EXCAVATION (ROADWAY)
|
CY
|
11,277.000
|
$10.000
|
$20.470
|
$26.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
3,552.000
|
$14.000
|
$8.230
|
$30.000
|
|
|
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
|
CY
|
5,964.000
|
$72.000
|
$94.780
|
$135.000
|
|
|
PRIME COAT (MC-30)
|
GAL
|
7,156.000
|
$6.000
|
$7.810
|
$7.000
|
|
|
EMULS ASPH (EROSN CONT)(MS-2)
|
GAL
|
2,379.000
|
$6.000
|
$5.880
|
$5.500
|
|
|
PLANE ASPH CONC PAV(0" TO 1")
|
SY
|
5,362.000
|
$6.000
|
$13.570
|
$6.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
79.000
|
$20.000
|
$8.250
|
$10.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
120.000
|
$30.000
|
$22.000
|
$25.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
14.000
|
$600.000
|
$193.990
|
$300.000
|
|
|
CONC BOX CULV (4 FT X 3 FT)
|
LF
|
200.000
|
$500.000
|
$479.120
|
$600.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
100.000
|
$90.000
|
$90.110
|
$100.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
442.000
|
$100.000
|
$110.240
|
$125.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
12.000
|
$150.000
|
$208.020
|
$225.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 4 FT)(4:1) (C)
|
EA
|
5.000
|
$6,500.000
|
$16,221.960
|
$18,000.000
|
|
|
SET (TY I)(S= 4 FT)(HW= 4 FT)(6:1) (C)
|
EA
|
5.000
|
$9,000.000
|
$20,423.720
|
$22,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$1,600.000
|
$1,867.140
|
$2,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
8.000
|
$1,900.000
|
$2,259.380
|
$2,500.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (C)
|
EA
|
10.000
|
$3,200.000
|
$2,386.860
|
$2,600.000
|
|
|
SET (TY II) (36 IN) (RCP) (3: 1) (C)
|
EA
|
4.000
|
$3,800.000
|
$5,525.980
|
$6,000.000
|
|
|
REMOV STR (PIPE)
|
EA
|
7.000
|
$1,500.000
|
$437.270
|
$1,500.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$413,070.000
|
$620,585.200
|
$550,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
7.000
|
$10,000.000
|
$22,604.020
|
$25,000.000
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (12")
|
LF
|
760.000
|
$7.000
|
$12.750
|
$12.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
760.000
|
$2.000
|
$3.730
|
$4.000
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
7.000
|
$8,000.000
|
$7,700.000
|
$8,000.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
55,241.000
|
$0.400
|
$0.130
|
$0.500
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
28,658.000
|
$0.400
|
$0.130
|
$0.500
|
|
|
ALUMINUM SIGNS (TY A)
|
SF
|
162.000
|
$50.000
|
$55.000
|
$60.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
87.000
|
$950.000
|
$605.000
|
$1,100.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
7.000
|
$1,000.000
|
$660.000
|
$1,200.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
2.000
|
$1,200.000
|
$715.000
|
$1,300.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
107.000
|
$165.000
|
$177.010
|
$200.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
19.000
|
$85.000
|
$77.000
|
$60.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
2,900.000
|
$1.500
|
$4.760
|
$1.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
55,241.000
|
$0.650
|
$0.550
|
$0.600
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
5,004.000
|
$0.650
|
$0.550
|
$0.600
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
17,234.000
|
$0.650
|
$0.550
|
$0.600
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
136.000
|
$20.000
|
$22.000
|
$25.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
217.000
|
$5.000
|
$5.500
|
$6.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
71,300.000
|
$0.350
|
$0.740
|
$1.000
|
|
|
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
|
EA
|
16.000
|
$7,500.000
|
$13,750.000
|
$12,000.000
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
14,393.000
|
$170.000
|
$154.000
|
$155.000
|
|
|
TACK COAT
|
GAL
|
9,872.000
|
$6.000
|
$6.630
|
$5.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$15,000.000
|
$21,743.970
|
$10,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
125.000
|
$250.000
|
$416.810
|
$300.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
14.000
|
$650.000
|
$884.340
|
$100.000
|
|
|
LEAD LED CHEVRON
|
EA
|
25.000
|
$4,000.000
|
$4,290.000
|
$5,000.000
|
|
|
LED CHEVRON
|
EA
|
34.000
|
$2,050.000
|
$2,750.000
|
$3,000.000
|
|
Totals: |
$4,655,120.950
|
$5,256,051.970
|
$5,642,324.400
|