PREPARING ROW
|
STA
|
4.050
|
$3,000.000
|
$5,000.000
|
$5,000.000
|
$7,000.000
|
$16,487.340
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
3,594.000
|
$14.000
|
$6.000
|
$10.000
|
$15.000
|
$16.530
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY C)
|
CY
|
6,848.000
|
$7.500
|
$10.000
|
$25.000
|
$20.000
|
$16.270
|
|
|
BLADING
|
HR
|
50.000
|
$100.000
|
$15.000
|
$115.000
|
$125.000
|
$146.630
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
10,745.000
|
$1.000
|
$3.000
|
$3.500
|
$1.000
|
$4.210
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
29,576.000
|
$0.350
|
$0.420
|
$0.500
|
$0.500
|
$0.460
|
|
|
CELL FBR MLCH SEED(TEMP)(WARM)
|
SY
|
7,394.000
|
$0.350
|
$0.520
|
$0.400
|
$0.500
|
$0.460
|
|
|
CELL FBR MLCH SEED(TEMP)(COOL)
|
SY
|
7,394.000
|
$0.350
|
$0.520
|
$0.400
|
$0.500
|
$0.460
|
|
|
VEGETATIVE WATERING
|
MG
|
249.310
|
$40.000
|
$10.000
|
$10.000
|
$40.000
|
$48.220
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY A)
|
SY
|
3,090.000
|
$1.000
|
$2.000
|
$1.100
|
$2.500
|
$1.500
|
|
|
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
|
CY
|
3,813.000
|
$65.000
|
$92.000
|
$90.000
|
$82.000
|
$79.420
|
|
|
CEMENT
|
TON
|
217.000
|
$150.000
|
$186.000
|
$155.000
|
$200.000
|
$170.400
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
10,714.000
|
$3.000
|
$2.000
|
$1.750
|
$5.000
|
$6.750
|
|
|
PRIME COAT (MC-30)
|
GAL
|
1,779.000
|
$5.000
|
$7.000
|
$5.000
|
$7.000
|
$5.560
|
|
|
AGGR(TY-PE GR-3 SAC-B)
|
CY
|
105.000
|
$120.000
|
$290.000
|
$220.000
|
$330.000
|
$222.300
|
|
|
AGGR(TY-PE GR-4 SAC-B)
|
CY
|
69.000
|
$125.000
|
$300.000
|
$190.000
|
$300.000
|
$284.580
|
|
|
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
|
GAL
|
6,582.000
|
$3.500
|
$3.000
|
$3.750
|
$4.600
|
$4.100
|
|
|
CEM STABIL BKFL
|
CY
|
194.000
|
$80.000
|
$85.000
|
$150.000
|
$220.000
|
$262.820
|
|
|
TEMPORARY SPL SHORING
|
SF
|
485.000
|
$20.000
|
$35.000
|
$32.000
|
$25.000
|
$44.760
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
1,070.000
|
$220.000
|
$336.000
|
$250.000
|
$250.000
|
$358.560
|
|
|
CL C CONC (ABUT)
|
CY
|
67.700
|
$1,000.000
|
$500.000
|
$1,250.000
|
$1,500.000
|
$1,598.400
|
|
|
CL C CONC (CAP)
|
CY
|
41.400
|
$1,150.000
|
$650.000
|
$1,500.000
|
$1,500.000
|
$1,598.400
|
|
|
CL C CONC (COLUMN)
|
CY
|
25.000
|
$1,150.000
|
$866.000
|
$1,550.000
|
$1,500.000
|
$1,958.400
|
|
|
REINF CONC SLAB
|
SF
|
15,640.000
|
$18.000
|
$15.000
|
$24.250
|
$25.000
|
$27.560
|
|
|
PRESTR CONC GIRDER (TX54)
|
LF
|
2,031.040
|
$130.000
|
$152.000
|
$150.000
|
$195.000
|
$181.920
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
412.000
|
$150.000
|
$135.000
|
$240.000
|
$230.000
|
$215.270
|
|
|
RAIL (TY T223)
|
LF
|
728.000
|
$120.000
|
$81.000
|
$130.000
|
$110.000
|
$115.820
|
|
|
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
|
LF
|
86.000
|
$110.000
|
$100.000
|
$135.000
|
$120.000
|
$123.200
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
32.000
|
$125.000
|
$92.000
|
$175.000
|
$180.000
|
$232.800
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$4,000.000
|
$3,216.000
|
$3,000.000
|
$2,200.000
|
$3,718.800
|
|
|
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
|
EA
|
1.000
|
$80,000.000
|
$100,000.000
|
$85,000.000
|
$100,000.000
|
$93,600.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$200,000.000
|
$200,000.000
|
$325,000.000
|
$300,000.000
|
$297,171.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
11.000
|
$3,800.000
|
$700.000
|
$2,000.000
|
$1,000.000
|
$3,850.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 1)
|
LF
|
170.000
|
$35.000
|
$10.000
|
$20.000
|
$45.000
|
$42.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
170.000
|
$10.000
|
$2.000
|
$10.000
|
$10.000
|
$12.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
3,050.000
|
$3.000
|
$2.000
|
$3.000
|
$4.000
|
$3.300
