EXCAVATION (SPECIAL)
|
CY
|
2.000
|
$400.000
|
$700.000
|
$850.000
|
$1,000.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
255.000
|
$275.000
|
$250.000
|
$275.000
|
$275.000
|
|
|
EMULS ASPH (EROSN CONT)(MULTI)
|
GAL
|
635.000
|
$6.000
|
$20.000
|
$7.500
|
$15.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
5,381.000
|
$65.000
|
$50.000
|
$70.000
|
$60.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
4,289.000
|
$1.330
|
$6.500
|
$6.000
|
$10.000
|
|
|
PLANE ASPH CONC PAV(MICRO-MLLING)(1")
|
SY
|
107,624.000
|
$0.770
|
$0.900
|
$4.500
|
$8.000
|
|
|
DRILL SHAFT (42 IN)
|
LF
|
84.000
|
$565.000
|
$570.000
|
$650.000
|
$625.000
|
|
|
DRILL SHAFT (54 IN)
|
LF
|
76.000
|
$565.000
|
$575.000
|
$700.000
|
$625.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
9.000
|
$490.000
|
$850.000
|
$900.000
|
$700.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
26.000
|
$475.000
|
$625.000
|
$700.000
|
$550.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$296,688.020
|
$52,000.000
|
$400,000.000
|
$600,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
3.000
|
$15,000.000
|
$2,500.000
|
$15,000.000
|
$25,000.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
42,240.000
|
$0.190
|
$0.130
|
$0.260
|
$2.000
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
300.000
|
$37.000
|
$45.000
|
$45.000
|
$45.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,460.000
|
$1,450.000
|
$2,000.000
|
$2,500.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$3,370.000
|
$3,200.000
|
$3,800.000
|
$3,800.000
|
|
|
CONDT (PVC) (SCH 40) (2")
|
LF
|
400.000
|
$33.000
|
$29.850
|
$35.000
|
$33.000
|
|
|
CONDT (PVC) (SCH 40) (2") (BORE)
|
LF
|
710.000
|
$40.000
|
$42.000
|
$60.000
|
$48.000
|
|
|
ELEC CONDR (NO.6) INSULATED
|
LF
|
1,000.000
|
$4.000
|
$3.260
|
$4.500
|
$5.000
|
|
|
ELEC CONDR (NO.4) INSULATED
|
LF
|
1,215.000
|
$4.200
|
$3.950
|
$5.000
|
$6.500
|
|
|
ELEC CONDR (NO.2) INSULATED
|
LF
|
1,650.000
|
$5.250
|
$4.700
|
$5.000
|
$6.000
|
|
|
GROUND BOX TY A (122311)W/APRON
|
EA
|
11.000
|
$1,550.000
|
$2,225.000
|
$2,700.000
|
$3,200.000
|
|
|
ELC SRV TY D 120/240 060(NS)GS(N)GC(O)
|
EA
|
3.000
|
$8,000.000
|
$9,880.000
|
$12,000.000
|
$12,000.000
|
|
|
ELC SRV TY D 120/240 100(NS)GS(N)GC(O)
|
EA
|
2.000
|
$9,000.000
|
$11,105.000
|
$13,000.000
|
$13,000.000
|
|
|
INS OH SN SUP(30 FT BAL TEE)
|
EA
|
2.000
|
$41,000.000
|
$60,000.000
|
$63,500.000
|
$67,000.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
1,708.000
|
$2.000
|
$2.050
|
$5.000
|
$4.000
|
|
REFL PAV MRK TY I (W)(NUMBER)(090MIL)
|
EA
|
2.000
|
$280.000
|
$250.000
|
$275.000
|
$350.000
|
|
REFL PAV MRK TY I(W)(ENTR GORE)(090MIL)
|
EA
|
2.000
|
$1,000.000
|
$1,425.000
|
$850.000
|
$2,500.000
|
|
REFL PAV MRK TY I(W)(EXIT GORE)(090MIL)
