PREPARING ROW
|
AC
|
276.500
|
$4,000.000
|
$796.000
|
$350.000
|
$820.000
|
$800.000
|
$900.000
|
|
|
REMOVING CONCRETE(MOW STRIP)
|
LF
|
78.000
|
$5.000
|
$24.000
|
$54.000
|
$36.000
|
$40.000
|
$10.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
209.000
|
$8.000
|
$10.600
|
$30.000
|
$62.000
|
$15.000
|
$100.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
276.500
|
$300.000
|
$314.260
|
$505.000
|
$1,040.000
|
$235.000
|
$250.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
7,957.000
|
$20.000
|
$15.000
|
$18.850
|
$23.000
|
$25.000
|
$15.000
|
|
|
BACKFILL (TY A OR B)
|
STA
|
276.500
|
$150.000
|
$150.000
|
$339.000
|
$230.000
|
$185.000
|
$150.000
|
|
|
BLADING
|
HR
|
100.000
|
$75.000
|
$150.000
|
$148.000
|
$130.000
|
$165.000
|
$150.000
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
52,992.000
|
$0.800
|
$1.000
|
$1.770
|
$2.350
|
$3.000
|
$0.400
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
26,502.000
|
$0.100
|
$0.130
|
$0.370
|
$0.130
|
$0.130
|
$0.240
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
26,502.000
|
$0.100
|
$0.130
|
$0.150
|
$0.130
|
$0.130
|
$0.240
|
|
|
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
|
SY
|
52,992.000
|
$0.300
|
$0.330
|
$0.370
|
$0.300
|
$0.300
|
$0.620
|
|
|
VEGETATIVE WATERING
|
MG
|
523.500
|
$25.000
|
$8.000
|
$4.200
|
$19.000
|
$15.000
|
$25.800
|
|
|
SOIL RETENTION BLANKETS (CL 1) (TY D)
|
SY
|
58.000
|
$5.000
|
$10.000
|
$10.500
|
$5.100
|
$5.250
|
$2.750
|
|
|
FL BS (RDWY DEL) (TY A GR 1-2)
|
TON
|
23,963.000
|
$30.000
|
$40.590
|
$42.000
|
$47.250
|
$35.000
|
$75.000
|
|
|
PRIME COAT (CSS-1H)
|
GAL
|
9,521.000
|
$4.000
|
$2.940
|
$2.950
|
$4.400
|
$2.600
|
$4.000
|
|
|
PLANE ASPH CONC PAV(0" TO 2")
|
SY
|
5,664.000
|
$2.500
|
$4.760
|
$4.450
|
$4.650
|
$3.500
|
$3.000
|
|
|
CEM STABIL BKFL
|
CY
|
110.000
|
$80.000
|
$178.500
|
$94.500
|
$121.000
|
$180.000
|
$100.000
|
|
|
CUT & RESTORING PAV
|
SY
|
193.000
|
$100.000
|
$89.250
|
$105.000
|
$151.000
|
$90.000
|
$70.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(6 IN)
|
CY
|
24.000
|
$200.000
|
$165.900
|
$375.000
|
$101.000
|
$170.000
|
$150.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
5.000
|
$455.000
|
$579.600
|
$682.500
|
$578.000
|
$580.000
|
$500.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
940.000
|
$70.000
|
$52.500
|
$42.000
|
$49.000
|
$53.000
|
$70.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
252.000
|
$90.000
|
$84.000
|
$90.000
|
$97.000
|
$85.000
|
$75.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
60.000
|
$110.000
|
$131.250
|
$131.250
|
$181.000
|
$130.000
|
$80.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 18 IN)
|
EA
|
1.000
|
$4,000.000
|
$3,675.000
|
$3,150.000
|
$3,050.000
|
$3,700.000
|
$2,500.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
2.000
|
$4,000.000
|
$4,725.000
|
$4,200.000
|
$4,550.000
|
$4,700.000
|
$2,700.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 30 IN)
|
EA
|
3.000
|
$5,000.000
|
$6,300.000
|
$5,250.000
|
$6,050.000
|
$6,400.000
|
$3,000.000
|
|
|
HEADWALL (CH-PW-0)(SPL)
|
EA
|
1.000
|
$80,000.000
|
$33,075.000
|
$23,100.000
|
$45,500.000
|
$33,000.000
|
$25,000.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
14.000
|
$1,000.000
|
$619.500
|
$735.000
|
$810.000
|
$620.000
|
$1,400.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
71.000
|
$800.000
|
$682.500
|
$735.000
|
$860.000
|
$690.000
|
$1,500.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
16.000
|
$1,300.000
|
$787.500
|
$787.500
|
$960.000
|
$800.000
|
$1,600.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$1,500.000
|
$997.500
|
$945.000
|
$1,010.000
|
$1,000.000
|
$1,800.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$2,000.000
|
$1,312.500
|
$2,625.000
|
$2,550.000
|
$1,300.000
|
$1,800.000
|
|
|
REMOV STR (SET)
|
EA
|
18.000
|
$500.000
|
$192.000
|
$367.500
|
$660.000
|
$700.000
|
$500.000
|
|
|
REMOV STR (HEADWALL)
|
EA
|
31.000
|
$1,000.000
|
$341.250
|
$525.000
|
$810.000
|
$350.000
|
$2,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
776.000
|
$20.000
|
$12.600
|
$12.600
|
$21.000
|
$11.000
|
$20.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$500,000.000
|
$420,000.000
|
$415,000.000
|
$416,090.000
|
$400,000.000
|
$550,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
12.000
|
$3,000.000
|
$2,115.000
|
$21,444.000
|
$1,300.000
|
$7,000.000
|
