
|
TON
|
937.000
|
$158.000
|
$200.000
|
$200.000
|
$183.000
|
$200.000
|
|
|
LIME TRT (SUBGRADE)(8")
|
SY
|
55,541.000
|
$4.200
|
$2.100
|
$2.900
|
$4.000
|
$5.000
|
|
|
CEMENT
|
TON
|
555.500
|
$150.000
|
$150.000
|
$230.000
|
$155.000
|
$200.000
|
|
|
CEMENT TREAT(EXIST MATL)(8")
|
SY
|
14,358.000
|
$3.000
|
$1.330
|
$4.700
|
$4.000
|
$5.000
|
|
|
CEMENT TREAT (NEW BASE)(6")(DC)
|
SY
|
69,899.000
|
$2.500
|
$1.850
|
$2.035
|
$3.500
|
$4.000
|
|
|
PRIME COAT (EC-30)
|
GAL
|
13,169.000
|
$3.300
|
$7.320
|
$5.250
|
$5.500
|
$5.000
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
17,822.000
|
$75.000
|
$89.320
|
$86.000
|
$99.000
|
$90.000
|
|
|
TACK COAT
|
GAL
|
10,117.000
|
$3.500
|
$3.300
|
$3.500
|
$3.150
|
$4.000
|
|
|
SUPERPAVE MIXTURES SP-C SAC-A PG70-28
|
TON
|
8,238.000
|
$110.000
|
$111.430
|
$101.250
|
$118.000
|
$95.000
|
|
|
TACK COAT
|
GAL
|
10,117.000
|
$3.500
|
$3.300
|
$3.500
|
$3.150
|
$4.000
|
|
|
PLANE ASPH CONC PAV(2" TO 4")
|
SY
|
81,074.000
|
$2.000
|
$1.990
|
$2.800
|
$2.700
|
$3.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
152.000
|
$500.000
|
$525.000
|
$650.000
|
$630.000
|
$400.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$2,500.000
|
$4,200.000
|
$2,250.000
|
$1,500.000
|
$1,285.000
|
|
|
REMOV STR (SET)
|
EA
|
2.000
|
$400.000
|
$1,050.000
|
$560.000
|
$1,000.000
|
$1,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$480,000.000
|
$549,000.000
|
$560,000.000
|
$650,000.000
|
$605,785.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
13.000
|
$5,000.000
|
$10,500.000
|
$8,000.000
|
$12,000.000
|
$3,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
736.000
|
$28.000
|
$27.500
|
$34.500
|
$24.650
|
$30.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
736.000
|
$7.500
|
$13.750
|
$12.250
|
$7.600
|
$9.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
112.000
|
$25.000
|
$20.350
|
$32.750
|
$24.000
|
$22.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
112.000
|
$10.000
|
$9.900
|
$13.000
|
$9.500
|
$9.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
961.000
|
$2.200
|
$1.650
|
$7.250
|
$3.200
|
$3.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
961.000
|
$0.500
|
$0.170
|
$1.700
|
$1.000
|
$1.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
736.000
|
$7.000
|
$4.130
|
$6.200
|
$5.000
|
$6.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
736.000
|
$1.800
|
$1.100
|
$1.500
|
$1.000
|
$1.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
13.000
|
$8,000.000
|
$6,300.000
|
$7,600.000
|
$8,000.000
|
$4,800.000
|
|
|
INTRSCT, DRVWAYS, & TURNOUT (ACP)
|
SY
|
926.000
|
$45.000
|
$36.000
|
$75.000
|
$76.000
|
$46.000
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
3,135.000
|
$23.000
|
$21.180
|
$25.000
|
$24.250
|
$19.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
4,210.000
|
$3.500
|
$2.200
|
$3.350
|
$3.300
|
$2.000
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
9.000
|
$245.000
|
$110.000
|
$280.000
|
$275.000
|
$100.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
18.000
|
$2,500.000
|
$2,860.000
|
$2,750.000
|
$2,800.000
|
$2,600.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
9.000
|
$300.000
|
$220.000
|
$280.000
|
$275.000
|
$200.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
47.000
|
$524.000
|
$495.000
|
$525.000
|
$650.000
|
$482.000
|
|
|
INSTL OM ASSM (OM-3R)(TWT)GND
|
EA
|
14.000
|
$212.000
|
$187.000
|
$279.000
|
$290.000
|
$170.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
33.000
|
$40.000
|
$40.700
|
$50.250
|
$50.000
|
$37.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
178,109.000
|
$0.200
|
$0.500
|
$0.560
|
$0.450
|
$0.250
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
11,428.000
|
$0.200
|
$0.500
|
$0.560
|
$0.570
|
$0.220
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
177,030.000
|
$0.200
|
$0.500
|
$0.560
|
$0.660
|
$0.230
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
1,440.000
|
$4.000
|
$3.740
|
$3.800
|
$4.950
|
$4.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
4,800.000
|
$0.700
|
$1.100
|
$1.120
|
$1.100
|
$0.600
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
176.000
|
$7.500
|
$8.800
|
$8.900
|
$13.200
|
$8.500
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
2,400.000
|
$0.700
|
$1.100
|
$1.120
|
$1.650
|
$0.650
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
135.000
|
$7.000
|
$6.050
|
$6.150
|
$16.500
|
$6.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
43,995.000
|
$0.450
|
$0.510
|
$0.500
|
$0.430
|
$0.300
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
10,125.000
|
$0.400
|
$0.570
|
$0.580
|
$0.110
|
$0.300
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
28,905.000
|
$0.350
|
$0.510
|
$0.510
|
$0.440
|
$0.300
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
471.000
|
$3.000
|
$3.740
|
$3.800
|
$4.950
|
$3.000
|
|
TRAFFIC BUTTON TY W
|
EA
|
9,463.000
|
$4.000
|
$3.080
|
$3.150
|
$2.600
|
$1.800
|
|
TRAFFIC BUTTON TY B
|
EA
|
9,463.000
|
$5.000
|
$3.080
|
$3.120
|
$2.750
|
$1.650
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
2,400.000
|
$0.400
|
$1.250
|
$1.120
|
$1.100
|
$0.400
|
|
|
PAV SURF PREP FOR MRK (4")
|
LF
|
83,025.000
|
$0.150
|
$0.060
|
$0.050
|
$0.060
|
$0.100
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
129.000
|
$1.400
|
$3.300
|
$3.350
|
$1.400
|
$1.100
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$10,000.000
|
$15,750.000
|
$14,000.000
|
$15,000.000
|
$7,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
50.000
|
$200.000
|
$735.000
|
$225.000
|
$300.000
|
$200.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
20.000
|
$60.000
|
$110.000
|
$115.000
|
$250.000
|
$45.000
|
|
Totals: |
$5,641,929.310
|
$5,769,636.534
|
$6,366,060.325
|
$6,732,042.300
|
$6,850,349.360
|