|
EA
|
2.000
|
$745.000
|
$1,675.000
|
$950.000
|
$2,700.000
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
25,389.000
|
$5.000
|
$0.750
|
$1.000
|
$1.100
|
|
RE PM W/RET REQ TY I (W)6"(BRK)(090MIL)
|
LF
|
5,280.000
|
$0.630
|
$1.200
|
$1.000
|
$2.000
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
25,389.000
|
$0.500
|
$0.750
|
$1.000
|
$1.150
|
|
REFL PAV MRKR TY II-C-R
|
EA
|
316.000
|
$3.230
|
$6.350
|
$6.000
|
$10.000
|
|
|
STONE-MTRX-ASPH SMA-C SAC-A PG76-22
|
TON
|
14,798.000
|
$160.000
|
$153.000
|
$180.000
|
$167.000
|
|
|
TACK COAT
|
GAL
|
16,144.000
|
$6.500
|
$5.500
|
$7.500
|
$7.750
|
|
|
TBWC (MEMBRANE)
|
GAL
|
23,677.000
|
$7.000
|
$5.000
|
$7.500
|
$7.750
|
|
|
TBWC PG76-22 SAC-A TY C
|
TON
|
5,381.000
|
$150.000
|
$145.000
|
$175.000
|
$167.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
DAY
|
20.000
|
$100.000
|
$130.000
|
$875.000
|
$200.000
|
|
|
ITS SYSTEM SUPPORT EQUIPMENT
|
LS
|
1.000
|
$40,000.000
|
$60,000.000
|
$58,000.000
|
$62,000.000
|
|
|
CCTV FIELD EQUIP (DIGITAL) (INSTL ONLY)
|
EA
|
4.000
|
$5,000.000
|
$1,055.000
|
$1,200.000
|
$1,300.000
|
|
|
INSTALL DMS (POLE MTD CABINET)
|
EA
|
2.000
|
$40,000.000
|
$40,000.000
|
$41,000.000
|
$46,000.000
|
|
|
ITS POLE (55 FT)(90 MPH)
|
EA
|
4.000
|
$24,000.000
|
$28,500.000
|
$29,000.000
|
$35,000.000
|
|
|
ITS POLE MNT CAB (TY 2)(CONF 2)
|
EA
|
4.000
|
$8,500.000
|
$7,900.000
|
$8,000.000
|
$10,000.000
|
|
|
INSTALLATION OF FES (FIELD CABINET)
|
EA
|
1.000
|
$1,800.000
|
$2,050.000
|
$2,200.000
|
$2,800.000
|
|
|
TMA (STATIONARY)
|
DAY
|
29.000
|
$300.000
|
$300.000
|
$325.000
|
$150.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
29.000
|
$450.000
|
$510.000
|
$600.000
|
$300.000
|
|
|
SYSTEM INTEGRATION
|
LS
|
1.000
|
$45,000.000
|
$45,000.000
|
$48,000.000
|
$51,000.000
|
|
|
INSTALLATION OF CELLULAR MODEM
|
EA
|
6.000
|
$750.000
|
$4,000.000
|
$4,100.000
|
$4,700.000
|
|
|
FUR & INST ROADWAY WEATHER INFO SYSTEM
|
EA
|
1.000
|
$120,000.000
|
$97,000.000
|
$98,000.000
|
$106,000.000
|
|
|
PRECIPITATION TYPE SENSOR
|
EA
|
1.000
|
$9,300.000
|
$11,000.000
|
$11,000.000
|
$12,500.000
|
|
|
AIR TEMPERATURE/RELATIVE HUMIDITY SENSO
|
EA
|
1.000
|
$2,000.000
|
$2,305.000
|
$2,500.000
|
$3,000.000
|
|
|
NON-INTRUSIVE PAVEMENT CONDITION SENSOR
|
EA
|
1.000
|
$21,000.000
|
$20,000.000
|
$22,000.000
|
$22,000.000
|
|
|
NON-INTRUSIVE PAVEMENT TEMP SENSOR
|
EA
|
1.000
|
$13,000.000
|
$15,250.000
|
$16,000.000
|
$17,300.000
|
|
|
WINDSPEED/DIRECTION SENSOR
|
EA
|
1.000
|
$4,600.000
|
$5,300.000
|
$5,500.000
|
$6,000.000
|
|
|
BAROMETRIC PRESSURE SENSOR
|
EA
|
1.000
|
$2,300.000
|
$2,650.000
|
$2,800.000
|
$3,200.000
|
|
Totals: |
$5,305,331.550
|
$4,777,419.050
|
$6,416,948.400
|
$6,891,382.500
|