$7,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
442.000
|
$30.000
|
$36.230
|
$26.250
|
$35.000
|
$36.250
|
$33.450
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
442.000
|
$10.000
|
$9.450
|
$5.250
|
$9.100
|
$9.500
|
$7.440
|
|
|
CONSTRUCTION PERIMETER FENCE
|
LF
|
500.000
|
$3.500
|
$5.250
|
$5.250
|
$5.100
|
$5.000
|
$3.190
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
8,182.000
|
$3.000
|
$2.990
|
$5.250
|
$2.900
|
$3.000
|
$2.880
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
8,182.000
|
$1.000
|
$0.900
|
$1.050
|
$0.870
|
$0.900
|
$0.580
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (18")
|
LF
|
1,082.000
|
$5.000
|
$5.780
|
$7.350
|
$5.550
|
$5.750
|
$4.880
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
1,082.000
|
$1.000
|
$1.050
|
$1.580
|
$1.010
|
$1.000
|
$0.880
|
|
|
DRIVEWAYS (CONC)
|
SY
|
100.000
|
$100.000
|
$94.500
|
$89.250
|
$126.000
|
$130.000
|
$100.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
1,465.000
|
$50.000
|
$19.930
|
$35.750
|
$27.000
|
$25.000
|
$60.000
|
|
|
TURNOUTS (ACP)
|
SY
|
591.000
|
$40.000
|
$29.340
|
$123.000
|
$78.000
|
$36.000
|
$60.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
594.000
|
$9.500
|
$10.520
|
$70.000
|
$52.000
|
$20.000
|
$20.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
55,898.000
|
$0.150
|
$0.210
|
$0.550
|
$0.210
|
$0.150
|
$0.200
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
27,969.000
|
$0.150
|
$0.210
|
$0.650
|
$0.210
|
$0.300
|
$0.200
|
|
|
MTL W-BEAM GD FEN ADJUSTMENT
|
LF
|
25.000
|
$10.500
|
$13.130
|
$14.000
|
$12.550
|
$13.000
|
$15.000
|
|
|
MTL THRIE-BEAM GD FEN ADJUSTMENT
|
LF
|
20.000
|
$23.500
|
$26.250
|
$26.250
|
$25.100
|
$26.000
|
$35.000
|
|
|
GUARDRAIL END TREATMENT (MOVE & RESET)
|
EA
|
1.000
|
$1,500.000
|
$1,207.500
|
$1,207.500
|
$1,160.000
|
$1,200.000
|
$943.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
25.000
|
$250.000
|
$309.750
|
$169.050
|
$300.000
|
$310.000
|
$161.000
|
|
|
MAILBOX INSTALL-D (TWW-POST) TY 4
|
EA
|
8.000
|
$300.000
|
$309.750
|
$204.750
|
$300.000
|
$310.000
|
$195.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
3.000
|
$350.000
|
$603.750
|
$467.250
|
$580.000
|
$600.000
|
$445.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
9.000
|
$500.000
|
$498.750
|
$350.700
|
$480.000
|
$500.000
|
$334.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
3.000
|
$550.000
|
$519.750
|
$446.250
|
$500.000
|
$520.000
|
$425.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
26.000
|
$500.000
|
$414.750
|
$341.250
|
$398.000
|
$420.000
|
$325.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
12.000
|
$100.000
|
$99.750
|
$99.750
|
$96.000
|
$100.000
|
$95.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
13.000
|
$80.000
|
$56.700
|
$56.700
|
$55.000
|
$56.000
|
$48.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
2,806.000
|
$1.000
|
$1.000
|
$6.440
|
$1.600
|
$0.750
|
$1.820
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
|
LF
|
55,324.000
|
$0.300
|
$0.290
|
$0.380
|
$0.360
|
$0.300
|
$0.360
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
|
LF
|
1,030.000
|
$0.350
|
$0.420
|
$0.530
|
$0.390
|
$0.450
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
|
LF
|
51,440.000
|
$0.300
|
$0.290
|
$0.380
|
$0.360
|
$0.260
|
$0.360
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
108.000
|
$10.000
|
$13.860
|
$18.900
|
$12.100
|
$14.000
|
$18.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
687.000
|
$3.500
|
$3.780
|
$4.200
|
$3.550
|
$3.800
|
$4.000
|
|
|
EMULSION
|
GAL
|
194,490.000
|
$2.750
|
$2.600
|
$2.150
|
$1.950
|
$3.500
|
$3.000
|
|
|
CEMENT
|
TON
|
387.000
|
$170.000
|
$222.600
|
$163.000
|
$219.000
|
$210.000
|
$250.000
|
|
|
EMUL TRTMNT(MX EXST MTRL & NEW BASE) 8"
|
SY
|
97,245.000
|
$2.500
|
$2.000
|
$2.000
|
$2.350
|
$4.500
|
$3.500
|
|
|
D-GR HMA TY-C SAC-A PG70-22
|
TON
|
10,419.000
|
$95.000
|
$108.020
|
$98.000
|
$100.000
|
$110.000
|
$103.750
|
|
|
TACK COAT
|
GAL
|
9,462.000
|
$4.000
|
$2.940
|
$3.700
|
$4.250
|
$3.000
|
$3.000
|
|
|
TMA (STATIONARY)
|
DAY
|
180.000
|
$250.000
|
$75.000
|
$200.000
|
$270.000
|
$275.000
|
$200.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
16.000
|
$250.000
|
$100.000
|
$78.750
|
$101.000
|
$400.000
|
$400.000
|
|
Totals: |
$5,354,773.850
|
$4,497,777.470
|
$4,811,181.790
|
$5,047,918.190
|
$5,075,460.620
|
$5,953,995.130
|