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
3,050.000
|
$1.000
|
$0.500
|
$1.250
|
$1.000
|
$0.900
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
11.000
|
$5,000.000
|
$3,500.000
|
$4,000.000
|
$5,600.000
|
$3,630.000
|
|
|
PORT CTB (MOVE)(F-SHAPE)(TY 1)
|
LF
|
990.000
|
$15.000
|
$3.000
|
$13.000
|
$20.000
|
$46.200
|
|
|
PORT CTB (STKPL)(F-SHAPE)(TY 1)
|
LF
|
840.000
|
$10.000
|
$10.000
|
$20.000
|
$20.000
|
$38.500
|
|
|
DRIVEWAYS (SURF TREAT)
|
SY
|
324.000
|
$35.000
|
$4.290
|
$35.000
|
$28.000
|
$4.080
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
400.000
|
$25.000
|
$20.000
|
$22.500
|
$28.000
|
$30.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
4.000
|
$1,850.000
|
$1,817.000
|
$2,000.000
|
$2,000.000
|
$1,920.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
200.000
|
$2.500
|
$6.310
|
$1.500
|
$4.000
|
$1.500
|
|
|
RM MTL BM GD FEN TRANS (T101)
|
EA
|
4.000
|
$250.000
|
$315.000
|
$200.000
|
$250.000
|
$600.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,800.000
|
$2,765.000
|
$2,700.000
|
$2,800.000
|
$3,240.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
4.000
|
$300.000
|
$97.000
|
$200.000
|
$350.000
|
$330.000
|
|
|
CRASH CUSH ATTEN (MOVE & RESET)
|
EA
|
2.000
|
$1,500.000
|
$1,894.000
|
$1,400.000
|
$3,500.000
|
$1,872.000
|
|
|
CRASH CUSH ATTEN (STKPL)
|
EA
|
2.000
|
$1,000.000
|
$631.000
|
$1,400.000
|
$2,000.000
|
$840.000
|
|
|
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
|
EA
|
2.000
|
$7,500.000
|
$9,612.000
|
$9,000.000
|
$8,500.000
|
$10,200.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
1.000
|
$500.000
|
$1,022.000
|
$1,000.000
|
$600.000
|
$600.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
6.000
|
$400.000
|
$453.860
|
$550.000
|
$450.000
|
$402.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
2.000
|
$400.000
|
$515.000
|
$750.000
|
$450.000
|
$480.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
9.000
|
$85.000
|
$86.000
|
$150.000
|
$200.000
|
$72.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
28.000
|
$20.000
|
$6.000
|
$30.000
|
$7.000
|
$24.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
14.000
|
$24.000
|
$171.000
|
$25.000
|
$137.000
|
$42.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
15,100.000
|
$1.000
|
$0.910
|
$0.550
|
$0.850
|
$0.860
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
24.000
|
$7.000
|
$6.320
|
$21.000
|
$6.000
|
$6.000
|
|
|
WK ZN PAV MRK REMOV (Y)4"(BRK)
|
LF
|
711.000
|
$1.000
|
$1.330
|
$0.600
|
$1.200
|
$1.260
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
16,910.000
|
$1.000
|
$0.910
|
$0.550
|
$0.850
|
$0.860
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
360.000
|
$2.000
|
$2.530
|
$1.050
|
$2.500
|
$2.640
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
13,200.000
|
$0.750
|
$0.630
|
$0.550
|
$0.550
|
$0.600
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
711.000
|
$0.750
|
$0.630
|
$0.550
|
$0.550
|
$0.600
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
9,710.000
|
$0.750
|
$0.630
|
$0.550
|
$0.550
|
$0.600
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
157.000
|
$5.000
|
$5.000
|
$5.500
|
$5.000
|
$4.800
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
19,900.000
|
$0.500
|
$0.510
|
$1.000
|
$0.450
|
$0.480
|
|
|
ELIM EXT PAV MRK & MRKS (24")
|
LF
|
24.000
|
$4.000
|
$2.530
|
$5.000
|
$2.000
|
$2.400
|
|
|
FULL - WIDTH MOWING
|
CYC
|
1.000
|
$2,600.000
|
$200.000
|
$2,500.000
|
$1,800.000
|
$3,960.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$8,500.000
|
$16,000.000
|
$10,000.000
|
$16,000.000
|
$24,420.000
|
|
|
TMA (STATIONARY)
|
DAY
|
20.000
|
$300.000
|
$300.000
|
$200.000
|
$320.000
|
$366.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
6.000
|
$400.000
|
$300.000
|
$250.000
|
$400.000
|
$780.000
|
|
Totals: |
$2,222,766.750
|
$2,346,537.140
|
$2,838,437.450
|
$2,996,709.650
|
$3,259,587.042
|